The preparation of tender documents is a critical phase in the quantity surveying process, as it sets the foundation for fair competition and accurate pricing. In Kenya, quantity surveyors must ensure that the tender documents are comprehensive, clear, and compliant with local construction standards and procurement regulations. Among the key components of tender documents are the working drawings, which provide the detailed visual instructions required for construction. This section focuses on the preparation of working drawings, essential for accurate estimation and successful project execution.
2.1 Preparation of working drawings
2.1.1 Purpose and importance of working drawings
Working drawings serve multiple purposes in construction projects and are crucial for quantity surveyors when preparing tender documents.
- Detailed project visualization: They translate design concepts into detailed representations, showing dimensions, materials, and construction methods, which help contractors understand the project fully.
- Basis for quantity takeoff: Quantity surveyors use these drawings to measure quantities accurately, ensuring precise cost estimation and budgeting.
- Communication tool: They facilitate clear communication among clients, contractors, engineers, and other stakeholders, reducing misunderstandings.
- Compliance and approvals: Working drawings demonstrate adherence to local building codes and standards, necessary for obtaining construction permits.
- Contractual reference: Once the contract is awarded, these drawings form part of the contract documents and are used to verify progress and quality.
2.1.2 Types of working drawings relevant to quantity surveyors
Quantity surveyors must be familiar with various types of working drawings, each serving distinct roles in the tendering process.
- Architectural drawings: Show building layouts, elevations, sections, and details, providing the overall design framework.
- Structural drawings: Detail the framework supporting the building, including foundations, beams, columns, and slabs.
- Mechanical and electrical drawings: Illustrate installations such as plumbing, HVAC, wiring, and lighting, essential for specialized works.
- Civil engineering drawings: Include site plans, drainage, roads, and earthworks, relevant for infrastructure projects.
- Finishing and landscaping drawings: Depict surface finishes, external works, and landscaping elements that affect final costs.
2.1.3 Steps in preparing working drawings for tender documents
The preparation of working drawings involves a systematic process to ensure accuracy and completeness.
- Review design briefs and specifications: Understand client requirements, design intent, and applicable standards.
- Coordinate with design professionals: Collaborate with architects, structural and services engineers to integrate all design aspects.
- Draft preliminary drawings: Prepare initial sketches showing general layout and key structural elements.
- Incorporate detailed information: Add dimensions, materials, construction methods, and technical notes.
- Verify compliance: Ensure drawings conform to Kenyan building codes and regulations.
- Finalize and approve drawings: Obtain necessary approvals from clients and regulatory authorities before inclusion in tender documents.
2.1.4 Common challenges in preparing working drawings and how to address them
Working drawings preparation can encounter challenges that affect tender accuracy and project execution.
Challenges
- Incomplete design information: Missing details can lead to inaccurate quantity takeoffs and cost overruns.
- Coordination issues: Lack of communication between design teams results in conflicting drawings.
- Non-compliance with standards: Drawings not adhering to local codes cause delays in approvals.
- Frequent design changes: Late modifications increase rework and confusion.
- Technical complexity: Highly technical systems require specialized knowledge to represent correctly.
How to address challenges
- Early collaboration: Engage all design disciplines from the start to ensure integration.
- Regular reviews: Conduct drawing audits to detect and correct inconsistencies promptly.
- Training and capacity building: Equip quantity surveyors with knowledge of local codes and technical aspects.
- Change management: Implement a formal process to handle design revisions and communicate updates.
- Use of technology: Employ CAD and BIM tools to improve accuracy and coordination.
Practice Questions
-
A quantity surveyor is preparing working drawings for a hospital project. The architectural drawings show a floor area of 1,200 m², and the structural drawings indicate slab thickness of 0.15 m with concrete density of 2,400 kg/m³. Calculate the volume and mass of concrete required for the slab. (5 marks)
-
During the preparation of working drawings, a drainage pipe of diameter 300 mm runs for 50 m. Calculate the internal cross-sectional area of the pipe and the volume of water it can hold when full. (5 marks)
-
A retail shop requires electrical wiring shown in the working drawings as 800 m in total length. If the cost per meter of wiring is Ksh 250, estimate the total cost for wiring installation. (5 marks)
Worked Solutions for Practice Questions
- Hospital slab calculation:
Given: Floor area = 1,200 m², Slab thickness = 0.15 m, Concrete density = 2,400 kg/m³
Volume of slab:$$
\text{Volume} = \text{Area} \times \text{Thickness} = 1,200 \times 0.15 = 180\, m^3
$$
Mass of concrete:$$
\text{Mass} = \text{Volume} \times \text{Density} = 180 \times 2,400 = 432,000\, kg
$$
Answer: Volume = 180 m³; Mass = 432,000 kg
- Drainage pipe calculation:
Given: Diameter = 300 mm = 0.3 m, Length = 50 m
Internal cross-sectional area:$$
A = \pi r^2 = \pi \times (0.15)^2 \approx 0.0707\, m^2
$$
Volume when full:$$
V = A \times \text{Length} = 0.0707 \times 50 = 3.535\, m^3
$$
Answer: Area = 0.0707 m²; Volume = 3.535 m³
- Electrical wiring cost:
Given: Length = 800 m, Cost per meter = Ksh 250
Total cost:$$
\text{Total Cost} = 800 \times 250 = 200,000\, Ksh
$$
Answer: Ksh 200,000
The rest of this chapter
🔒Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free account 🔒2.2 Work specifications
In preparing tender documents for quantity surveying in Kenya, work specifications define the detailed requirements of the construction works to be executed. These specifications guide contractors on the quality, materials, workmanship, and standards expected,…
🔒2.3 Bill of Quantities
The Bill of Quantities (BoQ) is a fundamental document in quantity surveying that provides a detailed, itemized list of materials, labour, and other costs required for a construction project. In Kenya, preparing an accurate BoQ is crucial for tendering, contra…
🔒2.4 Preparation of schedule of rates
In quantity surveying practice in Kenya, preparing a schedule of rates is a crucial step that influences tender evaluation, cost control, and contract administration. The schedule of rates provides a detailed list of unit prices for various work items, enablin…
🔒2.5 Preparation of conditions of contract
In quantity surveying practice in Kenya, the conditions of contract form a critical part of tender documents. They define the legal and procedural framework governing the relationship between the employer and the contractor once the tender is awarded. Properly…
🔒2.6 Forms of Agreement
In the Kenyan Quantity Survey context, forms of agreement are critical legal documents that define the contractual relationship between the client and the contractor or consultant. These agreements establish the rights, obligations, and responsibilities of all…
🔒2.7 Forms of Tender
In Kenyan quantity surveying practice, understanding the various forms of tender is vital for preparing comprehensive tender documents that align with client requirements and procurement regulations. The form of tender chosen affects how contractors submit bid…
Chapter Summary
This chapter covered the essential steps involved in preparing tender documents for construction projects. It began with the preparation of working drawings, which provide detailed visual instructions necessary for accurate project execution. The chapter then explored work specifications that define the quality and standards required for materials and workmanship. Next, it discussed the bill of quantities, a detailed itemized list that quantifies materials and labor needed for the project. The preparation of the schedule of rates followed, outlining the unit costs for various construction activities. Attention was given to the preparation of conditions of contract, which establish the legal framework and obligations of the parties involved. The chapter also examined forms of agreement, formalizing the contractual relationship between the client and contractor. Finally, it addressed forms of tender, which are the documents contractors submit to offer their bids for the project.
Self-Assessment
🔒 PDFDownload this self-assessment, with answers
Written Assessment
-
A quantity surveyor is preparing working drawings for a rectangular slab measuring 8 m by 6 m. Calculate the total area of the slab in square metres. (1 mark)
-
The specification for a concrete mix requires 1:2:4 (cement:sand:aggregate) by volume. If 3 m³ of concrete is needed, calculate the volume of cement required. (2 marks)
🔒18 more in this section.
Chapter Examination Questions
🔒 PDFDownload these examination questions, with worked answers
SECTION A (40 Marks) - Answer ALL Questions
- Explain the role of working drawings in the preparation of tender documents for a commercial building project in Nairobi. (4 marks)
- Identify four key components that must be included in work specifications for a residential housing project. (4 marks)
🔒18 more in this section.