Chapter 2: Take off quantities
📚 4 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • Prepare a neat and clear dimension sheet or paper using the standard quantities format.
  • Create a detailed list of quantities to measure based on the specific building items involved.
  • Calculate quantities of building elements accurately using the correct units of measurement.
  • Record all dimensions correctly by following the key principles of measurement.
  • Describe booked items clearly and correctly using the standard method of measurement (SMM) for building and civil works.

These skills will help you work confidently and accurately in the building trade, ensuring projects are measured and planned properly for success.

Measurement of building works requires precise preparation before quantities takeoff to ensure accuracy and efficiency in cost estimation and project planning. Quantity Surveyors in Kenya must follow a systematic checklist to avoid omissions and errors that can lead to financial losses or project delays. This chapter focuses on developing a comprehensive preparation of quantities checklist, essential for the professionalism and reliability demanded by Kenyan construction projects.

2.1 Preparation of quantities checklist

Preparation of quantities involves organizing all relevant documents, drawings, and tools before commencing the measurement process. A well-structured checklist guides the Quantity Surveyor through critical steps to ensure completeness and accuracy in the takeoff exercise. This systematic approach helps manage time, reduce errors, and enhances communication with other project stakeholders such as contractors, architects, and engineers.

2.1.1 Identification of project documents

Before any measurement begins, the Quantity Surveyor must identify and collect all necessary project documents. These documents form the foundation for accurate quantity assessment.

Key project documents include:

  • Architectural drawings: Provide detailed plans, elevations, and sections necessary for dimensional measurements.
  • Structural drawings: Show load-bearing elements and reinforcement details critical for structural quantity takeoff.
  • Mechanical and electrical drawings: Include specifications for installations that affect building works quantities.
  • Specifications: Contain qualitative descriptions that clarify material types and workmanship standards.
  • Bill of Quantities (BOQ) from previous stages: Useful for cross-referencing and ensuring consistency.
  • Contract documents: Define the scope and conditions affecting measurement scope and methods.

2.1.2 Verification of drawing scales and revisions

Accurate measurement depends on the correct interpretation of drawing scales and awareness of any revisions.

  • Confirm drawing scale: Check the scale noted on drawings (e.g., 1:100, 1:50) to ensure measurements correspond correctly.
  • Use scale rulers appropriate for the drawing scale: This avoids scaling errors.
  • Check for latest revisions: Verify that drawings are the most recent versions to prevent measuring obsolete designs.
  • Record revision dates and numbers: Important for traceability and audit.
  • Understand drawing symbols and abbreviations: Ensures correct interpretation of measured elements.

2.1.3 Setting up measurement tools and software

Modern quantity surveying integrates manual and digital tools for efficiency and accuracy.

Name Specification Use
Scale ruler Plastic or metal, scales 1:50, 1:100 For manual measurement from drawings
Digital planimeter Accuracy ±0.1%, compatible with prints Measures irregular areas on drawings
Quantity surveying software Compatible with CAD/BIM files For digital takeoff and data management
  • Calibrate scale rulers before use to maintain accuracy.
  • Ensure digital tools are loaded with latest project files.
  • Backup data regularly to prevent loss.
  • Train users on software features to optimize use.
  • Maintain tools clean and free from damage.

2.1.4 Organizing measurement workflow and records

A clear workflow and record-keeping system prevent confusion and facilitate verification.

  • Develop a measurement plan: Sequence measurement tasks logically by work sections or trade.
  • Use standard measurement sheets or software templates: Ensures uniformity.
  • Record measurements clearly with units and references: Avoids ambiguity.
  • Cross-check measurements with team members: Enhances accuracy.
  • File documentation systematically: Supports easy retrieval and audit.

Practice Questions

  1. A Quantity Surveyor is given architectural drawings at scale 1:100. If a wall length measures 7 cm on the drawing, calculate the actual wall length in meters. (3 marks)
  2. Identify five essential project documents a Quantity Surveyor must gather before starting quantity takeoff for a hospital construction project. (5 marks)
  3. A digital planimeter shows an area of 3500 cm² on a drawing scaled at 1:50. Calculate the actual area in square meters. (4 marks)
  4. List six steps in organizing a measurement workflow for a retail building project. (6 marks)
The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒2.2 Take off of Building Works

The take off of building works is a critical process in quantity surveying where quantities of various elements and components of a building are measured and recorded for costing and procurement purposes. Kenyan quantity surveyors must accurately measure build…

🔒2.3 Booking of dimensions

Booking of dimensions in quantity surveying involves the systematic recording of measurements taken from drawings or site works. This process is crucial for producing accurate bills of quantities (BoQs) and ensuring correct valuation of building works. In the…

🔒2.4 Booked items description

The description of booked items in quantity surveying must be precise and comprehensive to facilitate correct interpretation during tendering and construction. In Kenya, clear item descriptions ensure all parties understand the scope and specifications, reduci…

Chapter Summary

This chapter covers the essential process of preparing a quantities checklist as a foundation for accurate measurement of building works. It explains the take off of building works in various categories including framed structures, drainage works, external works, services, fixings and fixtures, as well as plumbing works, emphasizing the specific considerations for each. The chapter highlights the importance of careful booking of dimensions to ensure precision and consistency throughout the measurement process. It also details how to properly describe booked items to maintain clarity and facilitate correct interpretation by all stakeholders. By following these steps, quantity surveyors and construction professionals can achieve reliable and comprehensive quantity take-offs that support effective project planning and cost control. The chapter integrates practical techniques to enhance accuracy and efficiency in measurement tasks across diverse construction elements.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

Written Assessment

  1. A beam in a framed structure measures 6 m in length, 0.3 m in width, and 0.5 m in depth. Calculate the volume of concrete required for the beam. (2 marks)

  2. A drainage trench is 50 m long, 0.6 m wide, and 0.8 m deep. Determine the volume of earthworks required to excavate the trench. (2 marks)

🔒18 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Explain the purpose of a quantities checklist in the preparation of a bill of quantities for a commercial office block in Nairobi. (4 marks)
  2. Describe the key measurements required in the take off of framed structures using reinforced concrete beams and columns. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Prepare Quantities Checklist for a Single-Storey Residential Building

Quantity Survey · Level 6
Measurement Of Building Works III
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Prepare a comprehensive quantities checklist for a single-storey residential building measuring 12,000mm length x 9,000mm width.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring Tape (5m)Notebook
Calculator
Graph Paper A4
Pens
Ruler (30 cm)
Working Drawing (Single-storey residential building)
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Measuring Tape (5m)1 Pc per Candidate
2Calculator1 Pc per Candidate
3Graph Paper A45 Sheets per Candidate
4Pens2 Pcs per Candidate
5Ruler (30 cm)1 Pc per Candidate
6Working Drawing (Single-storey residential building)1 Set per Candidate
7Notebook1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: PREPARATION OF QUANTITIES CHECKLIST
Identified and used appropriate PPEs as per safety regulations
(Award 1 mark for each appropriate PPE worn)
3
Assembled all required tools and materials before commencing work
(Award 2 marks for assembling at least five tools/materials)
2
Accurately interpreted the working drawing and dimensions
(Award 1 mark per correct interpretation of length, width, and key elements)
5
Measured and recorded all relevant dimensions correctly
(Award 1 mark for each correctly measured dimension up to five)
5
Calculated quantities for major materials including cement, sand, ballast, reinforcement bars, and timber
(Award 2 marks per correctly calculated material quantity)
8
Organized the quantities checklist in a clear, logical format
(Award 1 mark each for clarity, completeness, and neatness)
3
Cross-checked calculations and entries for accuracy
(Award 1 mark per verified calculation or entry)
4
Cleaned and stored tools and materials after use
(Award 1 mark each for cleaning and proper storing)
2
Sub-Total32
PRODUCT CHECKLIST
Quantities checklist includes all materials with correct calculated amounts within ±5% tolerance
(Award 2 marks for each major material correctly quantified)
10
Checklist is well presented, legible, and logically arranged
(Award 5 marks for neatness, completeness, and presentation)
5
Dimensions used in calculations match the working drawing dimensions (12,000mm x 9,000mm)
(Award 3 marks for accurate dimension usage)
3
Sub-Total18
GRAND TOTAL50
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Take Off Quantities for a Single Storey Wall

