Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring tape | Concrete mix ratio chart |
| Calculator | |
| Notebook and pen |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring tape | 1 Pc per Candidate |
| 2 | Calculator | 1 Pc per Candidate |
| 3 | Notebook and pen | 1 set per Candidate |
| 4 | Concrete mix ratio chart | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Safety and Preparation | |||
| Appropriately wore PPE (dust coat, safety boots) (Award 1 mark for correct PPE use or zero) | 1 | ||
| Correctly observed safety on self and colleagues (Award 1 mark for safety observation or zero) | 1 | ||
| Correctly observed safety of tools and equipment by proper handling (Award 1 mark for correct tool handling or zero) | 1 | ||
| Sub-Total | 3 | ||
| TASK 2: Work Area Setup and Measurement | |||
| Prepared and cleared the working area (Award 1 mark for area readiness or zero) | 1 | ||
| Accurately measured the slab dimensions (length, width, depth) (Award 2 marks for correct measurements or zero) | 2 | ||
| Recorded measurements clearly and legibly (Award 1 mark for proper recording or zero) | 1 | ||
| Sub-Total | 4 | ||
| TASK 3: Quantity Estimation | |||
| Calculated slab volume correctly using measured dimensions (Award 3 marks for accurate volume calculation or zero) | 3 | ||
| Estimated quantity of concrete mix required based on volume and mix ratio (Award 3 marks for correct quantity estimate or zero) | 3 | ||
| Used calculator effectively for computations (Award 1 mark for correct calculator use or zero) | 1 | ||
| Recorded final quantities clearly in notebook (Award 1 mark for clear recording or zero) | 1 | ||
| Sub-Total | 8 | ||
| TASK 4: Housekeeping and Tool Storage | |||
| Cleaned the work area after task completion (Award 1 mark for cleaning or zero) | 1 | ||
| Properly stored tools and materials (Award 1 mark for correct storage or zero) | 1 | ||
| Sub-Total | 2 | ||
| PRODUCT CHECKLIST | |||
| Correct volume calculation for slab (2000x2000x150 mm = 0.6 m³) (Award 3 marks for correct volume or zero) | 3 | ||
| Accurate concrete quantity estimate based on volume and mix ratio (Award 3 marks for correct quantity or zero) | 3 | ||
| Clear and legible recording of all measurements and calculations (Award 2 marks for clarity or zero) | 2 | ||
| Sub-Total | 8 | ||
| GRAND TOTAL | 25 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape | Standard Bricks (230mm x 110mm x 75mm) |
| Calculator | Mortar Mix (Sand and Cement) |
| Pencil and Notebook |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Standard Bricks (230mm x 110mm x 75mm) | 500 Pcs per Candidate |
| 2 | Measuring Tape | 1 Pc per Candidate |
| 3 | Calculator | 1 Pc per Candidate |
| 4 | Pencil and Notebook | 1 Set per Candidate |
| 5 | Mortar Mix (Sand and Cement) | 1 Bag per 3 Candidates |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Check Presentation and Safety | |||
| Appropriately wore PPE (dust coat, safety boots) (Award 1 mark for correct PPE usage, 0 if not) | 1 | ||
| Observed safety for self and colleagues (Award 1 mark for correct safety observation, 0 if not) | 1 | ||
| Handled tools and equipment safely (Award 1 mark for correct handling, 0 if not) | 1 | ||
| Sub-Total | 3 | ||
| TASK 2: Prepare Work Area and Tools | |||
| Arranged work area free from hazards (Award 1 mark for safe and clean area, 0 if not) | 1 | ||
| Selected appropriate tools and materials for estimation (Award 1 mark for correct selection, 0 if not) | 1 | ||
| Sub-Total | 2 | ||
| TASK 3: Perform Measurement and Calculations | |||
| Measured wall dimensions accurately (Award 2 marks for accurate measurements, 0 if incorrect) | 2 | ||
| Calculated wall volume correctly (Award 3 marks for correct volume calculation, 0 if incorrect) | 3 | ||
| Calculated brick volume including mortar allowance (Award 2 marks for correct brick volume with mortar, 0 if incorrect) | 2 | ||
| Estimated total number of bricks required (Award 3 marks for correct brick quantity estimate, 0 if incorrect) | 3 | ||
| Sub-Total | 10 | ||
| TASK 4: Record and Present Findings | |||
| Clearly recorded all measurements and calculations (Award 2 marks for clear and accurate recording, 0 if not) | 2 | ||
| Presented estimation logically and neatly (Award 2 marks for neat presentation, 0 if not) | 2 | ||
| Sub-Total | 4 | ||
| TASK 5: Observe Housekeeping | |||
| Cleaned work area after task completion (Award 1 mark for cleanliness, 0 if not) | 1 | ||
| Properly stored tools and materials (Award 1 mark for proper storage, 0 if not) | 1 | ||
| Sub-Total | 2 | ||
| PRODUCT CHECKLIST | |||
| Estimated number of bricks matches calculation within 5% tolerance (Award 5 marks for correct estimate, 0 if outside tolerance) | 5 | ||
| Calculation of wall volume is accurate (4000mm x 2500mm x 300mm) (Award 3 marks for correct volume calculation, 0 if incorrect) | 3 | ||
| Brick dimensions correctly applied including mortar allowance (Award 2 marks for correct brick size with mortar, 0 if incorrect) | 2 | ||
| Sub-Total | 10 | ||
| GRAND TOTAL | 31 | ||