By the end of this chapter, you will be able to:
Mastering these skills helps you ensure construction projects start on the right track with precision and professionalism, making you a valuable part of any engineering team.
Surveying setting out works form a critical foundation in quantity surveying, ensuring that construction projects are executed precisely according to design specifications. Accurate setting out translates designs into physical markers on the ground, guiding construction teams during site preparation and building. In Kenya, quantity surveyors must be proficient in using surveying tools and equipment to enhance accuracy, reduce errors, and optimize project timelines and costs. This chapter covers essential surveying setting out tools and equipment, focusing on their specifications, usage, and relevance to quantity surveying practice.
Surveying setting out tools are fundamental for marking positions, distances, and levels on construction sites. For quantity surveyors in Kenya, mastery of these instruments enables precise measurement and control during site establishment, ensuring that structures are built within design tolerances. The choice of tool depends on the scale, accuracy required, and site conditions.
| Name | Specification | Use |
|---|---|---|
| Steel Tape | Lengths of 30m, 50m; width 13mm; steel blade with metric and imperial markings | Measuring linear distances on site, marking foundation lines, checking offsets |
| Fiberglass Tape | Lengths of 30m, 50m; flexible fiberglass blade with metric markings | Measuring on rough or uneven terrain where steel tape might bend or corrode |
| Cloth Tape | Lengths of 30m; flexible fabric blade | Used in site surveys where flexible measurement is needed, less durable |
Steel tapes offer high accuracy and durability, suitable for most standard site measurements. Fiberglass tapes resist stretching and corrosion, making them ideal for outdoor use in Kenya’s humid or wet environments. Cloth tapes are less precise and mainly used for rough measurements or in areas where steel tapes would be damaged.
The measuring wheel, also known as a surveyor’s wheel, is a mechanical device used for rapid measurement of longer distances on site, particularly where terrain is uneven or inaccessible by tape.
| Name | Specification | Use |
|---|---|---|
| Standard Wheel | Diameter 320mm; metric counter; handle height adjustable | Measuring distances up to several hundred meters quickly along roads, boundaries, and site perimeters |
The wheel rotates as it is rolled along the ground, with each full rotation corresponding to a known distance. The attached mechanical counter records the number of rotations and partial rotations, converting these into linear distance readings. This method allows quick, continuous measurement without the need to stretch a tape.
| Name | Specification | Use |
|---|---|---|
| Total Station | Angular accuracy ±1”; distance accuracy ±(2mm + 2ppm); integrated data collector | Measuring angles, distances, and coordinates for detailed site layout and control points |
Total stations enable quantity surveyors to perform accurate setting out of building corners, foundation lines, and infrastructure alignments. In Nairobi’s expanding urban areas, total stations are used for complex site layouts where precision is critical to avoid costly rework.
The automatic level is an optical instrument used primarily for establishing or checking height differences and levels across a construction site. It is essential for setting out foundations and floor levels.
| Name | Specification | Use |
|---|---|---|
| Automatic Level | Magnification 32x; horizontal circle graduated; self-leveling compensator | Determining height differences, establishing bench marks, setting foundation and slab levels |
The automatic level contains a compensator mechanism that automatically maintains the line of sight horizontal even if the instrument is slightly tilted. This reduces errors caused by manual leveling, increasing efficiency and accuracy.
Accurate leveling ensures that structures are built on correct elevations, preventing structural faults. Quantity surveyors use automatic levels to verify design levels on site, a critical step before excavation and concrete works commence.
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter explored the essential tools and equipment used in surveying setting out works, including tape measures, measuring wheels, total stations, and automatic levels, each playing a critical role in ensuring accuracy during site measurements. It then examined various types of setting out works, focusing on building layouts, paths, and vehicular parking areas, highlighting the importance of precise positioning for structural and functional integrity. The chapter reviewed common setting out methods such as the 3-4-5 method based on Pythagoras theorem, the use of a builder's square, and the site square method, demonstrating how these techniques facilitate accurate angle and distance measurements on site. Attention was given to the practical execution of setting out works, emphasizing careful application of tools and methods to translate design plans into physical markers. Finally, the chapter underscored the significance of thorough documentation of setting out activities to ensure clarity, accountability, and ease of verification throughout the construction process. Together, these topics provide a comprehensive understanding of the surveying setting out process critical for successful engineering projects.
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Tape measure 30m | Surveying pegs 600mm hardwood |
| Surveying pegs 600mm hardwood | |
| Chalk line reel | |
| Field book (surveying notebook) | |
| Pencil HB | |
| Reflective safety vest | |
| Safety boots | |
| Hard hat (helmet) |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Tape measure 30m | 1 Pc per Candidate |
| 2 | Surveying pegs 600mm hardwood | 10 Pcs per Candidate |
| 3 | Chalk line reel | 1 Pc per Candidate |
| 4 | Field book (surveying notebook) | 1 Pc per Candidate |
| 5 | Pencil HB | 2 Pcs per Candidate |
| 6 | Reflective safety vest | 1 Pc per Candidate |
| 7 | Safety boots | 1 Pair per Candidate |
| 8 | Hard hat (helmet) | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Use tape measure for linear measurements | |||
| Wore appropriate PPE: safety boots, hard hat, reflective safety vest (Award 1 mark each for any correct PPE worn) | 3 | ||
| Prepared and cleared site area for accurate measurement (Award 1 mark for proper site clearance) | 1 | ||
| Selected and inspected tape measure and pegs for suitability (Award 1 mark each for tape measure and pegs inspection) | 2 | ||
| Measured out linear distance of 25,000mm accurately using tape measure (Award up to 4 marks for accuracy within ±5mm) | 4 | ||
| Measured out linear distance of 15,000mm accurately using tape measure (Award up to 3 marks for accuracy within ±5mm) | 3 | ||
| Marked and pegged the measured positions clearly and securely (Award 3 marks for correct pegging and marking) | 3 | ||
| Recorded all measurements properly and legibly in the field book (Award 2 marks for complete and clear records) | 2 | ||
| Sub-Total | 18 | ||
| PRODUCT CHECKLIST | |||
| Linear distance 25,000mm measured and pegged within ±5mm accuracy (Award 5 marks for correct measurement and pegging accuracy) | 5 | ||
| Linear distance 15,000mm measured and pegged within ±5mm accuracy (Award 4 marks for correct measurement and pegging accuracy) | 4 | ||
| Clear, legible and complete recording of distances in field book (Award 3 marks for neat and accurate records) | 3 | ||
| Sub-Total | 12 | ||
| GRAND TOTAL | 30 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring wheel | Safety helmet |
| Measuring tape 30 meters | Safety boots |
| Survey pegs | Reflective safety jacket |
| Notebook and pen |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring wheel | 1 Pc per Candidate |
| 2 | Safety helmet | 1 Pc per Candidate |
| 3 | Safety boots | 1 Pair per Candidate |
| 4 | Reflective safety jacket | 1 Pc per Candidate |
| 5 | Measuring tape 30 meters | 1 Pc per Candidate |
| 6 | Survey pegs | 5 Pcs per Candidate |
| 7 | Notebook and pen | 1 Set per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Measuring the path length | |||
| Used appropriate PPE: helmet, safety boots, reflective jacket (Award 1 mark each for helmet, boots, and jacket) | 3 | ||
| Prepared the path by clearing obstacles and placing survey pegs at start and end points (Award 2 marks for proper site preparation and peg placement) | 2 | ||
| Calibrated and checked the measuring wheel for zero reading before use (Award 2 marks for correct calibration and zeroing) | 2 | ||
| Measured the 50-meter path using the measuring wheel with steady walking and correct handling (Award 4 marks for proper measurement technique and steady wheel operation) | 4 | ||
| Verified the measuring wheel reading using the 30-meter measuring tape for at least one segment (Award 3 marks for correctly verifying measurement with tape) | 3 | ||
| Recorded measurements accurately in the notebook (Award 2 marks for clear and accurate recording) | 2 | ||
| Sub-Total | 16 | ||
| PRODUCT CHECKLIST | |||
| Measured path length within ±0.5 meters of the actual 50 meters (Award 6 marks for measurement accuracy within tolerance) | 6 | ||
| Proper placement and visibility of survey pegs at start and end points (Award 3 marks for correct peg placement) | 3 | ||
| Complete and legible measurement record matching the measured length (Award 5 marks for complete and legible documentation) | 5 | ||
| Sub-Total | 14 | ||
| GRAND TOTAL | 30 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.