By the end of this chapter, you will be able to:
- prepare an abstracting sheet correctly using the standard format
- transfer the description of booked items accurately to the quantities abstracting sheet following SOPs
- accurately transfer squared quantities to the abstracting sheet following the correct procedure
- calculate net quantities correctly following standard operating procedures
- carry out running through dimensions accurately following standard operating procedures
Mastering these skills will help you measure civil works precisely, ensuring your work is reliable and trusted in the construction trade.
Quantity Survey professionals in Kenya rely heavily on accurate measurement and systematic recording of civil works to ensure precise costing and project control. Abstracting measured quantities is a critical step that involves summarizing detailed measurements into concise, organized sheets for valuation and tendering purposes. This chapter focuses on the preparation and use of abstracting sheets and the process of running through dimensions, both essential skills for effective quantity surveying in civil engineering projects.
The preparation of an abstracting sheet involves systematically organizing measured items into a clear, concise format that facilitates easy calculation and verification. The abstracting sheet acts as a bridge between detailed field measurements and the final bill of quantities, ensuring that quantities are neither duplicated nor omitted.
The general formula for total quantity calculation on an abstracting sheet is:
$$ Q_{total} = \sum_{i=1}^n Q_i $$
where \(Q_i\) represents individual measured quantities for each item.
Example 1: A quantity surveyor measures the length of a retaining wall as 30 m, with a consistent thickness of 0.3 m and height of 2.5 m. Calculate the total volume to be abstracted onto the sheet.
Given:
Length \(L = 30\, m\), Thickness \(T = 0.3\, m\), Height \(H = 2.5\, m\)
$$ Q = L \times T \times H $$
$$ Q = 30 \times 0.3 \times 2.5 $$
$$ Q = 22.5\, m^3 $$
Answer: 22.5 m³
Example 2: A slab has been measured as 15 m by 10 m with a thickness of 0.15 m. Determine the quantity to record on the abstracting sheet.
Given:
Length \(L = 15\, m\), Width \(W = 10\, m\), Thickness \(T = 0.15\, m\)
$$ Q = L \times W \times T $$
$$ Q = 15 \times 10 \times 0.15 $$
$$ Q = 22.5\, m^3 $$
Answer: 22.5 m³
Example 3: A trench for foundation footing is measured as 50 m long, 0.6 m wide, and 1.2 m deep. Calculate the abstracted quantity.
Given:
Length \(L = 50\, m\), Width \(W = 0.6\, m\), Depth \(D = 1.2\, m\)
$$ Q = L \times W \times D $$
$$ Q = 50 \times 0.6 \times 1.2 $$
$$ Q = 36\, m^3 $$
Answer: 36 m³
Example 4: A column has a square cross-section measuring 0.4 m by 0.4 m and a height of 3 m. Determine the quantity to abstract.
Given:
Cross-section \(0.4\, m \times 0.4\, m\), Height \(H = 3\, m\)
$$ Q = 0.4 \times 0.4 \times 3 $$
$$ Q = 0.16 \times 3 $$
$$ Q = 0.48\, m^3 $$
Answer: 0.48 m³
Example 5: A concrete beam is 6 m long with a rectangular cross-section 0.3 m wide and 0.5 m deep. Calculate the quantity for abstraction.
Given:
Length \(L = 6\, m\), Width \(W = 0.3\, m\), Depth \(D = 0.5\, m\)
$$ Q = L \times W \times D $$
$$ Q = 6 \times 0.3 \times 0.5 $$
$$ Q = 0.9\, m^3 $$
Answer: 0.9 m³
Example 6: A slab for the main entrance of the Nairobi City County Hall is measured as 20 m by 12 m with a thickness of 0.2 m. Calculate the quantity to record on the abstracting sheet.
Given:
Length \(L = 20\, m\), Width \(W = 12\, m\), Thickness \(T = 0.2\, m\)
$$ Q = L \times W \times T $$
$$ Q = 20 \times 12 \times 0.2 $$
$$ Q = 48\, m^3 $$
Answer: 48 m³
Example 7: A column for the Kenya Revenue Authority headquarters has a rectangular cross-section measuring 0.5 m by 0.3 m and a height of 4 m. Determine the quantity to abstract.
Given:
Cross-section \(0.5\, m \times 0.3\, m\), Height \(H = 4\, m\)
$$ Q = 0.5 \times 0.3 \times 4 $$
$$ Q = 0.15 \times 4 $$
$$ Q = 0.6\, m^3 $$
Answer: 0.6 m³
Transferring booked quantities from measurement books to the abstracting sheet requires accuracy and consistency to avoid errors in project costing. The process involves consolidating individual measurements into summary quantities, ensuring each item is correctly identified and recorded.
The total abstracted quantity for an item is:
$$ Q_{abstracted} = \sum_{j=1}^m Q_{booked_j} $$
where \(Q_{booked_j}\) are individual booked quantities.
Example 1: A measurement book contains three entries for excavation: 5 m³, 7 m³, and 8 m³. Calculate the total quantity to transfer to the abstracting sheet.
Given:
\(Q_1=5\, m^3\), \(Q_2=7\, m^3\), \(Q_3=8\, m^3\)
$$ Q_{abstracted} = 5 + 7 + 8 $$
$$ Q_{abstracted} = 20\, m^3 $$
Answer: 20 m³
Example 2: Concrete measurements for a slab are recorded as 10.5 m³, 12.3 m³, and 9.7 m³. Determine the total quantity to transfer.
Given:
\(Q_1=10.5\, m^3\), \(Q_2=12.3\, m^3\), \(Q_3=9.7\, m^3\)
$$ Q_{abstracted} = 10.5 + 12.3 + 9.7 $$
$$ Q_{abstracted} = 32.5\, m^3 $$
Answer: 32.5 m³
Example 3: Steel reinforcement bar quantities booked are 150 kg, 200 kg, and 180 kg. Find the total quantity to transfer.
Given:
\(Q_1=150\, kg\), \(Q_2=200\, kg\), \(Q_3=180\, kg\)
$$ Q_{abstracted} = 150 + 200 + 180 $$
$$ Q_{abstracted} = 530\, kg $$
Answer: 530 kg
Example 4: Measurements for wall plastering are 25 m², 30 m², and 28 m². Calculate the abstracted quantity.
Given:
\(Q_1=25\, m^2\), \(Q_2=30\, m^2\), \(Q_3=28\, m^2\)
$$ Q_{abstracted} = 25 + 30 + 28 $$
$$ Q_{abstracted} = 83\, m^2 $$
Answer: 83 m²
Example 5: Measurements for formwork are recorded as 40 m², 35 m², 45 m², and 30 m². Determine the total quantity.
Given:
\(Q_1=40\, m^2\), \(Q_2=35\, m^2\), \(Q_3=45\, m^2\), \(Q_4=30\, m^2\)
$$ Q_{abstracted} = 40 + 35 + 45 + 30 $$
$$ Q_{abstracted} = 150\, m^2 $$
Answer: 150 m²
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter focused on the process of abstracting measured quantities in civil works. It began with the preparation of the abstracting sheet, detailing how to organize and set up the sheet for efficient recording of measurements. The transfer of booked quantities to the abstracting sheet was explained to ensure accuracy and consistency. The chapter then covered running through dimensions, introducing the standard symbols used for this step to facilitate clear communication of measurements. Next, casting up dimensions was discussed, including the specific symbols employed to summarize and verify the measurements taken. Finally, the calculation of net quantities was explored, demonstrating how to derive the final values needed for billing or further analysis. Throughout, emphasis was placed on precision and correct notation to maintain the integrity of the measurement process.
