By the end of this chapter, you will be able to:
Mastering these skills ensures your building measurements are precise and reliable, which is essential for quality workmanship in the construction trade.
Measurement of building works is a fundamental aspect of quantity surveying, ensuring accurate calculation of materials, labour, and costs for construction projects. Squaring dimensions, a critical technique in measurement, involves the multiplication of linear measurements to determine areas and volumes essential for preparing bills of quantities. Mastery of these skills enables quantity surveyors in Kenya to produce precise cost estimates and control budgets effectively, supporting clients such as county governments, private developers, and financial institutions in managing their resources. This chapter focuses on the timesing of dimensions, a key process in squaring that underpins accurate quantification of building elements.
In quantity surveying, timesing of dimensions refers to the multiplication of linear measurements to calculate areas, volumes, or quantities of construction materials and works. This process is vital for developing bills of quantities and cost plans that reflect the true scope of works in a building project. Accurate timesing ensures that the quantities recorded correspond to the actual physical dimensions on site, enabling effective cost control and resource allocation. For instance, at a county government office expansion project in Kisumu, precise timesing of floor areas and wall volumes was essential to avoid budget overruns and delays due to material shortages.
Timesing of dimensions means multiplying two or more linear measurements to determine a derived quantity such as an area or volume. In building measurement, this is a fundamental arithmetic operation used to convert linear lengths into measurable quantities for costing and procurement.
The primary purpose of timesing is to translate linear measurements into quantities that can be priced and managed within a construction budget. This process supports cost estimation, procurement planning, and financial reporting.
Timesing can be performed using various methods depending on the complexity of the measurement and available tools. Quantity surveyors in Kenya often employ manual calculations, digital spreadsheets, and specialized software for accuracy and efficiency.
Timesing, while straightforward, can present challenges related to measurement errors, unit inconsistencies, and complex shapes. Addressing these challenges is crucial to maintaining accuracy in quantity surveying.
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter has explored the essential techniques involved in squaring dimensions within building measurement. It began with an explanation of timesing of dimensions, highlighting the process of multiplying booked measurements by a specified factor to facilitate accurate scaling and calculation. The discussion then moved to dotting of dimensions, a method used to clearly mark and differentiate specific measurements on drawings or records for ease of reference. Finally, the chapter covered the practical applications of squaring booked dimensions, emphasizing hands-on exercises and projects that reinforce the theoretical concepts. These projects demonstrate how to apply timesing and dotting methods in real-world measurement tasks to ensure precision in building works. Through this comprehensive approach, students gain both the theoretical understanding and practical skills necessary for effective dimension squaring in construction measurement.
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape 5m | Lime Powder |
| Builder's Square | Nails 2 inch |
| Spirit Level 600mm | Safety Helmet |
| Plumb Bob | Safety Boots |
| Profile Boards | Reflective Jacket |
| Hammer | |
| Pencil |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape 5m | 1 Pc per Candidate |
| 2 | Builder's Square | 1 Pc per 4 Candidates |
| 3 | Spirit Level 600mm | 1 Pc per Candidate |
| 4 | Plumb Bob | 1 Pc per Candidate |
| 5 | Profile Boards | 4 Pcs per Candidate |
| 6 | Lime Powder | Sufficient per Candidate |
| 7 | Nails 2 inch | Sufficient per Candidate |
| 8 | Hammer | 1 Pc per 4 Candidates |
| 9 | Pencil | 1 Pc per Candidate |
| 10 | Safety Helmet | 1 Pc per Candidate |
| 11 | Safety Boots | 1 Pair per Candidate |
