Mastering these skills helps you create reliable maps and data that are essential for safe and efficient mining operations.
Conducting accurate and reliable mapping is a fundamental responsibility of a land surveyor engaged in mine survey activities. The process involves detailed measurement and recording of the terrain and features within a mining area to support planning, development, and safety management. Among the core surveying techniques, levelling plays a critical role in determining height differences and establishing vertical control, which is essential for preparing precise mine maps. In the Kenyan mining sector, where terrain variability and safety considerations are paramount, mastering levelling techniques ensures that survey data supports efficient resource extraction and regulatory compliance.
Levelling in mine surveying is the process of determining the relative heights of points on or near the earth’s surface. This technique is vital for creating contour maps, designing drainage systems, and planning excavation works in mines. In Kenya, where mining activities often occur in rugged and varied topography, accurate levelling helps surveyors produce reliable vertical data that informs safe and effective mine operations. The technique requires precise instruments and systematic procedures to minimize errors and achieve the desired accuracy.
Understanding the fundamental principles and objectives of levelling is crucial for mine surveyors to apply the technique effectively in the field. Levelling relies on establishing a horizontal line of sight from a known reference point to determine the elevation of other points. The primary objectives focus on obtaining accurate height differences and ensuring vertical control across the mining site.
Mine surveyors employ various levelling methods, each suited to different requirements and site conditions. Selecting the appropriate levelling type depends on the accuracy needed, terrain complexity, and available equipment.
Spirit levelling is the most common and precise method used in mine surveying. It involves a dumpy or automatic level instrument and a graduated levelling staff. The surveyor reads the staff at different points to calculate height differences relative to a benchmark. This method is preferred for establishing primary vertical control and detailed contouring because of its high accuracy.
Trigonometric levelling uses angular measurements and distance to calculate height differences. By measuring vertical angles to a target point and the horizontal distance from the instrument, the height difference is computed using trigonometric formulas. This method is useful in inaccessible or steep areas where direct levelling is difficult. However, it is less accurate than spirit levelling and is often used to complement it.
Barometric levelling estimates elevation differences based on atmospheric pressure readings from a barometer. Since atmospheric pressure decreases with height, changes in pressure readings can approximate height differences. Although quick and useful for reconnaissance surveys, barometric levelling lacks the precision required for detailed mine mapping and is rarely used for final data.
Differential levelling involves measuring height differences between points over a long distance, often combining several levelling setups. This method is essential for establishing a vertical control network that spans the entire mining area. It requires careful planning to ensure continuity and accuracy across the traverse.
Successful levelling depends on the proper selection, handling, and maintenance of surveying instruments. The key equipment used in levelling includes the levelling instrument, levelling staff, tripods, and accessories.
| Name | Specification | Use |
|---|---|---|
| Automatic Level | Telescope with internal compensator, 24x magnification | Provides horizontal line of sight for height measurements |
| Levelling Staff | Graduated staff, typically 5 meters with markings in millimeters | Held vertically on points to read height on instrument |
| Tripod | Adjustable legs, stable base for instrument | Supports and stabilizes the levelling instrument |
| Plumb Bob | Weighted string for vertical alignment | Ensures levelling staff is held vertically |
| Measuring Tape | Steel or fiberglass, 30m or longer | Measures distances during trigonometric levelling |
Levelling instruments such as the automatic level are preferred in mine surveying for their ease of use and reliable horizontal line of sight. The levelling staff must be held perfectly vertical to avoid errors, which is aided by using a plumb bob. Tripods provide a stable platform for the instrument, minimizing vibrations and movement during readings.
Routine maintenance includes cleaning optical parts with lens tissue, checking and adjusting the instrument’s internal compensator, and ensuring the levelling staff’s graduations are clearly visible and undamaged. Proper storage in protective cases prevents damage during transport between mining sites.
Spirit levelling requires a systematic approach to obtain accurate height data. The procedure involves setting up the instrument, taking readings, recording data, and calculating reduced levels.
When conducting levelling over long distances, the instrument must be moved forward along the survey line, repeating the process to maintain accuracy. Careful recording in field books and cross-checking calculations minimize errors.
Example: At a county government quarry site, surveyors used spirit levelling to establish vertical control points to guide excavation depths. Accurate RLs ensured that the pit benches were cut to safe heights, minimizing collapse risk and facilitating drainage design.
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter on conducting mapping in mine surveying begins with levelling, which involves determining height differences between points to create accurate ground profiles essential for mine planning. The process of traversing follows, where a series of connected survey lines are measured to establish control networks that guide detailed mapping and ensure positional accuracy. Calculating resource volumes is then explored, focusing on how survey data is used to estimate the quantity of mineral deposits or excavated material, a critical factor for operational and financial decision-making. The chapter concludes with field measurements, emphasizing the practical techniques and instruments used to collect reliable data in the challenging mining environment. Together, these topics provide a comprehensive understanding of how precise mapping supports efficient mine development and resource management.
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Dumpy Level with tripod | Pegs |
| Levelling staff | Writing materials |
| Measuring tape | Calculator |
| Mallet | Personal Protective Equipment (PPE) |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Dumpy Level with tripod | 1 Pc per Candidate |
| 2 | Levelling staff (3 m graduated) | 1 Pc per Candidate |
| 3 | Measuring tape (30 m steel) | 1 Pc per Candidate |
| 4 | Pegs | 6 Pcs per Candidate |
| 5 | Mallet | 1 Pc per 5 Candidates |
| 6 | Writing materials (field notebook, pencil) | 1 Set per Candidate |
| 7 | Calculator (scientific) | 1 Pc per Candidate |
| 8 | Personal Protective Equipment (PPE) - apron/dust coat, boots/closed shoes | 1 Set per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: PPE and site preparation | |||
| Identified and used PPE appropriately: apron/dust coat and boots/closed shoes (Award 1 mark for correct PPE use) | 1 | ||
| Selected a suitable, level site and pegged points A, B, and C approximately 15 m apart in a straight line (Award 1 mark for correct site selection, 1 mark for proper pegging) | 2 | ||
| Sub-Total | 3 | ||
| TASK 2: Instrument setup and levelling | |||
| Correctly mounted and centred the dumpy level on the tripod over a stable point (Award 1 mark for proper instrument mounting and centring) | 1 | ||
| Levelled the instrument accurately by adjusting the foot screws and checked the spirit bubble (Award 2 marks for accurate levelling) | 2 | ||
| Focused the telescope on the levelling staff held vertically at each point (Award 1 mark for correct focusing) | 1 | ||
| Sub-Total | 4 | ||
| TASK 3: Taking and recording readings | |||
| Measured and recorded backsight (BS), intermediate sight (IS), and foresight (FS) readings correctly for points A, B, and C (Award 1 mark for each point’s readings correctly taken and recorded) | 3 | ||
| Booked all readings clearly and systematically in the field notebook (Award 2 marks for neat and complete booking) | 2 | ||
| Sub-Total | 5 | ||
| TASK 4: Level reduction and checks | |||
| Reduced levels calculated correctly using the rise and fall method (Award 3 marks for accurate reduction) | 3 | ||
| Performed arithmetic checks (e.g. check of sum of rises and falls) (Award 2 marks for correct arithmetic checks) | 2 | ||
| Sub-Total | 5 | ||
| TASK 5: Plotting results | |||
| Plotted the survey line with points A, B, and C in correct relative positions (Award 3 marks for correct plotting) | 3 | ||
| Marked the reduced levels at each point clearly on the plot (Award 2 marks for correct annotation) | 2 | ||
| Used a suitable scale (e.g. 1:500) and neat presentation on foolscap paper (Award 2 marks for neatness and scale choice) | 2 | ||
| Sub-Total | 7 | ||
| PRODUCT CHECKLIST | |||
| Accurate height difference measurements between points A, B, and C within ±5 mm tolerance (Award 4 marks for measurements within tolerance) | 4 | ||
| Correct and complete field notes including BS, IS, FS readings and calculated reduced levels (Award 3 marks for complete and accurate field notes) | 3 | ||
