These skills will help you measure building works confidently and accurately, which is essential for successful construction projects and cost management.
Preparation of quantities checklist is a critical preliminary step in the take off of building works. It ensures accuracy, completeness, and consistency in quantifying materials and work items, which are fundamental for preparing bills of quantities, cost estimates, and tender documents. For Quantity Surveyors in Kenya, mastering this checklist helps avoid costly errors, supports compliance with local standards such as the PWD Standard Method of Measurement, and facilitates effective communication with contractors and clients.
The first step in preparing a quantities checklist is to fully understand the project scope. This involves reviewing architectural and structural drawings, specifications, and contract documents to identify all elements that require measurement.
Example 1:
A hospital project has architectural drawings specifying a reinforced concrete slab of thickness 150 mm. The Quantity Surveyor needs to confirm the scope of work for the slab.
Given: Slab thickness = 150 mm, slab area = 200 m²$$\text{Volume} = \text{Area} \times \text{Thickness}$$$$= 200 \, m^{2} \times 0.15 \, m$$$$= 30 \, m^{3}$$
Answer: The scope includes 30 m³ of reinforced concrete slab.
Example 2:
A retail building specification includes a provisional sum for landscaping. The Quantity Surveyor must decide whether to include this in the measured works checklist.
Given: Provisional sum = Ksh 500,000
Example 3:
A school project has specified prime cost items for sanitary fittings. The Quantity Surveyor must list these separately.
Given: Prime cost for sanitary fittings = Ksh 1,200,000
The checklist must specify the measurement units and methods for each work item to ensure uniformity and compliance with Kenyan standards.
Example 1:
A bank building requires plastering on walls with an area of 350 m². The measurement unit is square meters.
Given: Area = 350 m²
Example 2:
A county government office requires 120 linear meters of electrical conduit. The measurement unit is linear meter.
Given: Length = 120 m
Example 3:
A hotel project includes concrete foundation excavation with an irregular shape approximated as a trapezoid. The Quantity Surveyor uses volume measurement.
Given: Base 1 = 8 m, Base 2 = 5 m, Height = 10 m, Depth = 1.2 m$$\text{Area} = \frac{(8 + 5)}{2} \times 10 = 65 \, m^{2}$$$$\text{Volume} = 65 \, m^{2} \times 1.2 \, m = 78 \, m^{3}$$
Answer: Excavation volume is 78 m³.
Accuracy in quantities depends on the reliability of the source documents. Verification of drawings and specifications is essential before commencing take off.
Example 1:
A SACCO office drawing shows a wall length of 12 m in the architectural plan but 11.8 m in the structural plan. The Quantity Surveyor must verify which to use.
Given: Architectural wall length = 12 m, Structural wall length = 11.8 m
Example 2:
A university project drawing scale is 1:100. The Quantity Surveyor measures a room length of 5 cm on the drawing.
Given: Drawing length = 5 cm, Scale = 1:100$$\text{Actual length} = 5 \, cm \times 100 = 500 \, cm = 5 \, m$$
Answer: Room length is 5 m.
Example 3:
A retail business project has missing specifications for floor finishes. The Quantity Surveyor must request missing details before measurement.
Given: Missing floor finish specs
Organized documentation supports accuracy and traceability in quantity take off. Proper preparation of measurement sheets is essential.
Example 1:
A cooperative society building project measurement sheet includes:
Example 2:
A KRA office project uses software to record measurements with automatic calculations and version tracking.
Given: Software generates measurement sheets with timestamps and user details.
Answer: Digital documentation improves accuracy and accountability.
Example 3:
A farm building project measurement sheet omits drawing references. The Quantity Surveyor must add these for completeness.
Given: Missing drawing reference
In Quantity Surveying practice in Kenya, accurate take off of building works is critical for preparing bills of quantities and cost estimates. Building works include diverse elements such as framed structures, reinforcement, staircases, doors, windows, and finishes. Each element has unique measurement requirements and calculation methods that must comply with Kenyan standards and construction practices.
Framed structures consist of beams, columns, slabs, and foundations forming the skeleton of a building. Quantity Surveyors must accurately measure the volume or length of these components to estimate materials and costs. The take off involves calculating the dimensions from drawings and converting them to quantities such as cubic meters for concrete or linear meters for beams.
The basic formula for volume of a rectangular beam or column is:
$$ V = L \times B \times H $$
where \(V\) is volume in cubic meters, \(L\) is length, \(B\) is breadth, and \(H\) is height.
Example 1: Calculate the volume of a rectangular beam with length 6 m, breadth 0.3 m, and height 0.5 m.
Given: \(L = 6\, m\), \(B = 0.3\, m\), \(H = 0.5\, m\)
$$ V = L \times B \times H $$
$$ V = 6 \times 0.3 \times 0.5 $$
$$ V = 0.9\, m^3 $$
Answer: 0.9 cubic meters
Example 2: Find the volume of a rectangular column measuring 0.4 m by 0.4 m by 3 m height.
Given: \(L = 3\, m\), \(B = 0.4\, m\), \(H = 0.4\, m\)
$$ V = L \times B \times H $$
$$ V = 3 \times 0.4 \times 0.4 $$
$$ V = 0.48\, m^3 $$
Answer: 0.48 cubic meters
Example 3: A slab measures 8 m by 5 m with a thickness of 0.15 m. Calculate the volume.
Given: \(L = 8\, m\), \(B = 5\, m\), \(H = 0.15\, m\)
$$ V = L \times B \times H $$
$$ V = 8 \times 5 \times 0.15 $$
$$ V = 6\, m^3 $$
Answer: 6 cubic meters
Example 4: Calculate the volume of a beam with a trapezoidal cross-section. The top width is 0.2 m, bottom width 0.4 m, height 0.5 m, length 4 m.
The average breadth \(B_{avg}\) is:
$$ B_{avg} = \frac{0.2 + 0.4}{2} = 0.3\, m $$
Volume:
$$ V = L \times B_{avg} \times H $$
$$ V = 4 \times 0.3 \times 0.5 $$
$$ V = 0.6\, m^3 $$
Answer: 0.6 cubic meters
Example 5: A column with circular cross-section of diameter 0.5 m and height 3 m. Calculate the volume.
Volume of cylinder:
$$ V = \pi \times r^2 \times h $$
Given: \(r = \frac{0.5}{2} = 0.25\, m\), \(h = 3\, m\)
$$ V = 3.142 \times 0.25^2 \times 3 $$
$$ V = 3.142 \times 0.0625 \times 3 $$
$$ V = 0.589\, m^3 $$
Answer: 0.589 cubic meters
Reinforcement take off involves measuring the length and weight of steel bars used in concrete members. Quantity Surveyors calculate the total length of bars by summing individual bar lengths and then convert to weight using the standard mass per unit length of steel bars.
The weight \(W\) of steel reinforcement is calculated by:
$$ W = L \times \rho $$
where \(L\) is total length in meters and \(\rho\) is mass per meter (kg/m) depending on bar diameter.
The mass per meter for steel bars is:
$$ \rho = \frac{d^2}{162} $$
where \(d\) is diameter in mm.
Example 1: Calculate the weight of 100 m of 12 mm diameter steel bars.
Given: \(L = 100\, m\), \(d = 12\, mm\)
Calculate \(\rho\):
$$ \rho = \frac{12^2}{162} = \frac{144}{162} = 0.889\, kg/m $$
Weight:
$$ W = 100 \times 0.889 = 88.9\, kg $$
Answer: 88.9 kilograms
Example 2: Find the total weight of 150 m of 16 mm diameter bars.
Given: \(L = 150\, m\), \(d = 16\, mm\)
$$ \rho = \frac{16^2}{162} = \frac{256}{162} = 1.58\, kg/m $$
$$ W = 150 \times 1.58 = 237\, kg $$
Answer: 237 kilograms
Example 3: A beam requires 8 bars each 6 m long of 20 mm diameter. Calculate total weight.
Given: Number of bars \(n = 8\), Length per bar \(L = 6\, m\), \(d = 20\, mm\)
Total length:
$$ L_{total} = 8 \times 6 = 48\, m $$
Calculate \(\rho\):
$$ \rho = \frac{20^2}{162} = \frac{400}{162} = 2.47\, kg/m $$
Weight:
$$ W = 48 \times 2.47 = 118.56\, kg $$
Answer: 118.56 kilograms
Example 4: Calculate the weight of 50 m of 10 mm diameter bars.