| 12 | Reflective Jacket | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: SETTING OUT AND TIMESING OF DIMENSIONS | |||
| Used appropriate PPEs (helmet, boots, reflective jacket) (Award 1 mark for each correctly used PPE, total 5 marks) | 5 | ||
| Assembled and prepared all required tools and materials for timesing (Award 1 mark each for assembling measuring tape, builder's square, profile boards) | 3 | ||
| Selected and cleared a sufficient area for layout (Award 2 marks for proper site preparation) | 2 | ||
| Set out profile boards accurately at corners according to layout (Award 1 mark for each correctly positioned profile board, total 4 marks) | 4 | ||
| Measured and marked linear dimensions on profile boards using timesing method (Award 1 mark per correct timesing measurement and marking, total 6 marks) | 6 | ||
| Checked and ensured layout is square by verifying diagonal measurements (Award 2 marks for each correct diagonal measurement, total 4 marks) | 4 | ||
| Recorded all timesing measurements clearly and accurately (Award 1 mark per correct recording, total 3 marks) | 3 | ||
| Marked layout on ground correctly with lime at corners and edges (Award 1 mark for each correctly lime marked corner, total 3 marks) | 3 | ||
| Cleaned and stored tools and working area after completion (Award 1 mark each for cleaning and proper storing, total 2 marks) | 2 | ||
| Sub-Total | 32 | ||
| PRODUCT CHECKLIST | |||
| Layout dimensions are accurate within ±50mm tolerance (6000mm x 4500mm) (Award 6 marks for correct linear dimensions within tolerance) | 6 | ||
| Layout is squared with diagonals measuring approximately 7500mm ±50mm (Award 5 marks for correct diagonal measurements indicating squareness) | 5 | ||
| Timesing markings on profile boards are clear, legible and complete (Award 3 marks for neat and complete timesing markings) | 3 | ||
| Profile boards are stable and correctly positioned as per layout (Award 4 marks for correct positioning and stability of profile boards) | 4 | ||
| Sub-Total | 18 | ||
| GRAND TOTAL | 50 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape (5m) | Lime Powder |
| Builder's Square | Nails 2" |
| Spirit Level | Profile Boards (25mm thick timber) |
| Hammer | |
| Plumb Bob | |
| Pencil / Marker Pen |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape (5m) | 1 Pc per Candidate |
| 2 | Builder's Square | 1 Pc per 4 Candidates |
| 3 | Spirit Level | 1 Pc per Candidate |
| 4 | Hammer | 1 Pc per 4 Candidates |
| 5 | Nails 2" | Sufficient per Candidate |
| 6 | Lime Powder | Sufficient per Candidate |
| 7 | Profile Boards (25mm thick timber) | 8m length Pc per Candidate |
| 8 | Plumb Bob | 1 Pc per Candidate |
| 9 | Pencil / Marker Pen | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: PREPARATION AND SITE SETTING OUT | |||
| Identified and used appropriate PPE: helmet, safety boots, reflective jacket (Award 1 mark each for correctly worn PPE) | 3 | ||
| Assembled all necessary tools and materials before starting work (Award 0.5 mark each for assembling 4 tools/materials) | 2 | ||
| Prepared the site by clearing and demarcating sufficient area for the layout (Award 2 marks for correct and clean site preparation) | 2 | ||
| Set out the profile boards at correct positions using measuring tape and nails (Award 1 mark each for correct placement of three profile boards) | 3 | ||
| Used builder's square and spirit level to ensure layout is squared and level (Award 1 mark each for correct use of builder's square, spirit level, and plumb bob) | 3 | ||
| Marked the layout corners and edges using lime powder accurately (Award 1 mark each for marking all four corners accurately) | 3 | ||
| Dotted the measured dimensions clearly and accurately on the layout (Award 1 mark each for dotting four key dimensions within +50mm tolerance) | 4 | ||
| Sub-Total | 20 | ||
| PRODUCT CHECKLIST | |||
| Dimensions dotted on layout match 4000mm length (+50mm tolerance) (Award 2 marks for correct length dimension) | 2 | ||
| Dimensions dotted on layout match 3000mm width (+50mm tolerance) (Award 2 marks for correct width dimension) | 2 | ||
| Layout is well squared with correct diagonal measurements (+50mm tolerance) (Award 3 marks for correct squaring of layout) | 3 | ||
| Profile boards are positioned correctly according to the layout plan (Award 3 marks for correct positioning and firm fixing) | 3 | ||
| Sub-Total | 10 | ||
| GRAND TOTAL | 30 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.