By the end of this chapter, you will be able to:
Mastering these skills will help you ensure water storage systems work safely and efficiently, making you a reliable professional in your trade.
Compiled by: Joseph Njoroge
Test and commissioning of water storage systems and their auxiliary fittings is a critical stage in plumbing projects, ensuring that installations function correctly, safely, and efficiently. In Kenya, plumbing professionals must adhere to stringent safety and health practices during these activities to protect themselves, users, and the environment. Proper safety measures reduce the risk of accidents and contamination, especially in institutions like hospitals and schools where water quality and system reliability directly impact public health. This chapter explores essential safety and health practices that plumbing technicians must observe during the testing and commissioning phases.
Recognizing potential hazards is the first step towards effective safety management in plumbing works involving storage systems. Plumbing technicians in county government water departments or private construction firms must be adept at spotting risks that can arise from water pressure tests, chemical usage, and confined spaces.
Proper PPE is fundamental to safeguarding plumbing personnel during the testing and commissioning of water storage systems. In Kenya, compliance with OSHA regulations mandates the provision and use of appropriate PPE to reduce injury risks.

A pair of protective gloves (Source: Wikimedia Commons)

A single safety boot for industrial use (Source: Wikimedia Commons)

Various types of respiratory masks on faces (Source: Wikimedia Commons)