A rectangular slab measures 6 m by 4 m with a thickness of 0.15 m. Calculate the volume of concrete to be abstracted. (2 marks)
A wall 10 m long, 3 m high, and 0.2 m thick is to be measured. Compute the net quantity of masonry in cubic metres. (2 marks)
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape 5m | Graph paper A4 size |
| Calculator | Project measurements sheet |
| Ruler 300mm | Abstracting sheet template |
| Pens | |
| Clipboard |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape 5m | 1 Pc per Candidate |
| 2 | Calculator | 1 Pc per Candidate |
| 3 | Ruler 300mm | 1 Pc per Candidate |
| 4 | Graph paper A4 size | 2 Sheets per Candidate |
| 5 | Pens (blue and red) | 2 Pcs per Candidate |
| 6 | Clipboard | 1 Pc per Candidate |
| 7 | Project measurements sheet | 1 Set per Candidate |
| 8 | Abstracting sheet template | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: PREPARATION AND ABSTRACTING | |||
| Used appropriate PPE (helmet, safety boots, reflective vest) (Award 1 mark for each correctly worn PPE) | 3 | ||
| Assembled all necessary tools and materials before starting (Award 2 marks for assembling all required items) | 2 | ||
| Reviewed the project measurements sheet accurately (Award 3 marks for thorough review without errors) | 3 | ||
| Measured and verified given dimensions on the site plan (Award 1 mark for each correct measurement verification, total 4 marks) | 4 | ||
| Calculated quantities of concrete, formwork, and reinforcement bars correctly (Award 1 mark for each correct calculation step, total 6 marks) | 6 | ||
| Entered all data accurately into the abstracting sheet template (Award 1 mark for each correctly entered category, total 4 marks) | 4 | ||
| Presented the abstracting sheet in a neat, legible, and organized format (Award 3 marks for overall neatness and clarity) | 3 | ||
| Cross-checked all entries for arithmetic and transcription errors (Award 3 marks for complete and accurate cross-checking) | 3 | ||
| Sub-Total | 28 | ||
| PRODUCT CHECKLIST | |||
| Abstracting sheet correctly details concrete volume for a 15000mm x 6000mm slab with 150mm thickness (+/- 5% tolerance) (Award 5 marks for correct concrete volume within tolerance) | 5 | ||
| Formwork area accurately calculated and recorded for all slab edges and sides (Award 4 marks for accurate formwork quantities) | 4 | ||
| Reinforcement bar lengths and quantities correctly abstracted as per project details (Award 5 marks for correct reinforcement abstraction) | 5 | ||
| All abstracted quantities summarized clearly with correct units and totals (Award 3 marks for clear summary presentation) | 3 | ||
| Abstracting sheet free from calculation and transcription errors (Award 5 marks for error-free document) | 5 | ||
| Sub-Total | 22 | ||
| GRAND TOTAL | 50 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measurement Book | Abstracting Sheet (standard format) |
| Calculator | |
| Ruler 30 cm | |
| Ballpoint Pen | |
| Clipboard |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measurement Book | 1 Pc per Candidate |
| 2 | Abstracting Sheet (standard format) | 1 Pc per Candidate |
| 3 | Calculator | 1 Pc per Candidate |
| 4 | Ballpoint Pen | 1 Pc per Candidate |
| 5 | Ruler 30 cm | 1 Pc per Candidate |
| 6 | Desk or Table for writing | 1 per 4 Candidates |
| 7 | Clipboard | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: PROCESS OF TRANSFERRING BOOKED QUANTITIES | |||
| Identified and used appropriate PPE (helmet, safety boots, reflective vest) (Award 1 mark each for any correct PPE used) | 3 | ||
| Assembled all required tools and materials correctly before starting (Award 2 marks for assembling all listed tools and materials) | 2 | ||
| Carefully read and interpreted the booked quantities in the measurement book (Award 3 marks for accurate interpretation without errors) | 3 | ||
| Entered the booked quantities correctly into the corresponding columns and rows on the abstracting sheet (Award 1 mark for each correctly transferred item, total 6 marks) | 6 | ||
| Calculated and summarized total quantities where applicable, showing working (Award 4 marks for correct calculations and neat presentation) | 4 | ||
| Cross-checked transferred data against measurement book for accuracy (Award 2 marks for complete and accurate cross-checking) | 2 | ||
| Maintained neatness and legibility throughout the abstracting sheet (Award 2 marks for neat, legible and organized presentation) | 2 | ||
| Properly stored tools and materials after completion (Award 2 marks for correct cleaning and storing) | 2 | ||
| Sub-Total | 24 | ||
| PRODUCT CHECKLIST | |||
| All booked quantities correctly transferred with no omissions or errors (Award 6 marks for 100% correct transfer) | 6 | ||
| Abstracting sheet totals and summaries are accurate and match measurement book (Award 5 marks for accurate totals) | 5 | ||
| Presentation of the abstracting sheet is neat, clear, and well-organized (Award 5 marks for neatness and clarity) | 5 | ||
| Completed abstracting sheet meets standard formats and conventions (Award 4 marks for adherence to standard abstracting sheet format) | 4 | ||
| Sub-Total | 20 | ||
| GRAND TOTAL | 44 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.