Quantity Survey  ·  Level 6
Measurement Of Building Works I
Chapter 2: Take off quantities
📚 7 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • Identify the key principles of measurement by following standard operating procedures (SOPs).
  • Prepare a dimension sheet or paper correctly using the standard format.
  • Make a clear list of quantities to be measured based on the specific building items.
  • Calculate quantities of building elements accurately using the correct units of measurement.
  • Record dimensions properly by applying the principles of measurement.
  • Describe booked items clearly using the standard method of measurement for building and civil works (SMM) ©2025, TVET CDACC.

Mastering these skills will help you work confidently and accurately in the building trade, ensuring projects are measured and planned right from the start!

Quantity Survey professionals in Kenya rely heavily on accurate measurement and quantification of building works to prepare bills of quantities, cost estimates, and tender documents. The process commonly referred to as "take off quantities" involves systematically extracting measurements from architectural and structural drawings. Mastery of this process ensures precise cost control and resource planning during construction projects such as county government office buildings, hospitals, and educational institutions.

2.1 Preparation of Quantities Checklist

The preparation of a quantities checklist is a foundational step for quantity surveyors to organize and streamline the measurement process. It serves as a systematic guide to ensure all components of the building works are accounted for before commencing the take off. In Kenya, where project timelines and budgets are tight, a well-prepared checklist reduces errors and omissions that could lead to cost overruns.

2.1.1 Purpose and Importance of a Quantities Checklist

The purpose of a quantities checklist is to ensure comprehensive coverage of all elements requiring measurement, preventing omissions that can affect tender accuracy. Its importance includes:

  • Ensuring completeness: It lists all building elements such as substructure, superstructure, finishes, and services to be measured.
  • Improving accuracy: Guides the surveyor to measure systematically, reducing chances of double counting or missing items.
  • Saving time: Streamlines the take off process by providing a clear measurement plan.
  • Facilitating communication: Acts as a reference for project teams to confirm measured items.
  • Supporting cost control: Accurate quantities underpin reliable cost estimates and budget management.

2.1.2 Components of a Quantities Checklist

A typical quantities checklist for building works includes:

  • Substructure elements: Foundations, bases, ground beams.
  • Superstructure elements: Columns, beams, slabs, walls.
  • Wall finishes and openings: Doors, windows, plastering.
  • Roofing: Timber or metal frameworks, coverings.
  • Floor finishes: Tiles, screeds.
  • External works: Drainage, pavements.

2.1.3 Steps to Prepare a Quantities Checklist

  1. Review project drawings: Study architectural, structural, and services drawings to identify all measurable items.
  2. Breakdown works by sections: Divide the project into logical sections such as substructure, superstructure, finishes.
  3. List all measurable components: Write down all elements under each section.
  4. Define measurement units: Specify units such as cubic meters for concrete, square meters for plaster.
  5. Cross-check with specifications: Ensure all items in the specification are included.
  6. Review with project team: Confirm checklist completeness with architects, engineers, and clients.

2.1.4 Tools Used in Preparing Quantities Checklist

Name Specification Use
Scale ruler Metric scale with various ratios To measure dimensions on drawings
Measuring tape Steel tape, 5m to 30m length For on-site verification of dimensions
Calculator Scientific calculator with memory For arithmetic calculations
Digital plan measurer Electronic device with LCD display For fast and accurate drawing measurements
  • Use the scale ruler to convert drawing dimensions to real sizes accurately.
  • Verify critical dimensions on site with the tape measure.
  • Use the calculator to compute areas, volumes, and quantities.
  • Maintain tools by keeping tapes clean and checking batteries in digital devices.

Practice Questions

  1. List the key components that should be included in a quantities checklist for a two-story hospital building. (5 marks)

  2. Describe six steps you would follow to prepare a comprehensive quantities checklist for a county government office project. (6 marks)

  3. Explain why verifying the checklist with the project team is essential before starting quantity take off. (4 marks)

The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒2.2 Take off of Building Works

Take off quantities involves detailed measurement of building components as per drawings and specifications. This process forms the basis for preparing bills of quantities and cost estimates in Kenyan construction projects such as schools, retail outlets, and…

🔒2.3 Booking of dimensions

Booking of dimensions in quantity surveying involves the systematic recording of measured lengths, areas, and volumes from drawings or site measurements onto a measurement book or electronic format. This process ensures accurate transfer of physical measuremen…

