Chapter 2: Apply building finishes
📚 8 Topics

Building finishes are critical in defining the aesthetic appeal, durability, and functionality of constructed buildings. For Quantity Surveyors in Kenya, understanding the types of finishes and their application methods is essential for accurate cost estimation, procurement planning, and quality assurance during construction projects. Building finishes not only enhance visual appearance but also protect structural elements from environmental damage, contributing to the longevity of the asset. This chapter explores the various types of building finishes and the prevalent methods used in their application within the Kenyan construction industry.

2.1 Types of Building Finishes

The selection of building finishes depends on factors such as building use, environmental conditions, budget constraints, and desired aesthetics. For Quantity Surveyors, knowledge of these finishes is vital for preparing detailed Bills of Quantities (BoQs), advising on cost-effective alternatives, and ensuring compliance with client specifications. Building finishes broadly fall into categories including surface finishes for walls, floors, ceilings, and external facades.

2.1.1 Surface Finishes for Walls

Wall finishes improve both the appearance and protection of internal and external walls. Internally, plaster and paint are common, while externally, finishes must resist weathering and moisture ingress.

Types of Wall Finishes

  • Plastering: This involves applying a mixture of sand, cement, and water to smooth and protect masonry surfaces. In Kenyan hospitals and schools, plastered walls provide a hygienic, easy-to-clean surface.
  • Painting: Paints add colour and weather resistance. Emulsion paints are widely used indoors for their low odour and ease of application, while oil-based paints are preferred externally for durability.
  • Wall Tiles: Ceramic or porcelain tiles are used in wet areas such as bathrooms and kitchens for water resistance and easy cleaning, common in hotels and retail shops.
  • Cladding: External cladding materials such as stone, timber, or metal sheets enhance aesthetics and protect against harsh weather, often seen in county government offices.
  • Wallpaper: Though less common in Kenya due to maintenance challenges, wallpaper offers decorative options for offices and commercial buildings.

2.1.2 Floor Finishes

Floor finishes must withstand traffic loads, provide safety, and complement the building’s function. Quantity Surveyors must understand the specifications to estimate materials and labour accurately.

Common Floor Finishes

  • Ceramic Tiles: Favoured in commercial buildings and hospitals for durability and ease of cleaning.
  • Terrazzo: A composite of marble chips and cement, terrazzo floors are durable and decorative, used in university lobbies and bank foyers.
  • Vinyl Flooring: Cost-effective and water-resistant, vinyl is common in clinics and schools.
  • Parquet and Timber Flooring: Used in offices and hotels for elegance, timber flooring requires maintenance against moisture and wear.
  • Concrete Finishes: Polished or coloured concrete floors are increasingly popular for industrial and retail spaces due to low maintenance and strength.

2.1.3 Ceiling Finishes

Ceiling finishes contribute to thermal comfort, acoustics, and aesthetics. Quantity Surveyors must consider ceiling types in cost plans and maintenance projections.

Ceiling Finish Types

  • Plastered Ceilings: Smooth and painted, plastered ceilings are common in residential and office buildings.
  • Suspended Ceilings: Comprised of panels fixed to a grid, suspended ceilings allow easy access to services and improve acoustics, frequently used in hospitals and corporate offices.
  • Timber Ceilings: Used for decorative purposes in hotels and upscale commercial buildings.
  • PVC Panels: Lightweight and moisture-resistant, PVC ceilings are suitable for kitchens and bathrooms.
  • Exposed Beams: In some architectural designs, ceilings expose structural elements for aesthetic effect, requiring protective finishes to prevent deterioration.

2.1.4 External Finishes

External finishes protect the building envelope against weather and impact the overall visual impression. Quantity Surveyors must account for durability and maintenance costs in their assessments.

Types of External Finishes

  • Rendering: Cement or lime-based renders provide a uniform surface and weather resistance.
  • Stone Cladding: Natural or artificial stone enhances durability and appearance, often used in public buildings.
  • Metal Cladding: Aluminium or steel panels offer modern aesthetics and protection, common in commercial developments.
  • Paint Finishes: Weather-resistant paints protect masonry surfaces.
  • Glass Facades: Used in modern office buildings, glass facades require specialized installation and maintenance considerations.

