By the end of this chapter, you will be able to:
Mastering these skills will help you confidently manage building measurements, ensuring precise and reliable work in your trade.
Abstracting measured quantities is a core skill for quantity surveyors tasked with preparing accurate cost estimates and bills of quantities. This chapter focuses on the processes involved in organizing and summarizing measured building work data into abstracting sheets, which form the basis for cost analysis and tender documentation. It also covers the technique of running through dimensions, a systematic method used to verify and record measurements with standardized symbols. Mastery of these techniques ensures precision and efficiency in quantity surveying practice in Kenya’s construction industry.
Abstracting sheets are essential documents where detailed measurements are compiled and summarized for pricing and costing. In the Kenyan quantity surveying profession, abstracting sheets enable clear communication of quantities for procurement and contract management. This section covers the preparation of abstracting sheets and the transfer of booked quantities from measurement records.
The preparation of an abstracting sheet involves organizing measured quantities into a structured format that facilitates pricing and analysis. The abstract sheet typically lists item descriptions, units, quantities, and references to original measurements.
The governing principle is:
$$ \text{Abstracted Quantity} = \sum \text{Booked Quantities from Measurement Sheets} $$
Example 1: A quantity surveyor has measured 5 slabs each with an area of 12 m². Prepare the abstracted quantity.
Given: Number of slabs = 5, Area per slab = 12 m²
$$ \text{Abstracted Quantity} = 5 \times 12 $$
$$ = 60 \text{ m}^2 $$
Answer: 60 m²
Example 2: A column has been measured with four sides each 0.3 m wide and 3 m high. The quantity to be abstracted is length of shuttering required.
Given: Number of sides = 4, Width per side = 0.3 m, Height = 3 m
$$ \text{Perimeter} = 4 \times 0.3 = 1.2 \text{ m} $$
$$ \text{Shuttering area} = \text{Perimeter} \times \text{Height} = 1.2 \times 3 $$
$$ = 3.6 \text{ m}^2 $$
Answer: 3.6 m²
Example 3: A beam of length 8 m, cross-sectional width 0.4 m, and depth 0.6 m is measured. Abstract the volume of concrete.
Given: Length = 8 m, Width = 0.4 m, Depth = 0.6 m
$$ \text{Volume} = \text{Length} \times \text{Width} \times \text{Depth} $$
$$ = 8 \times 0.4 \times 0.6 $$
$$ = 1.92 \text{ m}^3 $$
Answer: 1.92 m³
Example 4: Five identical walls each 4 m long, 3 m high, and 0.2 m thick are measured. Abstract the total wall volume.
Given: Number of walls = 5, Length = 4 m, Height = 3 m, Thickness = 0.2 m
$$ \text{Volume per wall} = 4 \times 3 \times 0.2 = 2.4 \text{ m}^3 $$
$$ \text{Total volume} = 5 \times 2.4 = 12 \text{ m}^3 $$
Answer: 12 m³
Example 5: A slab with dimensions 10 m by 6 m and thickness 0.15 m is measured. Abstract the quantity of concrete.
Given: Length = 10 m, Width = 6 m, Thickness = 0.15 m
$$ \text{Volume} = 10 \times 6 \times 0.15 $$
$$ = 9 \text{ m}^3 $$
Answer: 9 m³
Example 6: A measurement sheet records three different areas for suspended slabs: 10 m², 15 m², and 8 m². Abstract the total quantity.
Given: Areas = 10 m², 15 m², 8 m²
$$ \text{Abstracted Quantity} = 10 + 15 + 8 $$
$$ = 33\ \text{m}^2 $$
Answer: 33 m²
Transferring booked quantities involves moving measurements from field books or measurement sheets into the abstracting sheet accurately to avoid errors in costing.
The principle formula is:
$$ \text{Abstracted Quantity} = \sum \text{Booked Quantities Transferred} $$
Example 1: Measurement sheet shows 20 m² of plastering done on walls. Transfer this quantity to the abstracting sheet.
Given: Plastered area = 20 m²
$$ \text{Abstracted Quantity} = 20 \text{ m}^2 $$
Answer: 20 m²
Example 2: Booked quantity for floor screeding is 15 m². Confirm the total abstracted quantity after transferring.
Given: Booked quantity = 15 m²
$$ \text{Abstracted Quantity} = 15 \text{ m}^2 $$
Answer: 15 m²
Example 3: A measurement book shows 30 m length of pipework installed. Transfer this quantity.
Given: Pipe length = 30 m
$$ \text{Abstracted Quantity} = 30 \text{ m} $$
Answer: 30 m
Example 4: Booked quantity of blockwork is 50 m². Transfer to the abstract sheet.
Given: Blockwork area = 50 m²
$$ \text{Abstracted Quantity} = 50 \text{ m}^2 $$
Answer: 50 m²
Example 5: Booked quantity for excavation is 12 m³. Transfer to abstracting sheet.
Given: Excavation volume = 12 m³
$$ \text{Abstracted Quantity} = 12 \text{ m}^3 $$
Answer: 12 m³
Example 6: Measurement sheets show three booked quantities for blockwork: 12 m², 18 m², and 20 m². Transfer and sum these to the abstracting sheet.