Quantity Survey · Level 6
Measurement Of Building Works III
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Take off quantities for a 3000mm long, 2400mm high, 230mm thick masonry wall.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring Tape (5m)Working Drawing (Wall Layout)
Spirit LevelNotepad
Builder's Square
Plumb Bob
Pencils
Calculator
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Measuring Tape (5m)1 Pc per Candidate
2Spirit Level1 Pc per Candidate
3Builder's Square1 Pc per 4 Candidates
4Plumb Bob1 Pc per Candidate
5Pencils2 Pcs per Candidate
6Notepad1 Pc per Candidate
7Calculator1 Pc per Candidate
8Working Drawing (Wall Layout)1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: TAKE OFF AND BOOKING OF DIMENSIONS
Used appropriate PPE as per safety regulations
(Award 1 mark for each correct PPE used)
3
Assembled all required tools and materials before starting
(Award 0.5 marks for each tool/material assembled, max 2 marks)
2
Measured wall length accurately within +50 mm tolerance
(Award full marks for correct measurement, zero otherwise)
3
Measured wall height accurately within +50 mm tolerance
(Award full marks for correct measurement, zero otherwise)
3
Measured wall thickness accurately as 230 mm ± 10 mm
(Award full marks for correct measurement, zero otherwise)
2
Checked and recorded squareness using builder's square
(Award 2 marks if squareness checked and recorded correctly)
2
Checked and recorded verticality using plumb bob
(Award 2 marks if verticality checked and recorded correctly)
2
Booked all measurements neatly and clearly in notepad
(Award 1 mark each for length, height, thickness booking)
3
Calculated and recorded quantities for bricks and mortar
(Award 5 marks for correct quantity calculations with working shown)
5
Cleaned and stored tools and working area after task completion
(Award 1 mark for cleaning tools, 1 mark for cleaning area, 1 mark for proper storage)
3
Sub-Total28
PRODUCT CHECKLIST
Recorded wall length matches 3000 mm ± 50 mm
(Award 3 marks for correct length within tolerance)
3
Recorded wall height matches 2400 mm ± 50 mm
(Award 3 marks for correct height within tolerance)
3
Recorded wall thickness matches 230 mm ± 10 mm
(Award 2 marks for correct thickness within tolerance)
2
Quantity take off for bricks is accurate within 5% error margin
(Award 5 marks for correct brick quantity calculation)
5
Quantity take off for mortar is accurate within 5% error margin
(Award 4 marks for correct mortar quantity calculation)
4
Layout measurements demonstrate correct squareness and verticality
(Award 3 marks for proper squareness and verticality checks recorded)
3
Overall neatness and clarity of recorded take off quantities
(Award 3 marks for well-presented and legible booking)
3
Sub-Total23
GRAND TOTAL51
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Quantify and describe framed structural elements for a single storey buildingPractical 3
🔒Take off quantities for drainage pipe run systemPractical 4
🔒Quantify external site works including landscaping and pavingPractical 5
🔒Take off quantities for plumbing installations in a single-storey residential buildingPractical 6
🔒Quantify Electrical and Mechanical Services Installations for a Small Residential UnitPractical 7
🔒Measurement and Quantification of Fixings and Fixtures for a Residential WallPractical 8
🔒Booking and Description of Items for Quantity Take OffPractical 9
🔒Comprehensive Quantity Take Off for Mixed Building WorksPractical 10
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 16 questions Start quiz ▾
0%
0 / 2
🔒

14 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Prepare a neat and clear dimension sheet or paper using the standard quantities format.
  • Create a detailed list of quantities to measure based on the specific building items involved.
  • Calculate quantities of building elements accurately using the correct units of measurement.
  • Record all dimensions correctly by following the key principles of measurement.
  • Describe booked items clearly and correctly using the standard method of measurement (SMM) for building and civil works.