Practice Questions

  1. Explain the importance of wall finishes in building construction and list five common types used in Kenyan buildings. (10 marks)

  2. Describe four types of floor finishes and their suitability for different building uses. (8 marks)

  3. Identify three ceiling finish types and discuss their impact on building functionality. (6 marks)

The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒2.2 Methods of Finishes Application

The application method of building finishes affects the quality, durability, and cost of the finished surface. Quantity Surveyors overseeing projects in Kenya need to understand these methods to advise on appropriate techniques, schedule work sequences, and ev…

🔒2.3 Finishes Application Procedures

In quantity surveying, understanding the application procedures for various building finishes is essential for accurate cost estimation, quality control, and contract administration. Finishes not only enhance the aesthetic appeal but also protect the structura…

🔒2.4 Emerging Technology

Emerging technologies in building finishes are reshaping the construction landscape in Kenya, offering quantity surveyors innovative materials and methods that enhance durability, aesthetics, and environmental sustainability. As Kenya’s construction industry g…

🔒2.5 Smart Wall Finishes

Smart wall finishes represent a transformative shift in interior and exterior surface treatments, combining functionality with aesthetics to meet modern demands for energy efficiency, comfort, and design innovation. In Kenya’s evolving built environment, these…

🔒2.6 Sustainability/Greening

In Kenya's evolving construction industry, sustainability and greening have become critical considerations for quantity surveyors. These concepts address the environmental, economic, and social impacts of building finishes and construction processes. Quantity…

🔒2.7 Renewable Resources

In the Kenyan construction sector, renewable resources are gaining traction as alternatives to conventional building materials. These resources regenerate naturally and can be replenished within a short time frame, making them vital for sustainable building pr…

🔒2.8 Recycled Content

In Quantity Surveying for building construction, understanding recycled content is essential for promoting sustainability while managing costs effectively. Kenyan construction projects increasingly emphasize environmental responsibility, with government polici…

Chapter Summary

This chapter explored the various types of building finishes, emphasizing their role in enhancing both the functionality and aesthetics of structures. It detailed the methods used to apply these finishes, highlighting the importance of proper technique for durability and appearance. Specific application procedures were examined for a range of finishes including tiles, paints, parquets-facing, pebble dash, plaster, render, floor screed, marquees, granolithic finish, terrazzo, cladding, curtain walling, wall in-fills, wallpapers, and ceiling boards, each with its unique process and considerations. The chapter also introduced emerging technologies that are transforming finishing techniques, followed by a focus on smart wall finishes such as advanced aesthetics, heat-reflective coatings, and acoustic finishes that improve building performance. Sustainability was addressed through the discussion of greening practices and the use of renewable resources, particularly natural materials. Finally, the incorporation of recycled content in finishes was highlighted as a key strategy for reducing environmental impact in modern construction.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. Identify five common types of building finishes used in commercial buildings in Kenya. (5 marks)
  2. Explain the procedure for applying plaster as a building finish, including surface preparation steps. (6 marks)
🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Identify five common types of building finishes used in commercial office buildings in Nairobi and explain one key characteristic of each. (4 marks)
  2. Describe the general procedure for applying ceramic tiles on a wet substrate in a residential building. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Apply plaster and render finishes on a 2.5m x 2.0m wall surface

Quantity Survey · Level 6
Building Construction Works II
PRACTICAL ASSESSMENT
TIME: 5 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Prepare and apply plaster and render finishes on a 2500mm wide by 2000mm high internal wall surface ensuring smooth and even coverage.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring Tape (5m)Sand (fine)
Spirit LevelCement (OPC)
TrowelWater
Float
Hawk Board
Mixing Hoe
Wheelbarrow
Bucket
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Measuring Tape (5m)1 Pc per Candidate
2Spirit Level1 Pc per Candidate
3Trowel1 Pc per Candidate
4Float1 Pc per Candidate
5Hawk Board1 Pc per Candidate
6Mixing Hoe1 Pc per 4 Candidates
7Wheelbarrow1 Pc per 4 Candidates
8Bucket1 Pc per Candidate
9WaterSufficient per Candidate
10Sand (fine)Sufficient per Candidate
11Cement (OPC)Sufficient per Candidate
12Protective Gloves1 Pair per Candidate
13Dust Mask1 Pc per Candidate
14Safety Goggles1 Pc per Candidate
15Protective Apron1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Preparation and Application Process
Identified and used appropriate PPE (gloves, dust mask, goggles, apron)
(Award 1 mark for each correct PPE worn)
4
Assembled all necessary tools and materials before starting
(Award 2 marks for assembling all required tools and materials)
2
Prepared the wall surface by cleaning and removing loose particles
(Award 3 marks for thorough surface preparation)
3
Mixed plaster/render with correct cement to sand ratio (1:4) and water to achieve workable consistency
(Award 5 marks for correct mixing ratio and consistency)
5
Applied the first coat (scratch coat) evenly ensuring proper thickness (10mm approx.)
(Award 5 marks for uniform and correct thickness application)
5
Applied the second coat (float coat) smoothly and evenly after initial set of first coat
(Award 5 marks for smooth and even float coat application)
5
Finished with a smooth trowelled surface ensuring no cracks or unevenness
(Award 4 marks for neat, smooth finishing without defects)
4
Cleaned the working area after completion
(Award 2 marks for proper cleaning of the work area)
2
Cleaned and stored tools and materials correctly after use
(Award 2 marks for correct cleaning and storage)
2
Sub-Total32
PRODUCT CHECKLIST
Plastered/rendered wall surface measuring approximately 2500mm wide by 2000mm high within ±50mm tolerance
(Award 5 marks for correct dimensions within tolerance)
5
Wall surface is smooth, even and free from cracks or blisters
(Award 5 marks for surface quality and uniformity)
5
Plaster thickness uniform and consistent at approximately 15mm total thickness
(Award 5 marks for consistent and correct thickness)
5
Rendered finish is well bonded to the wall with no peeling or detachment
(Award 3 marks for good adhesion and bonding)
3
Overall neatness and workmanship of the finished wall
(Award 5 marks for overall presentation and care)
5
Sub-Total23
GRAND TOTAL55
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Mix and lay floor screed with granolithic finish on 2.5m x 2.5m floor area

Quantity Survey · Level 6
Building Construction Works II
PRACTICAL ASSESSMENT
TIME: 5 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Mix and lay floor screed and apply granolithic finish on a 2500mm x 2500mm floor area achieving a durable, level, and smooth surface as per standard practice.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring Tape (5m)Cement
Spirit Level (600mm)Sharp sand
TrowelGranolithic aggregate
FloatWater
Wheelbarrow
Shovel
Compaction rod
Buckets
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Measuring Tape (5m)1 Pc per Candidate
2Spirit Level (600mm)1 Pc per Candidate
3Trowel1 Pc per Candidate
4Float (wooden or plastic)1 Pc per Candidate
5Wheelbarrow1 Pc per 4 Candidates
6Shovel1 Pc per 4 Candidates
7Compaction rod (steel rod 20mm diameter, 600mm long)1 Pc per Candidate
8Buckets (20L capacity)2 Pcs per Candidate
9Water supplySufficient per Candidate
10Cement (Portland cement)5 kg per Candidate
11Sharp sand15 kg per Candidate
12Granolithic aggregate (granite chippings 3-6 mm)10 kg per Candidate
13Protective gloves1 Pair per Candidate
14Safety boots1 Pair per Candidate
15Dust mask1 Pc per Candidate
16Protective eyewear1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: PREPARATION AND MIXING
Identified and used appropriate PPE (gloves, boots, dust mask, eyewear)
(Award 1 mark for each correctly donned PPE item)
5
Assembled all required tools and materials before starting
(Award 0.5 marks for each of six or more tools/materials assembled)
3
Prepared the floor area by cleaning and removing debris
(Award 2 marks for thorough cleaning and clearing)
2
Measured and marked the 2.5m x 2.5m screed area accurately
(Award 1 mark each for correct length, width, and marking method)
3
Mixed floor screed in correct proportion (1:3 cement to sand by volume) with uniform consistency
(Award 4 marks for proper ratio and uniform mix, 2 marks for attempted mixing)
4
Sub-Total17
TASK 2: LAYING AND FINISHING
Laid floor screed evenly to 25mm thickness over the marked area
(Award 4 marks for correct thickness and even application)
4
Compacted screed uniformly using compaction rod immediately after laying
(Award 3 marks for uniform compaction without segregation)
3
Applied granolithic finish mix (1:2 cement to granite chippings) uniformly over screed
(Award 4 marks for proper mix application and coverage)
4
Trowelled and floated granolithic finish to achieve a smooth and level surface
(Award 4 marks for smooth, level and durable finish)
4
Cleaned and stored tools properly after completion
(Award 2 marks for cleaning and correct storage)
2
Sub-Total17
PRODUCT CHECKLIST
Finished floor screed dimensions correct within ±50mm tolerance (2500mm x 2500mm area, 25mm thickness)
(Award 2 marks each for length, width, and thickness within tolerance)
6
Granolithic finish surface is smooth, level, and free from cracks or segregation
(Award 6 marks for durable, uniform, and crack-free finish)
6
Overall neatness and workmanship of the finished floor surface
(Award 4 marks for professional appearance and care)
4
Sub-Total16
GRAND TOTAL50
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Installation of Ceramic Tiles on a 2m x 2m Floor SectionPractical 3
🔒Applying paint finishes on wall surfacePractical 4
🔒Installation of Parquet Flooring 4m x 3mPractical 5
🔒Apply pebble dash finish on an external wall section 3m x 2.5mPractical 6
🔒Installation of External Wall Cladding Panels 2400mm x 1200mmPractical 7
🔒Erect curtain walling system framework and install panels on a building facadePractical 8
🔒Installation of Timber Wall In-Fill Panels within Structural FramesPractical 9
🔒Applying wallpaper finish on a prepared wall surfacePractical 10
🔒Fix ceiling boards on timber framework to 3m x 3m ceiling areaPractical 11
🔒Apply terrazzo flooring finish on a 3m x 3m floor surfacePractical 12
🔒Application of Heat-Reflective and Acoustic Wall Finishes on Interior WallsPractical 13
🔒Apply sustainable natural finishes on interior wall surfacePractical 14
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 19 questions Start quiz ▾
0%
0 / 2
🔒

17 more in this section.

Create a free account