Given: Blockwork areas = 12 m², 18 m², 20 m²
$$ \text{Abstracted Quantity} = 12 + 18 + 20 $$
$$ = 50\ \text{m}^2 $$
Answer: 50 m²
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter focuses on the process of abstracting measured quantities in building works, starting with the preparation of the abstracting sheet, which organizes and summarizes the quantities derived from measurements. It explains how to transfer booked quantities accurately onto the abstracting sheet to ensure clarity and correctness in the documentation. The chapter then covers running through dimensions, detailing the common symbols used to represent various measurements and how they assist in the clear communication of dimensional data. Following this, casting up dimensions is discussed, including the symbols used to compile and sum these dimensions effectively. Finally, the chapter addresses the calculation of net quantities, emphasizing the importance of precise arithmetic to determine the actual amounts of materials or work needed. Together, these topics provide a comprehensive overview of managing and interpreting measurements for building projects.
A wall is 5 m long, 3 m high, and 0.3 m thick. Calculate the volume of the wall to be abstracted. (2 marks)
A floor slab measures 8 m by 6 m with a thickness of 0.15 m. Determine the net concrete volume required. (2 marks)
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape (5m) | Abstracting Sheet template (printed) |
| Calculator | Measurement data sheet |
| Pens | |
| Ruler (30cm) | |
| Clipboard |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape (5m) | 1 Pc per Candidate |
| 2 | Calculator | 1 Pc per Candidate |
| 3 | Pens | 2 Pcs per Candidate |
| 4 | Ruler (30cm) | 1 Pc per Candidate |
| 5 | Abstracting Sheet template (printed) | 1 Pc per Candidate |
| 6 | Measurement data sheet | 1 Pc per Candidate |
| 7 | Clipboard | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: PREPARATION OF ABSTRACTING SHEET | |||
| Used appropriate PPE (helmet, boots, reflective vest) (Award 1 mark for each PPE worn correctly) | 3 | ||
| Assembled all required tools and materials before starting (Award 2 marks for assembly of all listed tools and materials) | 2 | ||
| Reviewed the measurement data sheet accurately (Award 3 marks for thorough review and understanding) | 3 | ||
| Correctly calculated quantities for walling (m2) based on measurements (Award 5 marks for accurate calculations within ±2% tolerance) | 5 | ||
| Accurately abstracted concrete volumes (m3) from given measurements (Award 5 marks for correct volume abstraction within ±2% tolerance) | 5 | ||
| Correctly abstracted reinforcement quantities (kg) as per provided data (Award 5 marks for accurate reinforcement abstraction within ±2% tolerance) | 5 | ||
| Organized the abstracting sheet neatly with correct headings and units (Award 3 marks for clear, legible, and well-organized sheet) | 3 | ||
| Cross-checked all entries for consistency and correctness (Award 4 marks for thorough verification and correction of errors) | 4 | ||
| Sub-Total | 30 | ||
| PRODUCT CHECKLIST | |||
| Abstracting sheet accurately reflects measured quantities with correct totals (Award 10 marks for complete and correct abstracting sheet matching provided data) | 10 | ||
| Sheet is neat, legible, and properly formatted with no calculation errors (Award 5 marks for overall presentation and absence of errors) | 5 | ||
| Sub-Total | 15 | ||
| GRAND TOTAL | 45 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape (5m) | Booking Sheets |
| Calculator | Abstracting Sheets |
| Pens | |
| Ruler (30 cm) | |
| Clipboard |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape (5m) | 1 Pc per Candidate |
| 2 | Calculator | 1 Pc per Candidate |
| 3 | Pens | 2 Pcs per Candidate |
| 4 | Booking Sheets | 1 Set per Candidate |
| 5 | Abstracting Sheets | 1 Set per Candidate |
| 6 | Clipboard | 1 Pc per Candidate |
| 7 | Ruler (30 cm) | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: TRANSFER OF QUANTITIES | |||
| Identified and used appropriate PPE (e.g. helmet, safety boots) according to safety regulations (Award 1 mark for each correctly used PPE) | 3 | ||
| Assembled all required tools and materials before starting the transfer (Award 0.5 mark for each correctly assembled tool/material, max 2 marks) | 2 | ||
| Read and interpreted the booking sheets correctly (Award 1 mark for each correct interpretation of at least 4 quantity items) | 4 | ||
| Accurately transferred each booked quantity to the abstracting sheet without errors (Award 2 marks for each correctly transferred quantity, max 8 marks) | 8 | ||
| Used calculator correctly to sum totals where necessary (Award 1 mark for each correct calculation of totals) | 3 | ||
| Maintained neatness and legibility of entries on the abstracting sheet (Award 2 marks for neat and legible handwriting) | 2 | ||
| Verified totals and cross-checked transferred quantities for accuracy (Award 1 mark for each verification step completed, max 3 marks) | 3 | ||
| Sub-Total | 25 | ||
| PRODUCT CHECKLIST | |||
| Abstracting sheet contains all booked quantities accurately transferred with correct totals (Award 2 marks for each set of quantities transferred correctly and totals verified) | 8 | ||
| Entries on the abstracting sheet are neat, clear and well-organized (Award 5 marks for overall neatness and presentation) | 5 | ||
| Final abstracting sheet matches the booking sheet quantities within acceptable tolerance (±1%) (Award 7 marks for accuracy within tolerance) | 7 | ||
| Sub-Total | 20 | ||
| GRAND TOTAL | 45 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.