Land Survey  ·  Level 6
Mine Survey
Chapter 2: Set out mine works
📚 3 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • Prepare the mining site correctly according to the job requirements.
  • Perform staking accurately to mark out mine works as needed.
  • Carry out necessary checks and make adjustments correctly based on job needs.
  • Assess the accuracy of mine plans by comparing them to job plans and requirements.
  • Complete practical mine surveying tasks effectively and to standard.
  • Carry out project work related to mine surveying with quality and precision.
  • Prepare and understand third-party reports related to mine surveying.
  • Gather and integrate survey data accurately, and compile clear reports following workplace procedures.
  • Develop plans that help optimize mining processes according to job requirements.

Mastering these skills will help you contribute confidently and safely to successful mining operations!

Mining site preparation is a foundational phase in mine surveying that ensures the site is ready for safe and efficient mining operations. In Kenya, where mining activities range from small-scale artisanal ventures to large commercial enterprises, proper preparation minimizes risks and facilitates accurate setting out of mine works. This chapter focuses on the critical tasks land surveyors undertake to prepare mining sites, aligning surveying precision with operational requirements. Effective site preparation supports compliance with regulatory standards and optimizes resource extraction.

2.1 Mining Site Preparation

Mining site preparation involves a series of coordinated activities to ready the terrain and environment for mining operations. Surveyors play a pivotal role in this stage by providing accurate spatial data, establishing control points, and ensuring the site conforms to design specifications. In Kenya, mining sites often face challenges such as irregular terrain, environmental sensitivity, and proximity to community settlements, necessitating meticulous preparation.

2.1.1 Initial Site Assessment and Reconnaissance

Initial site assessment involves gathering comprehensive information about the mining location to inform subsequent surveying and mining activities. This step is essential for identifying potential constraints, hazards, and features that influence mine design and setting out.

Site Evaluation Objectives

  • Topographical Surveying: Capturing the natural surface features and elevations provides a baseline for planning excavation and infrastructure placement. Accurate topographical data is vital for drainage design and slope stability analysis.
  • Geological Mapping: Understanding rock formations, faults, and mineral deposits guides the positioning of shafts, adits, and pits, ensuring efficient resource extraction.
  • Environmental Considerations: Identifying protected areas, water bodies, and vegetation helps in designing mitigation measures to minimize ecological impact, complying with NEMA guidelines.
  • Access and Infrastructure Review: Assessing existing roads, power supply, and water availability informs logistical planning and site accessibility.
  • Community and Land Use Survey: Evaluating nearby settlements and land ownership clarifies social impact and legal compliance under Kenyan mining laws.

Reconnaissance Survey Techniques

  • Preliminary GPS Mapping: Utilizing handheld GPS devices to quickly locate key features and boundaries.
  • Drone Imagery: Employing unmanned aerial vehicles to capture aerial photographs for detailed site visualization.
  • Walkover Surveys: Physically inspecting the site to note obstacles, hazardous zones, and potential survey control points.
  • Soil and Terrain Sampling: Collecting samples to assess ground conditions for foundation and excavation stability.
  • Stakeholder Consultations: Engaging local authorities and communities to gather insights and address concerns early.

2.1.2 Establishment of Survey Control Network

A robust survey control network is critical for accurate mine layout and ongoing monitoring. This network comprises fixed reference points whose positions are precisely determined to serve as the foundation for all survey measurements.

Principles of Control Network Design

  • Stability of Control Points: Control markers must be placed on stable ground to avoid displacement caused by mining activities or environmental factors.
  • Visibility and Accessibility: Points should be clearly visible and easily accessible for repeated surveys throughout the mine lifecycle.
  • Redundancy: Establishing multiple control points provides backup in case of marker loss or damage.
  • Geodetic Accuracy: Control points are tied to national coordinate systems such as the Kenya Coordinate Reference System to ensure consistency.
  • Integration with Existing Networks: Linking new control points with established geodetic benchmarks enhances reliability.

Methods for Control Point Establishment

  • Total Station Traversing: Using total stations to measure angles and distances between points with high precision.
  • GNSS Surveying: Employing Global Navigation Satellite Systems for rapid and accurate coordinate determination.
  • Benchmark Installation: Placing durable markers such as concrete pillars or metal discs at control locations.
  • Leveling Surveys: Determining precise elevations to support vertical control for underground and surface works.
  • Documentation and Mapping: Recording coordinates, descriptions, and sketches of control points for future reference.

2.1.3 Clearing and Preparation of Site Ground

Before setting out mine works, the physical ground must be cleared and prepared to facilitate safe and precise surveying and construction activities. This process involves removing obstacles and ensuring the site surface is suitable for equipment and personnel.

Clearing Procedures

  • Vegetation Removal: Cutting and clearing shrubs, trees, and undergrowth to open access and improve visibility for survey operations.
  • Debris and Obstruction Removal: Eliminating rocks, waste materials, and abandoned equipment that could hinder movement or damage instruments.
  • Surface Leveling: Grading uneven surfaces to create stable platforms for survey equipment and construction machinery.
  • Drainage Management: Constructing temporary channels or berms to prevent water accumulation that could affect site stability.
  • Safety Measures: Marking hazardous zones and ensuring cleared areas are free from underground cables or pipelines.

Preparation for Surveying

  • Establishing Temporary Markers: Placing stakes or flags to identify key survey points and boundaries.
  • Construction of Access Paths: Creating walkways or vehicle tracks to facilitate movement of personnel and equipment.
  • Site Security: Installing fencing or barriers to protect control points and prevent unauthorized access.
  • Equipment Calibration Zones: Designating areas for setting up and calibrating surveying instruments.
  • Communication Setup: Ensuring reliable communication channels for coordination during survey activities.

2.1.4 Compliance with Regulatory and Environmental Requirements

Mining site preparation must align with Kenyan legal frameworks and environmental standards to avoid penalties and ensure sustainable operations. Surveyors contribute by verifying that site layouts respect these requirements.

Regulatory Compliance Aspects

  • Mining Licenses and Permits: Verifying the validity and scope of mining permits issued by the Ministry of Mining.
  • Land Use Approvals: Ensuring that mining activities do not encroach on protected or reserved lands under county government plans.
  • Safety Regulations: Adhering to Occupational Safety and Health Act provisions by planning safe access and emergency routes.
  • Environmental Impact Assessments (EIA): Supporting EIA processes through accurate mapping of sensitive zones and proposed disturbance areas.
  • Reporting and Documentation: Maintaining detailed records of site preparation activities for audits by agencies such as NEMA.

Environmental Protection Measures

  • Buffer Zones: Establishing no-go areas around water bodies and conservation sites to prevent contamination.
  • Erosion Control: Implementing measures such as silt fences and re-vegetation plans to minimize soil loss.
  • Waste Management Plans: Designing designated areas for waste disposal away from critical habitats.
  • Water Management: Ensuring that surface and groundwater flows are not adversely affected by site preparation.
  • Community Engagement: Facilitating consultations and information sharing with local communities to address environmental concerns.

Practice Questions

  1. Explain the role of initial site assessment in mining site preparation and list five key objectives involved in this process. (10 marks)
  2. Describe the principles guiding the establishment of a survey control network in mine surveying. (10 marks)
  3. Outline six steps involved in clearing and preparing the ground of a mining site for survey operations. (12 marks)
  4. Discuss five regulatory and environmental compliance requirements that must be observed during mining site preparation in Kenya. (10 marks)
The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒2.2 Staking

Staking is a fundamental activity in mine surveying that involves marking out positions on the ground to guide excavation, construction, and other mining operations. In the Kenyan mining sector, accurate staking ensures that mine workings follow approved desig…

🔒2.3 Checks and adjustment

In mine surveying, the precision of set out works is critical to ensure safety, operational efficiency, and compliance with regulatory standards. Given the complexities of underground environments and the high stakes involved in mining operations, rigorous che…

Chapter Summary

This chapter has explored the essential stages involved in setting out mine works, beginning with mining site preparation. It emphasized the importance of clearing and leveling the area to ensure accurate measurements and safe operations. The process of staking was examined next, highlighting how precise marking of boundaries and key points guides excavation and construction activities. Finally, the chapter addressed the critical role of checks and adjustment, which involve verifying measurements and correcting any discrepancies to maintain alignment with design specifications. Together, these steps ensure that mining projects proceed efficiently, safely, and according to plan. Mastery of these procedures is fundamental for surveyors working in the mining industry to support successful project execution.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. What are the key considerations during the preparation of a mining site before any survey work begins? (3 marks)
  2. Define staking in the context of mine surveying and explain its importance. (3 marks)
🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Explain the key considerations that must be made during mining site preparation to ensure accurate mine survey set out. (4 marks)
  2. Describe the role of staking in mine surveying and how it affects mine development in a Kenyan gold mine. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Prepare mining site for accurate staking and survey

Land Survey · Level 6
Mine Survey
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Prepare and clear a rectangular mining site measuring 30,000mm by 15,000mm for staking and survey works.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Safety helmetPegs
Apron/dust coat
Safety boots
30 m steel tape
Mallet
Pegs
Handheld GPS Receiver
Scientific calculator
Writing materials
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Safety helmet1 Pc per Candidate
2Apron/dust coat1 Pc per Candidate
3Safety boots1 Pair per Candidate
430 m steel tape1 Pc per Candidate
5Mallet1 Pc per 3 Candidates
6Pegs6 Pcs per Candidate
7Handheld GPS Receiver1 Pc per 2 Candidates
8Writing materials (foolscap sheets, pen)2 Sheets and 1 Pen per Candidate
9Scientific calculator1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Use of PPE
Identified and wore safety helmet
(Award 1 mark for correctly wearing helmet)
1
Wore apron/dust coat
(Award 1 mark for correctly wearing apron/dust coat)
1
Wore safety boots
(Award 1 mark for correctly wearing safety boots)
1
Sub-Total3
TASK 2: Site selection and clearing
Selected a suitable flat and accessible mining site
(Award 1 mark for correct site selection)
1
Cleared vegetation and debris within the 30m x 15m area
(Award 2 marks for thorough clearing of the site)
2
Marked and pegged the four corners of the rectangular site accurately
(Award 2 marks for correct pegging and marking)
2
Sub-Total5
TASK 3: Measurement and recording
Measured and confirmed the length of 30,000mm and width of 15,000mm using a steel tape
(Award 2 marks for accurate measurement)
2
Recorded measurements and site coordinates correctly in writing materials
(Award 2 marks for accurate recording)
2
Used handheld GPS receiver to record coordinates of the four corner points
(Award 2 marks for correct GPS use and recording)
2
Sub-Total6
TASK 4: Final site preparation
Checked and ensured pegs are firmly fixed and visible
(Award 1 mark for firm pegging)
1
Ensured site is free from obstacles and ready for staking and survey works
(Award 1 mark for readiness confirmation)
1
Sub-Total2
PRODUCT CHECKLIST
Rectangular site correctly pegged at 30,000mm by 15,000mm with visible and firmly fixed pegs
(Award 3 marks for correct dimensions and pegging)
3
Accurate recording of four corner coordinates in writing materials and GPS readings
(Award 3 marks for accuracy and completeness)
3
Sub-Total6
GRAND TOTAL22
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Set out mine access road alignment 60m x 5m

Land Survey · Level 6
Mine Survey
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Set out and stake the alignment of a mine access road 60m long and 5m wide.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Total Station with accessoriesPegs
Handheld GPS ReceiverPrinting materials (A4 size)
30 m steel tape
Mallet
Scientific Calculator
Writing materials (foolscap paper)
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Total Station with accessories1 per 3 Candidates
2Handheld GPS Receiver1 per 3 Candidates
330 m steel tape1 per Candidate
4Pegs10 Pcs per Candidate
5Mallet1 per 5 Candidates
6Writing materials (foolscap paper)2 Sheets per Candidate
7Scientific Calculator1 per Candidate
8Printing materials (A4 size)2 Sheets per Candidate
9Printer/Plotter1 per 5 Candidates
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Use of PPE
Identified and wore apron or dust coat
(Award 1 mark if worn correctly)
1
Identified and wore boots or closed shoes
(Award 1 mark if worn correctly)
1
Sub-Total2
TASK 2: Site selection and initial point marking
Selected a suitable flat site for road alignment
(Award 1 mark for correct site selection)
1
Marked and pegged two intervisible points 60m apart for road length
(Award 2 marks if points are correctly spaced and visible)
2
Sub-Total3
TASK 3: Measurement and coordinate recording
Configured handheld GPS receiver correctly
(Award 1 mark for correct configuration)
1
Measured and recorded coordinates of the two end points (N, E, Z)
(Award 2 marks if coordinates recorded accurately)
2
Sub-Total3
TASK 4: Total Station setup and orientation
Mounted tripod stand correctly over first point
(Award 1 mark if tripod is stable and centred)
1
Levelled and centred total station over the point
(Award 2 marks if instrument is levelled and centred accurately)
2
Oriented total station to the second point
(Award 2 marks if orientation is precise)
2
Sub-Total5
TASK 5: Setting out road width and staking alignment
Measured and pegged road width of 5m along the length at correct intervals
(Award 3 marks if width is consistent and stakes are well aligned)
3
Labelled pegs correctly according to layout plan
(Award 1 mark for correct labelling)
1
Sub-Total4
TASK 6: Recording and plotting
Recorded all peg coordinates accurately in field notes
(Award 2 marks if records are complete and accurate)
2
Plotted alignment on graph paper or software as per layout
(Award 3 marks for neatness and accuracy)
3
Sub-Total5
PRODUCT CHECKLIST
Road alignment set out correctly with length 60,000 mm and width 5,000 mm with correct peg positions and labels
(Award up to 10 marks for accuracy within ±0.1m, correct peg spacing, and alignment per drawing)
10
Sub-Total10
GRAND TOTAL32
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Check and Adjust Survey Instruments for Mine Work Setting OutPractical 3
🔒Verify staking accuracy with site checks for a 30m x 12m mine shaft layoutPractical 4
🔒Prepare and level a drilling site area 30m by 20m for mining operationsPractical 5
🔒Adjust and level theodolite for staking mine worksPractical 6
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 17 questions Start quiz ▾
0%
0 / 2
🔒

15 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Prepare the mining site correctly according to the job requirements.
  • Perform staking accurately to mark out mine works as needed.
  • Carry out necessary checks and make adjustments correctly based on job needs.
  • Assess the accuracy of mine plans by comparing them to job plans and requirements.
  • Complete practical mine surveying tasks effectively and to standard.
  • Carry out project work related to mine surveying with quality and precision.
  • Prepare and understand third-party reports related to mine surveying.
  • Gather and integrate survey data accurately, and compile clear reports following workplace procedures.
  • Develop plans that help optimize mining processes according to job requirements.

Tick each one you can genuinely do.