Given: \(L = 50\, m\), \(d = 10\, mm\)
$$ \rho = \frac{10^2}{162} = \frac{100}{162} = 0.617\, kg/m $$
$$ W = 50 \times 0.617 = 30.85\, kg $$
Answer: 30.85 kilograms
Example 5: A column requires 12 bars each 4.5 m long of 25 mm diameter. Calculate total weight.
Given: \(n = 12\), \(L = 4.5\, m\), \(d = 25\, mm\)
Total length:
$$ L_{total} = 12 \times 4.5 = 54\, m $$
$$ \rho = \frac{25^2}{162} = \frac{625}{162} = 3.86\, kg/m $$
$$ W = 54 \times 3.86 = 208.44\, kg $$
Answer: 208.44 kilograms
Measurement of staircases, podiums, and ramps involves calculating areas and volumes of complex shapes. Quantity Surveyors measure tread and riser dimensions for stairs, surface areas for podiums, and slope lengths for ramps to estimate concrete, finishes, and reinforcement.
Volume of a staircase is often approximated by the product of the floor area it occupies and average thickness.
The slope length \(L_s\) of a ramp is:
$$ L_s = \frac{H}{\sin \theta} $$
where \(H\) is vertical height and \(\theta\) is slope angle.
Example 1: Calculate the volume of concrete for a staircase occupying 3 m by 2 m floor area with an average thickness of 0.2 m.
Given: \(L = 3\, m\), \(B = 2\, m\), \(H = 0.2\, m\)
$$ V = L \times B \times H $$
$$ V = 3 \times 2 \times 0.2 $$
$$ V = 1.2\, m^3 $$
Answer: 1.2 cubic meters
Example 2: A ramp rises 1.5 m with a slope angle of 10°. Calculate the slope length.
Given: \(H = 1.5\, m\), \(\theta = 10^\circ\)
$$ L_s = \frac{H}{\sin \theta} $$
$$ L_s = \frac{1.5}{\sin 10^\circ} $$
$$ L_s = \frac{1.5}{0.1736} = 8.64\, m $$
Answer: 8.64 meters
Example 3: Find the surface area of a podium measuring 5 m by 4 m.
Given: \(L = 5\, m\), \(B = 4\, m\)
$$ A = L \times B $$
$$ A = 5 \times 4 = 20\, m^2 $$
Answer: 20 square meters
Example 4: Calculate the volume of concrete in a ramp 8 m long, 2 m wide, and 0.3 m thick.
Given: \(L = 8\, m\), \(B = 2\, m\), \(H = 0.3\, m\)
$$ V = L \times B \times H $$
$$ V = 8 \times 2 \times 0.3 $$
$$ V = 4.8\, m^3 $$
Answer: 4.8 cubic meters
Example 5: A staircase has 12 steps, each with a tread of 0.3 m and riser of 0.15 m. Calculate the total vertical height and horizontal length.
Given: Number of steps \(n=12\), tread \(t=0.3\, m\), riser \(r=0.15\, m\)
Total height:
$$ H = n \times r = 12 \times 0.15 = 1.8\, m $$
Total length:
$$ L = n \times t = 12 \times 0.3 = 3.6\, m $$
Answer: Height = 1.8 meters, Length = 3.6 meters
Doors take off involves measuring the number, sizes, and types of doors for materials and labour estimation. Quantity Surveyors measure door leaf dimensions, frame sizes, and count ironmongery items. Door areas are used to estimate finishes such as paint or veneer.
The area \(A\) of a door leaf is:
$$ A = H \times W $$
where \(H\) is height and \(W\) is width.
Example 1: Calculate the area of a door measuring 2 m by 0.9 m.
Given: \(H = 2\, m\), \(W = 0.9\, m\)
$$ A = H \times W = 2 \times 0.9 = 1.8\, m^2 $$
Answer: 1.8 square meters
Example 2: A project has 10 doors each measuring 2.1 m by 0.8 m. Calculate total door area.
Given: \(n = 10\), \(H = 2.1\, m\), \(W = 0.8\, m\)
Single door area:
$$ A = 2.1 \times 0.8 = 1.68\, m^2 $$
Total area:
$$ A_{total} = 10 \times 1.68 = 16.8\, m^2 $$
Answer: 16.8 square meters
Example 3: Calculate the perimeter of a door leaf measuring 2 m by 0.9 m to estimate door frame length.
Given: \(H = 2\, m\), \(W = 0.9\, m\)
$$ P = 2(H + W) = 2(2 + 0.9) = 2 \times 2.9 = 5.8\, m $$
Answer: 5.8 meters
Example 4: A double leaf door has each leaf measuring 2 m by 0.75 m. Calculate total leaf area.
Given: \(n = 2\), \(H = 2\, m\), \(W = 0.75\, m\)
Single leaf area:
$$ A = 2 \times 0.75 = 1.5\, m^2 $$
Total area:
$$ A_{total} = 2 \times 1.5 = 3.0\, m^2 $$
Answer: 3.0 square meters
Example 5: Calculate the volume of timber needed for door leaves 2 m by 0.9 m with thickness 50 mm.
Given: \(H = 2\, m\), \(W = 0.9\, m\), thickness \(t = 0.05\, m\)
$$ V = H \times W \times t = 2 \times 0.9 \times 0.05 = 0.09\, m^3 $$
Answer: 0.09 cubic meters
Windows take off includes measuring window frame dimensions, glass area, and quantity. Quantity Surveyors calculate the perimeter for frames and area for glazing. This helps in material take off and costing for frames, glass, and finishes.
Window area \(A\) is calculated as:
$$ A = H \times W $$
where \(H\) is height and \(W\) is width.
Example 1: Calculate the glass area of a window measuring 1.2 m by 1.0 m.
Given: \(H = 1.2\, m\), \(W = 1.0\, m\)
$$ A = 1.2 \times 1.0 = 1.2\, m^2 $$
Answer: 1.2 square meters
Example 2: A building has 15 windows each measuring 1.5 m by 1.2 m. Calculate total glass area.
Given: \(n = 15\), \(H = 1.5\, m\), \(W = 1.2\, m\)
Single window area:
$$ A = 1.5 \times 1.2 = 1.8\, m^2 $$
Total area:
$$ A_{total} = 15 \times 1.8 = 27\, m^2 $$
Answer: 27 square meters
Example 3: Calculate the perimeter of a window frame 1.2 m by 1 m.
Given: \(H = 1.2\, m\), \(W = 1.0\, m\)
$$ P = 2(H + W) = 2(1.2 + 1.0) = 4.4\, m $$
Answer: 4.4 meters
Example 4: Calculate the volume of timber needed for a window frame 1.2 m by 1.0 m with frame cross-section 0.05 m by 0.05 m.
Given: \(P = 4.4\, m\), cross-section \(A = 0.05 \times 0.05 = 0.0025\, m^2\)
$$ V = P \times A = 4.4 \times 0.0025 = 0.011\, m^3 $$
Answer: 0.011 cubic meters
Example 5: Calculate the glass area for a bay window consisting of three panels: one 1.2 m by 1 m and two 0.6 m by 1 m.
Given: Panel 1: \(1.2 \times 1 = 1.2\, m^2\), Panels 2 and 3: \(0.6 \times 1 = 0.6\, m^2\) each
Total area:
$$ A_{total} = 1.2 + 2 \times 0.6 = 1.2 + 1.2 = 2.4\, m^2 $$
Answer: 2.4 square meters
Finishes take off involves measuring surface areas for plaster, paint, tiles, and other finishes. Quantity Surveyors measure wall and floor areas, deduct openings, and calculate quantities for materials. Accurate measurement ensures correct costing and reduces wastage.
Surface area \(A\) is found by:
$$ A = L \times H $$
for walls, subtracting areas of doors and windows.
Example 1: Calculate the plastering area of a wall 5 m long and 3 m high with one door 2 m by 0.9 m.
Given: Wall area:
$$ A_{wall} = 5 \times 3 = 15\, m^2 $$
Door area:
$$ A_{door} = 2 \times 0.9 = 1.8\, m^2 $$
Plaster area:
$$ A_{plaster} = 15 - 1.8 = 13.2\, m^2 $$
Answer: 13.2 square meters
Example 2: Calculate paint area for a room with four walls each 6 m by 3 m, with two windows 1.2 m by 1.5 m and one door 2 m by 1 m.
Wall area:
$$ A_{walls} = 4 \times 6 \times 3 = 72\, m^2 $$
Windows area:
$$ A_{windows} = 2 \times 1.2 \times 1.5 = 3.6\, m^2 $$
Door area:
$$ A_{door} = 2 \times 1 = 2\, m^2 $$
Paint area:
$$ A_{paint} = 72 - (3.6 + 2) = 72 - 5.6 = 66.4\, m^2 $$
Answer: 66.4 square meters
Example 3: Calculate floor tiling area for a hall 10 m by 8 m with a built-in staircase of 3 m by 2 m.
Floor area:
$$ A_{floor} = 10 \times 8 = 80\, m^2 $$
Staircase area:
$$ A_{stairs} = 3 \times 2 = 6\, m^2 $$
Tiling area:
$$ A_{tile} = 80 - 6 = 74\, m^2 $$
Answer: 74 square meters
Example 4: Calculate the plastering area of a ceiling 6 m by 5 m.
Given:
$$ A = 6 \times 5 = 30\, m^2 $$
Answer: 30 square meters
Example 5: Calculate the paintable surface area of a room measuring 4 m by 3 m by 3 m high with one door 2 m by 0.9 m and one window 1.2 m by 1.2 m.
Wall area:
$$ A_{walls} = 2 \times (4 + 3) \times 3 = 2 \times 7 \times 3 = 42\, m^2 $$
Door area:
$$ A_{door} = 2 \times 0.9 = 1.8\, m^2 $$
Window area:
$$ A_{window} = 1.2 \times 1.2 = 1.44\, m^2 $$
Paint area:
$$ A_{paint} = 42 - (1.8 + 1.44) = 42 - 3.24 = 38.76\, m^2 $$
Answer: 38.76 square meters
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter focused on the measurement process for building works, starting with the preparation of a quantities checklist to ensure systematic and accurate take off. It then detailed the take off of various building components including framed structures, reinforcement, staircases, podiums, ramps, doors, windows, and finishes, emphasizing the specific considerations for each. The importance of precise booking of dimensions was highlighted to maintain clarity and consistency in measurement records. Finally, the chapter addressed the correct description of booked items to ensure that all quantities are clearly and comprehensively documented for effective communication and cost estimation. Together, these topics provide a comprehensive framework for the accurate measurement and documentation of building works.
A rectangular framed structure has a length of 8 m, width of 6 m, and height of 3 m. Calculate the total length of columns if columns are placed at every corner and at the midpoint of each side. (2 marks)
Calculate the total volume of concrete required for a slab measuring 10 m by 8 m with a thickness of 0.15 m. (2 marks)
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape 5m | Working Drawing - Single Storey Residential Building |
| Calculator | Standard Quantity Takeoff Sheets |
| Scale Ruler (Metric) | |
| Notebook and Pen |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape 5m | 1 Pc per Candidate |
| 2 | Notebook and Pen | 1 Set per Candidate |
| 3 | Calculator | 1 Pc per Candidate |
| 4 | Scale Ruler (Metric) | 1 Pc per Candidate |
| 5 | Working Drawing - Single Storey Residential Building | 1 Set per Candidate |
| 6 | Standard Quantity Takeoff Sheets | 1 Set per Candidate |
| 7 | PPE Kit (Helmet, Safety Boots, Reflective Jacket) | 1 Set per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: PREPARATION AND USE OF PPE | |||
| Identified and donned appropriate PPE (helmet, safety boots, reflective jacket) (Award 1 mark for each correctly worn PPE item) | 3 | ||
| Assembled all necessary tools and materials before starting the task (Award 2 marks for assembling all listed tools and materials) | 2 | ||
| Reviewed the working drawing accurately to understand building dimensions and specifications (Award 3 marks for thorough review and understanding) | 3 | ||
| Prepared a suitable workspace for taking measurements and recording quantities (Award 2 marks for proper workspace preparation) | 2 | ||
| Sub-Total | 10 | ||
| TASK 2: QUANTITY TAKEOFF EXECUTION | |||
| Measured and noted all linear dimensions (lengths, widths, heights) accurately from the drawing (Award 1 mark for each correct dimension measurement: length, width, height, thickness) | 4 | ||
| Calculated quantities of bricks, concrete, steel reinforcement, sand, and ballast correctly (Award 1 mark for each material correctly quantified: bricks, concrete, steel, sand, ballast, cement) | 6 | ||
| Completed the quantities checklist clearly and legibly with correct units (Award 3 marks for neat, complete, and accurate checklist) | 3 | ||
| Cross-checked all quantities against the working drawing for consistency (Award 3 marks for thorough cross-checking) | 3 | ||
| Sub-Total | 16 | ||
| PRODUCT CHECKLIST | |||
| Quantities checklist includes all required materials: bricks, cement (bags), sand (m3), ballast (m3), steel reinforcement (kg) (Award 1 mark for each material correctly listed with quantity) | 4 | ||
| Dimensions in the quantities checklist match the building dimensions 12,000mm length x 8,000mm width x 3,000mm height (Award 3 marks for accurate dimension matching) | 3 | ||
| Calculations show correct unit conversions and measurement tolerances applied (+/- 50mm where applicable) (Award 3 marks for correct application of tolerances and units) | 3 | ||
| Checklist is complete, logically organized, and suitable for use by procurement and site teams (Award 4 marks for completeness and presentation quality) | 4 | ||
| Sub-Total | 14 | ||
| GRAND TOTAL | 40 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape (5m) | Binding Wire (1kg) |
| Spirit Level | Reinforcement Bars (R12) |
| Builder's Square | Reinforcement Bars (R8) |
| Calculator | |
| Pencil and Eraser | |
| Scale Ruler (Metric) | |
| Drawing Board | |
| Cutting Tool / Pliers |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape (5m) | 1 Pc per Candidate |
| 2 | Spirit Level | 1 Pc per Candidate |
| 3 | Builder's Square | 1 Pc per 4 Candidates |
| 4 | Calculator | 1 Pc per Candidate |
| 5 | Pencil and Eraser | 1 Set per Candidate |
| 6 | Scale Ruler (Metric) | 1 Pc per Candidate |
| 7 | Drawing Board | 1 Pc per Candidate |
| 8 | Binding Wire (1kg) | 1 Kg per Candidate |
| 9 | Reinforcement Bars (R12) | 1 Full Length Pc per Candidate |
| 10 | Reinforcement Bars (R8) | 1 Full Length Pc per Candidate |
| 11 | Cutting Tool / Pliers | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: PPE and Preparation | |||
| Identified and used appropriate PPE (helmet, safety boots, reflective vest) (Award 1 mark for each correct PPE used) | 3 | ||
| Assembled all required tools and materials for the task (Award 1 mark for each correctly assembled tool/material, max 3) | 3 | ||
| Prepared workspace and arranged drawing and tools neatly (Award 2 marks for proper preparation and neat arrangement) | 2 | ||
| Sub-Total | 8 | ||
| TASK 2: Measurement and Quantity Take Off | |||
| Measured beam length, width, and depth accurately within ±10mm tolerance (Award 2 marks for length, 1 mark each for width and depth accuracy) | 4 | ||
| Measured and calculated main reinforcement bars (R12) length and quantity correctly (Award 1 mark for each correct step: measurement, calculation, total length, quantity, and presentation) | 5 | ||
| Measured and calculated stirrups (R8) length, spacing, and quantity correctly (Award 1 mark for each correct step: measurement, spacing, calculation, quantity, and presentation) | 5 | ||
| Calculated concrete volume for the beam accurately (Award 4 marks for correct volume calculation with units) | 4 | ||
| Recorded all measurements and calculations clearly and legibly (Award 2 marks for clarity and legibility of records) | 2 | ||
| Sub-Total | 20 | ||
| PRODUCT CHECKLIST | |||
| Beam dimensions match drawing within ±10mm tolerance (Length 4000mm, Width 300mm, Depth 500mm) (Award 4 marks for all dimensions correct) | 4 | ||
| Main reinforcement bars quantity and length match drawing specifications (Award 5 marks for correct quantities and lengths) | 5 | ||
| Stirrups quantity, spacing, and length match drawing specifications (Award 5 marks for correct stirrup calculations) | 5 | ||
| Concrete volume calculation is accurate and consistent with beam dimensions (Award 4 marks for correct concrete volume) | 4 | ||
| Final quantity take off report is neat, complete, and well presented (Award 4 marks for overall neatness and completeness) | 4 | ||
| Sub-Total | 22 | ||
| GRAND TOTAL | 50 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.