Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Screwdrivers (Flat and Phillips) | Programmable Logic Controller (PLC) 12/24 V DC |
| Side Cutter | Mechatronic Arm with actuator |
| Multimeter | Push Button N.O (Green) |
| Hammer | Proximity Sensor (Inductive, N.O) |
| Indicator Bulb 75W, 240 VAC | |
| Bulb Holder | |
| DIN Rail 15 cm | |
| Single Core Cable 1.5 mm (Red, Black, Green) | |
| Power Supply 12/24 V DC | |
| Power Supply 240 V AC | |
| Mini Trunking | |
| Installation Board 1m x 0.5m | |
| Personal Protective Equipment (PPE) |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Programmable Logic Controller (PLC) 12/24 V DC | 1 Pc per Candidate |
| 2 | Mechatronic Arm with actuator | 1 Pc per Candidate |
| 3 | Push Button N.O (Green) | 1 Pc per Candidate |
| 4 | Proximity Sensor (Inductive, N.O) | 2 Pcs per Candidate |
| 5 | Indicator Bulb 75W, 240 VAC | 2 Pcs per Candidate |
| 6 | Bulb Holder | 2 Pcs per Candidate |
| 7 | DIN Rail 15 cm | 1 Pc per Candidate |
| 8 | Single Core Cable 1.5 mm (Red, Black, Green) | 3 Meters per Candidate |
| 9 | Power Supply 12/24 V DC | 1 Pc per Candidate |
| 10 | Power Supply 240 V AC | 1 Pc per Candidate |
| 11 | Mini Trunking | 1 Meter per Candidate |
| 12 | Multimeter | 1 Pc per Candidate |
| 13 | Screwdrivers (Flat and Phillips) | 1 Set per Candidate |
| 14 | Side Cutter | 1 Pc per Candidate |
| 15 | Installation Board 1m x 0.5m | 1 Pc per Candidate |
| 16 | Personal Protective Equipment (PPE): Overall/Dust Coat, Safety Boots | 1 Set per Candidate |
| 17 | Hammer | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Setup and Wiring | |||
| Wore personal protective equipment (Overall/Dust Coat and Safety Boots) (Award 1 mark for each PPE worn) | 2 | ||
| Observed electrical safety by disconnecting mains before wiring (Award 2 marks for correct safety procedure) | 2 | ||
| Used correct tools for wiring (Screwdrivers, Side Cutter, Multimeter) (Award 1 mark for correct tool use) | 3 | ||
| Installed components firmly and level on installation board (Award 2 marks for correct installation) | 2 | ||
| Correctly terminated and connected cables to PLC inputs and outputs (Award 4 marks for proper cable termination and connections) | 4 | ||
| Connected power supply lines (Live, Neutral, Earth) correctly (Award 1 mark per correct connection) | 3 | ||
| Tested circuit for short circuits using multimeter (Award 2 marks for correct testing) | 2 | ||
| Powered ON the PLC successfully (Award 1 mark for powering PLC) | 1 | ||
| Sub-Total | 19 | ||
| TASK 2: Programming the Mechatronic Arm | |||
| Opened correct PLC programming software and created new project (Award 2 marks for correct software use and project setup) | 2 | ||
| Developed I/O distribution list correctly (Award 2 marks for accurate I/O list) | 2 | ||
| Wrote ladder logic program to control start pushbutton, sensor inputs, and indicator bulbs (Award 8 marks for correct and functional ladder logic) | 8 | ||
| Documented code by commenting each rung’s function (Award 2 marks for clear code documentation) | 2 | ||
| Simulated or debugged program using PLC simulation tool (Award 3 marks for successful simulation/debug) | 3 | ||
| Set PLC to programming mode before downloading (Award 2 marks for correct mode setting) | 2 | ||
| Downloaded program to PLC and verified successful upload (Award 3 marks for correct download) | 3 | ||
| Set PLC to running mode after program download (Award 1 mark for correct mode switching) | 1 | ||
| Sub-Total | 23 | ||
| TASK 3: Testing and Operation | |||
| Connected power correctly and powered system ON (Award 1 mark for correct powering) | 1 | ||
| Operated system by pressing start pushbutton to power system and turn ON green indicator bulb (Award 1 mark for correct start operation) | 1 | ||
| Verified sensor 1 activates indicator bulb 1 which stays ON for 5 seconds then turns OFF (Award 2 marks for correct sensor 1 operation) | 2 | ||
| Verified sensor 2 activates indicator bulb 2 which remains ON until object is removed (Award 3 marks for correct sensor 2 operation) | 3 | ||
| Tested mechatronic arm motion control as per programmed sequence (Award 3 marks for correct arm motion operation) | 3 | ||
| Disconnected components following SOP (Award 1 mark for proper disconnection) | 1 | ||
| Stored tools, components, and accessories properly (Award 1 mark for proper storage) | 1 | ||
| Cleaned the work area (Award 1 mark for housekeeping) | 1 | ||
| Sub-Total | 13 | ||
| PRODUCT CHECKLIST | |||
| Program correctly controls start, sensor inputs, and indicator bulbs as per specifications (Award 5 marks for fully functional program) | 5 | ||
| Mechatronic arm moves accurately according to the programmed motion sequence (Award 5 marks for correct arm motion control) | 5 | ||
| Wiring and component installation is neat, firm, and safe (Award 3 marks for neat and safe installation) | 3 | ||
| Code is well documented and easy to understand (Award 2 marks for code documentation) | 2 | ||
| System operates without faults or errors during testing (Award 5 marks for faultless operation) | 5 | ||
| Sub-Total | 20 | ||
| GRAND TOTAL | 75 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Multi-meter | Normally Open (N.O) Push Button Green |
| Side Cutter | Proximity Sensor (Inductive, N.O) |
| Screwdrivers | Indicator Bulb 75W, 240VAC |
| Hammer | Bulb Holders |
| Programmable Logic Controller (PLC) 12/24 VDC | |
| Terminal Blocks | |
| DIN Rail 15 cm | |
| Installation Board 1 m x 0.5 m | |
| Single Core Cable Red, Black, Green 1.5 mm² | |
| Power Supply 12/24 VDC | |
| Power Supply 240 VAC | |
| Mini Trunking 1 Meter | |
| Tuck Nails | |
| Equipment Labels | |
| Personal Protective Equipment (PPE) Overall/Dust Coat, Safety Boots |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Normally Open (N.O) Push Button Green | 1 Pc per Candidate |
| 2 | Proximity Sensor (Inductive, N.O) | 2 Pcs per Candidate |
| 3 | Indicator Bulb 75W, 240VAC | 2 Pcs per Candidate |
| 4 | Bulb Holders | 2 Pcs per Candidate |
| 5 | Programmable Logic Controller (PLC) 12/24 VDC | 1 Pc per Candidate |
| 6 | Terminal Blocks | 1 Set per Candidate |
| 7 | DIN Rail 15 cm | 1 Pc per Candidate |
| 8 | Installation Board 1 m x 0.5 m | 1 Pc per Candidate |
| 9 | Single Core Cable Red, Black, Green 1.5 mm² | 3 Meters per Candidate |
| 10 | Power Supply 12/24 VDC | 1 Pc per Candidate |
| 11 | Power Supply 240 VAC | 1 Pc per Candidate |
| 12 | Multi-meter | 1 Pc per Candidate |
| 13 | Side Cutter | 1 Pc per Candidate |
| 14 | Screwdrivers (Flat and Phillips) | 1 Set per Candidate |
| 15 | Hammer | 1 Pc per Candidate |
| 16 | Personal Protective Equipment (PPE) Overall/Dust Coat, Safety Boots | 1 Set per Candidate |
| 17 | Mini Trunking 1 Meter | 1 Pc per Candidate |
| 18 | Tuck Nails | 10 Pcs per Candidate |
| 19 | Equipment Labels | 1 Set per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Installation and wiring of components | |||
| Wore personal protective gear: overall/dust coat and safety boots (Award 1 mark each for overall/dust coat and safety boots) | 2 | ||
| Observed electrical safety rules: disconnected from mains before wiring (Award 2 marks for proper disconnection before wiring) | 2 | ||
| Correctly identified and fixed components firmly and level on installation board (Award 2 marks each for correct fixing of PLC and sensors/bulbs) | 4 | ||
| Properly terminated cables: firm connections, folded neatly, no nicks (Award 2 marks for neat and correct cable termination) | 2 | ||
| Correctly connected PLC inputs and outputs as per I/O distribution (Award 1 mark each for correct connection of push button, two sensors, and two bulbs) | 4 | ||
| Used correct tools for wiring and assembly (Award 1 mark each for correct use of screwdrivers, side cutter, hammer) | 3 | ||
| Sub-Total | 17 | ||
| TASK 2: Development and upload of PLC program | |||
| Developed detailed I/O distribution list for sensors, push button, bulbs (Award 2 marks for complete and correct I/O list) | 2 | ||
| Opened PLC programming software and started new project with correct PLC model (Award 2 marks for correct software and PLC setup) | 2 | ||
| Developed ladder logic program integrating sensor inputs to control bulbs with timing delays (Award 8 marks for correct and functional ladder logic) | 8 | ||
| Documented code with comments explaining each rung (Award 2 marks for clear and complete documentation) | 2 | ||
| Debugged and simulated program using PLC simulation tool (Award 3 marks for successful debugging and simulation) | 3 | ||
| Set PLC to programming mode before uploading (Award 2 marks for correct mode selection) | 2 | ||
| Connected programming cable and established communication with PLC (Award 2 marks for correct cable connection and communication) | 2 | ||
| Downloaded program to PLC and set to running mode (Award 3 marks for correct download and mode setting) | 3 | ||
| Sub-Total | 24 | ||
| TASK 3: Testing, operation and housekeeping | |||
| Powered the system correctly with 12/24 VDC and 240 VAC supplies (Award 1 mark for correct power connection) | 1 | ||
| Tested system operation: pushbutton starts system; sensor 1 turns on indicator bulb 1 for 5 seconds; sensor 2 turns on indicator bulb 2 until object removal (Award 1 mark for each correct operation step) | 5 | ||
| Disconnected components following standard operating procedures (Award 1 mark for proper disconnection) | 1 | ||
| Properly stored tools, components, and accessories (Award 1 mark for correct storage) | 1 | ||
| Cleaned the work area after completion (Award 1 mark for cleanliness) | 1 | ||
| Sub-Total | 9 | ||
| PRODUCT CHECKLIST | |||
| Installation board setup with components fixed firmly, cables neatly terminated and connected as per I/O distribution (Award 5 marks for firm fixing, neat wiring, and correct connections) | 5 | ||
| Programmed ladder logic matches required sensor-actuator sequence with timing delays (Award 7 marks for correct and functional program) | 7 | ||
| Sub-Total | 12 | ||
| GRAND TOTAL | 62 | ||