| Neat, to-scale plot showing points A, B, C with reduced levels clearly indicated (Award 3 marks for neatness and accuracy in plotting) | 3 | ||
| Sub-Total | 10 | ||
| GRAND TOTAL | 34 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Total Station with accessories | Pegs |
| Handheld GPS Receiver | Writing materials (foolscap notebook, pencil, eraser) |
| 30 m steel tape | Printer and A4 printing materials |
| Mallet | |
| Scientific Calculator | |
| Computer with Microsoft Excel and ArcGIS/AutoCAD installed |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Total Station with accessories | 1 per 1 Candidate |
| 2 | Handheld GPS Receiver | 1 per 1 Candidate |
| 3 | 30 m steel tape | 1 per 1 Candidate |
| 4 | Pegs | 6 per 1 Candidate |
| 5 | Mallet | 1 per 5 Candidates |
| 6 | Writing materials (foolscap notebook, pencil, eraser) | 2 sets per 1 Candidate |
| 7 | Scientific Calculator | 1 per 1 Candidate |
| 8 | Computer with Microsoft Excel and ArcGIS/AutoCAD installed | 1 per 5 Candidates |
| 9 | Printer and A4 printing materials | 1 printer per 5 Candidates; 2 A4 sheets per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Use of PPE | |||
| Identified and used apron or dust coat appropriately (Award 1 mark for correct PPE use) | 1 | ||
| Wore boots or closed shoes correctly (Award 1 mark for correct PPE use) | 1 | ||
| Sub-Total | 2 | ||
| TASK 2: Site selection and polygon setting out | |||
| Selected a suitable site for the closed traverse polygon (Award 1 mark for correct site selection) | 1 | ||
| Measured and marked out a rectangle of 45m by 15m on the ground (Award 1 mark for accurate measurement and marking) | 1 | ||
| Pegged the corners of the polygon correctly and labelled points A, B, C, D (Award 2 marks for correct pegging and labelling) | 2 | ||
| Sub-Total | 4 | ||
| TASK 3: Measurement of angles and distances | |||
| Configured and set up the total station at starting point A (Award 1 mark for correct setup) | 1 | ||
| Oriented the total station to the next traverse point correctly (Award 1 mark for correct orientation) | 1 | ||
| Measured horizontal angles at each traverse station accurately (Award 1 mark per station for three angles) | 3 | ||
| Measured distances between traverse stations using steel tape or total station (Award 1 mark per distance for four sides and one diagonal) | 3 | ||
| Recorded all measurements legibly and systematically in field notes (Award 1 mark for accurate recording) | 1 | ||
| Sub-Total | 9 | ||
| TASK 4: Coordinate determination and area computation | |||
| Computed coordinates of traverse stations using the recorded angles and distances (Award 1 mark per station for four stations) | 4 | ||
| Arranged coordinates correctly in a coordinate table (Award 1 mark for correct tabulation) | 1 | ||
| Computed the area of the polygon using the coordinate method accurately (Award 3 marks for correct area calculation) | 3 | ||
| Sub-Total | 8 | ||
| TASK 5: Data processing and map preparation | |||
| Entered coordinates into Microsoft Excel correctly and saved as .csv file (Award 2 marks for correct data entry and saving) | 2 | ||
| Imported coordinates into ArcGIS or AutoCAD and displayed points accurately (Award 2 marks for correct import and display) | 2 | ||
| Digitized and joined points to form a closed polygon matching ground layout (Award 3 marks for accurate digitizing and joining) | 3 | ||
| Prepared and printed a neat mine map on A4 paper including title, scale, and neat line (Award 3 marks for complete and neat map preparation) | 3 | ||
| Sub-Total | 10 | ||
| PRODUCT CHECKLIST | |||
| Polygon dimensions on map match 45m length and 15m width within ±0.1m accuracy (Award 3 marks for correct polygon dimensions) | 3 | ||
| Traverse stations coordinates are accurate and consistent with field measurements (Award 3 marks for coordinate accuracy) | 3 | ||
| Area computed matches polygon dimensions with correct units and method (Award 2 marks for correct area computation) | 2 | ||
| Map is clear, legible, and includes title, scale bar, and neat line on A4 paper (Award 2 marks for map presentation quality) | 2 | ||
| Sub-Total | 10 | ||
| GRAND TOTAL | 43 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.