🔒2.4 Booked items description

The description of booked items is the detailed narrative that accompanies the recorded dimensions in measurement books or BoQs. It provides clarity on what the dimension represents, the location, the type of material, and workmanship standards. Accurate descr…

🔒2.5 Timesing of dimensions

Timesing of dimensions is a fundamental technique in the measurement of building works used extensively by Quantity Surveyors in Kenya to accurately calculate quantities from measured dimensions. It involves multiplying linear dimensions to obtain areas, volum…

🔒2.6 Dotting of dimensions

Dotting of dimensions is a detailed measurement technique used by Quantity Surveyors in Kenya to indicate the multiplication of several dimensions in a takeoff sheet. It visually clarifies which dimensions are to be multiplied and prevents errors in complex qu…

🔒2.7 Squaring of booked dimensions

Squaring of booked dimensions is a fundamental process in quantity surveying that ensures the accuracy and consistency of measurements taken on site or from drawings. In the Kenyan construction industry, precise dimension squaring is crucial to avoid costly er…

Chapter Summary

This chapter covers the essential process of preparing a quantities checklist as the foundation for accurate measurement of building works. It then details the take off procedures for various building components including the substructure, superstructure frames made of reinforced concrete and steel, walling, and roofing systems comprising timber and metal materials. The importance of precise booking of dimensions is emphasized to ensure clarity and consistency in quantity measurement. Following this, the chapter explains how to properly describe booked items to maintain uniformity in documentation. It further explores the timesing of dimensions, a critical step to multiply quantities correctly for volume or area calculations. The technique of dotting dimensions is introduced as a method to avoid errors in measurement transfer. Finally, the chapter discusses squaring of booked dimensions to verify accuracy and completeness before final quantity computations.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

Written Assessment

  1. A rectangular foundation trench measures 8 m long, 1.2 m wide, and 1.5 m deep. Calculate the volume of concrete required for the foundation. (2 marks)

  2. A reinforced concrete column has a square cross-section of 0.4 m by 0.4 m and a height of 3.5 m. Determine the volume of concrete needed for this column. (2 marks)

🔒18 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Define the purpose of a quantities checklist during the preparation of a building project measurement. (4 marks)
  2. List four typical items included under substructure take off in reinforced concrete building works. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Prepare Quantities Checklist for a Single-Storey Residential Wall

Quantity Survey · Level 6
Measurement Of Building Works I
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Prepare a detailed quantities checklist for external walls measuring 10,000 mm length, 3,000 mm height, and 230 mm thickness.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring Tape (5m)Architectural Drawing
Builder's SquareNotepad
Spirit Level
Pencil
Calculator
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Measuring Tape (5m)1 Pc per Candidate
2Builder's Square1 Pc per 4 Candidates
3Spirit Level1 Pc per Candidate
4Pencil1 Pc per Candidate
5Notepad1 Pc per Candidate
6Calculator1 Pc per Candidate
7Architectural Drawing (Scale 1:100)1 Set per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Preparation Process
Identified and donned appropriate PPEs including helmet, safety boots, and reflective vest
(Award 1 mark for each correctly worn PPE)
3
Assembled all required tools and materials before starting the checklist preparation
(Award 1 mark for each of three correctly assembled items)
3
Read and interpreted the architectural drawing correctly
(Award 1 mark for each accurate interpretation of length, height, thickness, and wall type)
4
Measured and verified wall dimensions from the drawing accurately
(Award 1 mark each for correct length, height, thickness, and wall openings dimensions)
5
Identified all building elements and materials to be measured including bricks, mortar, wall ties, damp proof course, and plaster
(Award 1 mark for each correctly identified element/material)
5
Recorded quantities in the checklist clearly and systematically
(Award 1 mark for clarity, 1 mark for systematic arrangement, 3 marks for completeness)
5
Reviewed and cross-checked the quantities checklist for accuracy
(Award 3 marks for thorough review and correction of errors)
3
Cleaned and stored tools and working area after task completion
(Award 1 mark each for cleaning and proper storage)
2
Sub-Total30
PRODUCT CHECKLIST
Quantities checklist includes wall length 10,000 mm ±50 mm tolerance
(Award 2 marks for correct length with tolerance)
2
Quantities checklist includes wall height 3,000 mm ±50 mm tolerance
(Award 2 marks for correct height with tolerance)
2
Quantities checklist includes wall thickness 230 mm ±10 mm tolerance
(Award 2 marks for correct thickness with tolerance)
2
All building elements and materials are listed with correct units and quantities
(Award 1 mark each for bricks, mortar, wall ties, damp proof course)
4
Checklist is well presented, legible, and logically organized
(Award 5 marks for neatness and logical flow)
5
Sub-Total15
GRAND TOTAL45
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Take Off Quantities for a Single Storey Wall and Footing

Quantity Survey · Level 6
Measurement Of Building Works I
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Perform a complete take off of quantities for a 200mm thick wall 6m long and 3m high with a 600mm wide by 300mm deep strip footing.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring Tape (5m)Safety Helmet
Spirit LevelSafety Boots
Builder's SquareReflective Jacket
Plumb Bob
Pencil and Notepad
Calculator
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Measuring Tape (5m)1 Pc per Candidate
2Spirit Level1 Pc per Candidate
3Builder's Square1 Pc per 4 Candidates
4Plumb Bob1 Pc per Candidate
5Pencil and Notepad1 Set per Candidate
6Calculator1 Pc per Candidate
7Safety Helmet1 Pc per Candidate
8Safety Boots1 Pair per Candidate
9Reflective Jacket1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: OBSERVATION CHECKLIST
Identified and used PPEs correctly (helmet, boots, jacket)
(Award 1 mark each for correct PPE usage)
3
Assembled all required tools before starting the take off
(Award 0.5 mark each for at least six tools assembled)
3
Measured wall length accurately within ±50 mm tolerance
(Award full marks for correct measurement within tolerance)
3
Measured wall height accurately within ±50 mm tolerance
(Award full marks for correct measurement within tolerance)
3
Measured wall thickness correctly as 200 mm
(Award full marks for correct thickness measurement)
2
Measured footing width accurately as 600 mm ± 50 mm
(Award full marks for correct footing width measurement)
3
Measured footing depth accurately as 300 mm ± 50 mm
(Award full marks for correct footing depth measurement)
3
Used builder's square and plumb bob to check wall verticality and corners
(Award 1 mark each for correct use of tools)
3
Recorded all measurements and quantities clearly and legibly
(Award full marks for clear recording)
3
Calculated quantities of bricks, mortar, concrete, and reinforcement bars
(Award 1 mark per correctly calculated quantity, zero otherwise)
6
Sub-Total32
PRODUCT CHECKLIST
Accurate take off quantities matching the dimensions: wall 6m x 3m x 200mm and footing 600mm x 300mm
(Award 2 marks for each correct major quantity: bricks, mortar, concrete, reinforcement)
8
Calculations presented clearly and logically with correct units
(Award 4 marks for clear and correct presentation)
4
Take off list is complete with all relevant items included
(Award 2 marks for inclusion of each key item: bricks, mortar, concrete, reinforcement, formwork)
6
Overall neatness and professionalism of the final document
(Award full marks for neat and professional presentation)
4
Sub-Total22
GRAND TOTAL54
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Measure substructure quantities for strip foundationPractical 3
🔒Take off quantities for reinforced concrete and steel superstructure framePractical 4
🔒Measure walling quantities for a single-storey residential wallPractical 5
🔒Take off quantities for timber and metal roofing materialsPractical 6
🔒Booking linear dimensions from a single-storey residential wall drawingPractical 7
🔒Describe Booked Items for Concrete Beam Take OffPractical 8
🔒Calculate Areas and Volumes by Timesing Dimensions for Quantity TakeoffPractical 9
🔒Dotting Dimensions on a Wall Elevation DrawingPractical 10
🔒Squaring Booked Dimensions for Accurate Quantity Take OffPractical 11
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 20 questions Start quiz ▾
0%
0 / 2
🔒

18 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Identify the key principles of measurement by following standard operating procedures (SOPs).
  • Prepare a dimension sheet or paper correctly using the standard format.
  • Make a clear list of quantities to be measured based on the specific building items.
  • Calculate quantities of building elements accurately using the correct units of measurement.
  • Record dimensions properly by applying the principles of measurement.
  • Describe booked items clearly using the standard method of measurement for building and civil works (SMM) ©2025, TVET CDACC.

Tick each one you can genuinely do.

So, are you there yet?

You're competent when you can confidently do 50% or more of what this chapter promised.

Sign in to record how you're doing.