By the end of this chapter, you will be able to:
Mastering these skills will help you measure building works precisely, ensuring your work is reliable and valued in the construction trade.
Abstracting measured quantities is a critical step in the Quantity Surveying process, enabling the efficient compilation of detailed measurements into manageable summaries. This chapter focuses on the preparation and use of abstracting sheets, essential for organizing measurements before pricing and valuation. It also covers the technique of running through dimensions, a method used to verify and cross-check measurements for accuracy and consistency in building works.
The abstracting sheet records quantities measured from drawings or site measurements and groups them logically. There is no mathematical formula but a standardized format is followed.
Example 1: Preparing an abstracting sheet for wall plastering quantities
Given: Wall plaster area measured as 120 m², window openings 4 m² to be deducted
Abstracting sheet entry: Plastering area = 116 m²
Example 2: Abstracting concrete volume for a beam
Given: Beam dimensions, length 6 m, width 0.3 m, depth 0.5 m
Abstracting sheet entry: Concrete volume = 0.9 m³
Example 3: Abstracting quantities for floor finishes
Given: Floor area 80 m², 10% wastage allowance
Abstracting sheet entry: Floor finish = 88 m²
Kenyan Context Note:
In practice, abstracting sheets are commonly used by Kenyan construction firms such as Epco Builders Ltd and government agencies like the State Department for Public Works. For example, when preparing an abstracting sheet for a project at Kenyatta National Hospital, the measured quantities would be grouped and summarized in the same way as shown above.
Transferring booked quantities from measurement books to abstracting sheets requires accuracy and verification to prevent discrepancies in costing.
The transfer process is a systematic transcription of quantities without change, but cross-checking totals is essential.
Example 1: Transferring wall blockwork quantity
Given: Blockwork measured as 50 m² in measurement book
Abstracting sheet entry: Blockwork = 50 m²
Example 2: Transferring excavation volume
Given: Excavation volume measured as 12 m³
Abstracting sheet entry: Excavation = 12 m³
Example 3: Transferring steel reinforcement weight
Given: Reinforcement measured as 150 kg
Abstracting sheet entry: Steel reinforcement = 150 kg
Kenyan Context Note:
For instance, in projects managed by the National Construction Authority (NCA), transferring booked quantities from site measurement books to abstracting sheets is a standard procedure to ensure accuracy in the Bills of Quantities for public infrastructure works such as roads and schools.
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter covers the process of abstracting measured quantities in building works, starting with the preparation of the abstracting sheet, which organizes all relevant data systematically for clarity and accuracy. It explains how to transfer booked quantities onto the abstracting sheet to ensure consistency between measurement and costing. The chapter then discusses running through dimensions, detailing the symbols commonly used to represent various measurements and ensure precise communication. Following that, it addresses the casting up of dimensions, including the specific symbols applied during this stage to consolidate measurements effectively. Finally, the chapter explains the calculation of net quantities by accurately summing and adjusting the measured data to reflect the true quantities required for construction. Together, these topics provide a comprehensive guide for managing and interpreting measurement data in building projects.
A slab measures 6 m by 4 m and is 0.15 m thick. Calculate the volume of concrete required. (2 marks)
A wall is 10 m long, 3 m high, and 0.3 m thick. Calculate the net quantity of bricks required if the brickwork accounts for 85% of the wall volume after accounting for openings. (3 marks)
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape (5m) | Project Drawings (Measured Quantities Sheet) |
| Calculator | Abstracting Sheet Template |
| Ruler (30cm) | Graph Paper A4 |
| Set Square | |
| Pens |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape (5m) | 1 Pc per Candidate |
| 2 | Calculator | 1 Pc per Candidate |
| 3 | Graph Paper A4 | 3 Sheets per Candidate |
| 4 | Pens | 2 Pcs per Candidate |
| 5 | Ruler (30cm) | 1 Pc per Candidate |
| 6 | Set Square | 1 Pc per Candidate |
| 7 | Project Drawings (Measured Quantities Sheet) | 1 Set per Candidate |
| 8 | Abstracting Sheet Template | 1 Sheet per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: PREPARATION OF ABSTRACTING SHEET | |||
| Identified and wore appropriate PPE (helmet, safety boots, reflective jacket) (Award 1 mark for each correct PPE used) | 3 | ||
| Assembled all required tools and materials correctly (Award 2 marks for assembling all listed tools and materials) | 2 | ||
| Interpreted the project measurements accurately from the provided drawings (Award up to 5 marks for correct interpretation of measurements) | 5 | ||
| Calculated quantities of concrete for footing correctly with 5% tolerance (Award 6 marks for correct volume calculations within tolerance) | 6 | ||
| Calculated quantities of walling materials accurately (Award 6 marks for accurate walling quantities) | 6 | ||
| Recorded all abstracted quantities neatly and clearly on the abstracting sheet template (Award 3 marks for neatness and completeness of recording) | 3 | ||
| Checked calculations for accuracy and corrected errors where applicable (Award 3 marks for evidence of checking and corrections) | 3 | ||
| Sub-Total | 28 | ||
| PRODUCT CHECKLIST | |||
| Abstracting sheet includes all required items: concrete footing, walling, reinforcement quantities (Award 5 marks for completeness of abstracted items) | 5 | ||
| Quantities match the given measurements within allowable tolerances (+/-5%) (Award 7 marks for accuracy of abstracted quantities) | 7 | ||
| Abstracting sheet is presented in a clear, logical format and free from calculation errors (Award 5 marks for clarity and error-free presentation) | 5 | ||
| Sub-Total | 17 | ||
| GRAND TOTAL | 45 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape (5m) | Abstracting Sheet (Pre-printed) |
| Calculator | |
| Pencil | |
| Ruler (30cm) | |
| Clipboard | |
| Eraser |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape (5m) | 1 Pc per Candidate |
| 2 | Calculator | 1 Pc per Candidate |
| 3 | Pencil | 2 Pcs per Candidate |
| 4 | Ruler (30cm) | 1 Pc per Candidate |
| 5 | Abstracting Sheet (Pre-printed) | 1 Sheet per Candidate |
| 6 | Clipboard | 1 Pc per Candidate |
| 7 | Eraser | 1 Pc per Candidate |
| 8 | Protective Gloves | 1 Pair per Candidate |
| 9 | Hard Hat | 1 Pc per Candidate |
| 10 | Safety Boots | 1 Pair per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: PROCESS AND ACCURACY OF TRANSFER | |||
| Wore appropriate PPE including hard hat, safety boots, and gloves (Award 1 mark each for correctly worn PPE) | 3 | ||
| Assembled all necessary tools and materials before starting (Award 2 marks for assembling all required tools and materials) | 2 | ||
| Read and interpreted booked quantities correctly from original booking sheets (Award 1 mark for each correctly read quantity; 4 quantities total) | 4 | ||
| Used measuring tape and calculator accurately to verify quantities (Award 1 mark for correct use of measuring tape; 2 marks for correct calculator use) | 3 | ||
| Transferred quantities to abstracting sheet neatly and legibly (Award 4 marks for complete and neat transfer with no errors) | 4 | ||
| Checked transferred data for accuracy before submission (Award 2 marks for correct verification and correction of errors) | 2 | ||
| Cleaned and stored tools appropriately after completion (Award 1 mark each for cleaning and proper storing) | 2 | ||
| Sub-Total | 20 | ||
| PRODUCT CHECKLIST | |||
| Abstracting sheet contains all booked quantities correctly transferred with no omissions (Award 6 marks for 100% correct transfer; lesser marks for partial correctness) | 6 | ||
| Quantities match original booking sheet within ±2% tolerance (Award 6 marks for all quantities within tolerance) | 6 | ||
| Sheet is neat, legible, and organized according to abstracting sheet format (Award 4 marks for neatness and proper organization) | 4 | ||
| Final submission is complete and ready for use in costing or procurement (Award 4 marks for completeness and readiness) | 4 | ||
| Sub-Total | 20 | ||
| GRAND TOTAL | 40 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.