Green hard hat worn by worker (Source: Wikipedia (Hard hat))
Chemical agents such as chlorine or other disinfectants are commonly used to ensure water quality during commissioning of storage tanks. Their handling and disposal require strict safety measures to protect workers and the environment.
Despite preventive measures, accidents may occur during the test and commissioning of water storage systems. Plumbing professionals must be prepared to respond promptly and effectively.
Explain five common hazards associated with testing and commissioning of water storage systems and how they can be mitigated. (10 marks)
Describe the types of personal protective equipment necessary for plumbing professionals during commissioning and their maintenance requirements. (10 marks)
Outline the procedures for safe handling and disposal of chemicals used in water storage system commissioning in Kenya. (10 marks)
Discuss the key elements of emergency preparedness and first aid measures relevant to plumbing work during commissioning. (10 marks)
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter covered essential safety and health practices necessary during the testing and commissioning of water storage systems to ensure a secure working environment. It explained various functionality tests designed to verify the performance and reliability of storage tanks and their auxiliary fittings. The chapter identified the specific tools and equipment required to carry out these tests effectively. Common faults that may arise during testing were discussed, emphasizing their impact on system operation. Methods for correcting these faults were detailed, highlighting practical approaches to restore proper function. Finally, the chapter outlined the commissioning process, which involves final inspections and approvals to confirm that the water storage system is ready for use. Together, these topics provide a comprehensive guide to ensuring water storage systems operate safely and efficiently from installation through to operational readiness.
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Personal Protective Equipment (Safety boots, Gloves, Helmet, Overall, Hearing protector) | First aid kit |
| Pipe wrench | Waste disposal bags |
| Tape measure | |
| Hacksaw | |
| Flashlight | |
| Inspection checklist form |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Personal Protective Equipment (Safety boots, Gloves, Helmet, Overall, Hearing protector) | Full set per Candidate |
| 2 | Inspection checklist form | 1 per Candidate |
| 3 | Flashlight | 1 per Candidate |
| 4 | Pipe wrench | 1 per Candidate |
| 5 | Tape measure | 1 per Candidate |
| 6 | Hacksaw | 1 per Candidate |
| 7 | Hand gloves | 1 pair per Candidate |
| 8 | First aid kit | 1 shared per 5 Candidates |
| 9 | Waste disposal bags | 2 bags per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Conduct Safety Inspection and Demonstrate Health Practices | |||
| Wears all required personal protective equipment correctly (Award 1 mark for each correctly worn PPE or zero) | 3 | ||
| Identifies and inspects all safety hazards around the storage system area (Award 4 marks for thorough hazard identification or zero) | 4 | ||
| Checks and verifies condition of storage tank fittings and auxiliary components (Award 3 marks for correct identification and condition check or zero) | 3 | ||
| Demonstrates safe handling of tools and equipment during inspection (Award 3 marks for safe handling or zero) | 3 | ||
| Completes inspection checklist accurately and legibly (Award 3 marks for completeness and accuracy or zero) | 3 | ||
| Demonstrates correct waste disposal methods for inspection debris (Award 2 marks for proper disposal or zero) | 2 | ||
| Demonstrates emergency response procedure including location and use of first aid kit (Award 2 marks for demonstration or zero) | 2 | ||
| Sub-Total | 20 | ||
| PRODUCT CHECKLIST | |||
| Completed safety inspection checklist with all items addressed (Award 5 marks for fully completed checklist or zero) | 5 | ||
| Sub-Total | 5 | ||
| GRAND TOTAL | 25 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Pipe Wrench | 5000L Poly Plastic Storage Tank |
| Adjustable Spanner | 1/2 inch Ball Valve |
| Measuring Tape | 1/2 inch Gate Valve |
| 1/2 inch Tank Connector | |
| 20mm GI Union | |
| Thread Seal Tape | |
| Hose Pipe | |
| Safety Boots | |
| Overall | |
| Gloves |
| S/N | Item | Quantity |
|---|---|---|
| 1 | 5000L Poly Plastic Storage Tank | 1 Pc per Candidate |
| 2 | 1/2 inch Ball Valve | 2 Pcs per Candidate |
| 3 | 1/2 inch Gate Valve | 1 Pc per Candidate |
| 4 | 1/2 inch Tank Connector | 2 Pcs per Candidate |
| 5 | 20mm (3/4") GI Union | 2 Pcs per Candidate |
| 6 | Thread Seal Tape | 3 Rolls per Candidate |
| 7 | Hose Pipe (sufficient length to water source) | 5 m per Candidate |
| 8 | Pipe Wrench | 1 Pc per Candidate |
| 9 | Adjustable Spanner | 1 Pc per Candidate |
| 10 | Measuring Tape | 1 Pc per Candidate |
| 11 | Safety Boots | 1 Pair per Candidate |
| 12 | Overall | 1 Pc per Candidate |
| 13 | Gloves | 1 Pair per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Functionality Testing of Storage Tank Valves | |||
| Used personal protective equipment in line with occupational safety and health requirements (Safety boots, Overall, Gloves) (Award 1 mark for each PPE used or zero x 3 = 3 Marks) | 3 | ||
| Identified valves and fittings according to job requirements (Award 2 marks for correct identification or zero) | 2 | ||
| Checked tightness and proper installation of tank connectors and unions (Award 3 marks for correct checking or zero) | 3 | ||
| Applied thread seal tape correctly on valve threads (Award 2 marks for correct application or zero) | 2 | ||
| Operated ball valve to test smooth opening and closing (Award 3 marks for smooth operation or zero) | 3 | ||
| Operated gate valve to test smooth opening and closing (Award 3 marks for smooth operation or zero) | 3 | ||
| Checked valves for leaks and proper sealing under water pressure (Award 4 marks for leak-free operation or zero) | 4 | ||
| Documented test results and reported any faults found (Award 2 marks for complete and clear documentation or zero) | 2 | ||
| Sub-Total | 22 | ||
| PRODUCT CHECKLIST | |||
| Valves installed and tested on 5000L tank with proper functionality: opening, closing, sealing verified (Award 5 marks for valves functioning as per specifications or zero) | 5 | ||
| Measurements: Tank capacity 5000L and valve sizes 1/2 inch confirmed (Award 3 marks for correct confirmation or zero) | 3 | ||
| No visible leakage or defects on tested valves and fittings (Award 4 marks for no leakage or defects or zero) | 4 | ||
| General neatness and completeness of valve assembly and testing area (Award 3 marks for neat, complete setup or zero) | 3 | ||
| Sub-Total | 15 | ||
| GRAND TOTAL | 37 | ||
At the start of this chapter we promised you would be able to: