By the end of this chapter, you will be able to:
Mastering these skills helps you ensure accurate project costing and resource planning, which are essential for successful civil engineering work.
Measurement of civil works requires precise take off of quantities to ensure accurate cost estimation and project control. Preparation of a quantities checklist is a critical initial step that guides the quantity surveyor through the systematic measurement process. This checklist helps organize the work, reduces errors, and ensures compliance with contract documents and specifications. Mastery of preparing a comprehensive checklist is essential for quantity surveyors working on construction projects in Kenya, from county government offices to private developments.
Preparation of a quantities checklist involves identifying all the items of work to be measured, the measurement rules to apply, and the sequence of measurement activities. This process ensures completeness and accuracy in taking off quantities for costing and valuation. In Kenya, quantity surveyors often rely on standard methods of measurement such as the Civil Engineering Standard Method of Measurement (CESMM) or the Standard Method of Measurement of Building Works (SMM). A well-structured checklist is indispensable for managing complex projects with multiple trades and subcontractors.
A quantities checklist should include all the major elements of the work to be measured, broken down into manageable components. This structure facilitates systematic measurement and cross-checking.
Preparation of a comprehensive checklist follows a logical sequence to capture all relevant measurement items accurately.
The accuracy of the quantities checklist depends on strict adherence to recognized measurement rules. These rules define how to measure each item, what to include or exclude, and how to deal with special cases.
Preparing a quantities checklist can encounter challenges that affect measurement accuracy and project costing. Quality assurance measures are necessary to mitigate these risks.
You are preparing a quantities checklist for a hospital construction project. List and explain six steps you would follow to prepare this checklist accurately. (15 marks)
Given a project scope including earthworks, concrete works, masonry, and finishes, identify appropriate units of measurement for each work item. Justify your choices based on standard measurement rules. (10 marks)
Discuss five common challenges encountered in preparing quantities checklists and suggest quality assurance measures to overcome each. (15 marks)
Explain how measurement rules influence the preparation of a quantities checklist, focusing on inclusion/exclusion criteria and rounding rules. Provide examples for each. (10 marks)
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter focused on the essential process of measuring civil works through the preparation of a comprehensive quantities checklist that ensures accuracy and completeness in project estimation. It detailed the take off procedures for various building works, covering key areas such as water supply installations, roadworks including driveways and parking areas, as well as drainage systems. The chapter further explored measurement techniques for foundations, highlighting their critical role in structural stability. Additionally, it addressed the quantification of culverts and bridges, emphasizing their unique measurement requirements. Fencing works were also included, illustrating how to account for linear and material dimensions. The booking of dimensions was explained as a systematic method for recording measurements clearly and efficiently. Finally, the chapter described how to compile booked items with precise descriptions to facilitate clear communication and effective project management.
A rectangular water tank measures 4 m by 3 m by 2 m high. Calculate the volume of concrete needed for the tank walls, assuming walls are 0.2 m thick and the base is 0.3 m thick. (2 marks)
A driveway is 50 m long and 4 m wide, with a compacted gravel layer 0.15 m thick. Calculate the volume of gravel required. (2 marks)
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape (5m) | Site Plan / Layout Drawing |
| Calculator | Graph Paper A4 Size |
| Writing Pens | |
| Scale Ruler (Metric) | |
| Clipboard |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape (5m) | 1 Pc per Candidate |
| 2 | Calculator | 1 Pc per Candidate |
| 3 | Writing Pens | 1 Pc per Candidate |
| 4 | Graph Paper A4 Size | 2 Sheets per Candidate |
| 5 | Scale Ruler (Metric) | 1 Pc per Candidate |
| 6 | Site Plan / Layout Drawing | 1 Set per Candidate |
| 7 | Clipboard | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: PREPARATION OF QUANTITIES CHECKLIST | |||
| Identified and donned appropriate PPE before starting the task (Award 1 mark each for helmet, safety boots, reflective vest) | 3 | ||
| Assembled all necessary tools and materials before commencing work (Award 0.5 mark for each correctly assembled tool/material up to 4) | 2 | ||
| Accurately read and interpreted the provided site plan/layout drawing (Award 5 marks for correct interpretation including dimensions and foundation type) | 5 | ||
| Measured and recorded all linear dimensions relevant to the foundation (length, width, depth) (Award 1 mark for each correct dimension recorded with units) | 5 | ||
| Calculated quantities for excavation (volume in m³) using correct formula (Award 6 marks for correct calculation with units and formula shown) | 6 | ||
| Calculated quantities for concrete (volume in m³) required for foundation base and walls (Award 6 marks for correct calculation with units and formula shown) | 6 | ||
| Calculated quantities for reinforcement bars (length in meters and number of bars) (Award 5 marks for correct estimation based on foundation drawing) | 5 | ||
| Compiled all quantities neatly and logically in a checklist format (Award 4 marks for clear, organized checklist with headings and units) | 4 | ||
| Checked calculations and quantities for accuracy and completeness (Award 4 marks for error-free and verified quantities checklist) | 4 | ||
| Sub-Total | 40 | ||
| PRODUCT CHECKLIST | |||
| Quantities checklist matches foundation dimensions (10000mm x 8000mm) with correct volume and lengths (+/- 50mm tolerance) (Award 10 marks for accurate quantities within tolerance) | 10 | ||
| Checklist includes all relevant materials: excavation volume, concrete volume, reinforcement lengths and counts (Award 6 marks for completeness of materials listed) | 6 | ||
| Quantities checklist is neat, legible, and professionally presented (Award 4 marks for overall presentation and clarity) | 4 | ||
| Sub-Total | 20 | ||
| GRAND TOTAL | 60 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape (5m) | Safety Helmet |
| Spirit Level | Safety Boots |
| Builder's Square | Reflective Safety Jacket |
| Plumb Bob | |
| Pencil and Eraser | |
| Calculator |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape (5m) | 1 Pc per Candidate |
| 2 | Spirit Level | 1 Pc per Candidate |
| 3 | Builder's Square | 1 Pc per 4 Candidates |
| 4 | Plumb Bob | 1 Pc per Candidate |
| 5 | Pencil and Eraser | 1 Set per Candidate |
| 6 | Note Book / Quantity Take Off Sheet | 1 Pc per Candidate |
| 7 | Calculator | 1 Pc per Candidate |
| 8 | Safety Helmet | 1 Pc per Candidate |
| 9 | Safety Boots | 1 Pair per Candidate |
| 10 | Reflective Safety Jacket | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: PROCESS OBSERVATION | |||
| Identified and used PPEs in line with occupational safety and health regulations (Award 1 mark for each PPE donned: helmet, boots, jacket, gloves, eye protection) | 5 | ||
| Assembled and used measuring tools correctly (tape, spirit level, builder's square, plumb bob) (Award 1 mark for each tool correctly assembled and used) | 5 | ||
| Measured wall length, height, and thickness accurately within ±50mm tolerance (Award 2 marks per dimension measured accurately) | 6 | ||
| Booked all measurements clearly and legibly on the take-off sheet (Award 1 mark for each correct booking of length, height, thickness, and notes) | 4 | ||
| Calculated quantities of wall materials (volume, surface area, number of bricks) correctly (Award marks for correct formula application and calculations) | 8 | ||
| Cleaned and stored tools properly after use (Award 2 marks for proper cleaning and storage) | 2 | ||
| Maintained safety and orderliness throughout the practical (Award marks for neatness and adherence to safety procedures) | 3 | ||
| Sub-Total | 33 | ||
| PRODUCT CHECKLIST | |||
| Quantities taken off match the wall dimensions 6,000mm length, 3,000mm height, 230mm thickness within ±50mm tolerance (Award 2 marks each for correct length, height, thickness measurements) | 6 | ||
| Calculated total wall volume is accurate within 5% error margin (Award 5 marks for accurate volume calculation) | 5 | ||
| Brick quantity calculation corresponds to standard brick size 230mm x 110mm x 75mm with 10mm mortar joints (Award 6 marks for correct brick quantity calculation) | 6 | ||
| Take off sheet is complete, neat, and legible (Award 4 marks for completeness and presentation) | 4 | ||
| Final calculations show correct units and appropriate rounding (Award 4 marks for correct units and rounding) | 4 | ||
| Sub-Total | 25 | ||
| GRAND TOTAL | 58 | ||
At the start of this chapter we promised you would be able to: