Building Technology  ·  Level 6
Building Finishes
Chapter 2: Carry out floor finishes
📚 6 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • Wear the correct personal protective equipment safely and follow all job safety procedures.
  • Correctly assemble all terrazzo tools and equipment needed for the floor finishing job.
  • Accurately screed the terrazzo surface to meet the National Building Code requirements.

Mastering these skills ensures you create strong, safe, and beautiful floor finishes that last and meet professional standards in the building trade.

Compiled by: John Wachira

Carrying out floor finishes is a critical aspect of building technology that directly affects the durability, aesthetics, and safety of a building’s interior environment. In Kenya, where diverse climatic conditions and usage demands prevail, selecting and applying appropriate floor finishes requires specialized knowledge and skills. Professionals engaged in building finishes must understand the protective equipment necessary for safe operations and be proficient with the tools and materials used for various types of floor finishes. This chapter addresses the essential protective gear and the practical aspects of floor finishing to equip technicians with the competence needed for quality workmanship.

2.1 Protective Equipment

2.1.1 Types of Protective Equipment

Protective equipment used in floor finishing covers various categories of personal protective gear designed to shield the worker from physical, chemical, and environmental hazards. These include:

  • Respiratory Protection: Masks and respirators prevent inhalation of dust, fumes, and volatile organic compounds emitted by adhesives, sealants, and finishes. For example, workers applying epoxy resin floors in hospital settings must wear respirators to avoid respiratory irritation.

  • Eye Protection: Safety goggles and face shields guard against splashes of chemicals and flying debris during grinding or polishing operations, which are frequent in finishing concrete or terrazzo floors.

  • Hand Protection: Gloves made from nitrile, latex, or leather protect hands from chemical burns, cuts, and abrasions. For instance, electricians installing underfloor heating cables in a retail store must use insulated gloves to prevent electrical hazards.

  • Foot Protection: Steel-toe boots with slip-resistant soles protect feet from heavy falling objects and prevent slips on wet or polished surfaces, a common risk in hotel lobbies during floor finishing.

  • Protective Clothing: Overalls and aprons shield the body from chemical spills and dust contamination. Workers applying waterproofing membranes in county government offices benefit from full-body suits to avoid skin contact with hazardous substances.

2.1.2 Uses of Protective Equipment

Proper use of protective equipment is crucial to ensuring safety and compliance on-site during floor finishing processes. The uses include:

  • Preventing Respiratory Illnesses: Respirators reduce exposure to airborne particles and harmful vapors, which can cause chronic respiratory conditions, especially in enclosed environments such as university laboratories.

  • Protecting Vision: Goggles prevent eye injuries from flying particles during mechanical polishing of marble floors in banking halls, preserving workers’ eyesight.

  • Maintaining Hand Safety: Gloves protect against cuts from sharp tools like trowels and scrapers used in ceramic tile installation at SACCO offices.

  • Ensuring Foot Stability and Protection: Safety boots prevent foot injuries from heavy equipment and provide traction on slippery surfaces, essential in busy hospital corridors undergoing floor restoration.

  • Minimizing Skin Contact: Protective clothing reduces allergic reactions and chemical burns when applying solvent-based stains or sealants in commercial kitchens.

Correct maintenance and regular inspection of protective equipment ensure its effectiveness. For example, damaged gloves or cracked goggles should be replaced immediately to maintain safety standards.

Practice Questions

  1. Explain five types of protective equipment used in floor finishing and their specific roles in ensuring worker safety. (10 marks)

  2. Describe how improper use of protective equipment can affect health and safety during floor finishing activities in a county government office. (10 marks)

  3. Identify the protective equipment necessary for applying epoxy resin floors in a hospital and justify their use. (10 marks)

The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒2.2 Floor Finishing

Floor finishing involves the application of various materials and techniques to the floor surface to enhance its durability, appearance, and functionality. In Kenya’s building sector, floor finishes must withstand heavy foot traffic, climatic stresses, and mai…

🔒2.3 Floor Finishes Tools and Equipment

In the Kenyan building industry, the choice and use of appropriate tools and equipment for floor finishing are critical to achieving quality, durability, and aesthetic appeal. Building technology professionals must be well-versed in the types of tools availabl…

🔒2.4 Floor Finishing Materials

Selecting appropriate floor finishing materials is a critical decision that affects the floor’s functionality, aesthetics, and lifespan. In building technology practice within Kenya, materials are chosen based on the building’s purpose, traffic load, maintenan…

🔒2.5 Floor backgrounds

A floor background (also called the substrate or sub-floor) is the base surface on which a floor finish, such as tiles, terrazzo, vinyl, timber or an epoxy coating, is laid or applied. The background carries the finish and transfers loads to the structure, so…

🔒2.6 Floor finish

A floor finish is the final wearing surface laid or applied on a prepared floor background, such as cement screed, terrazzo, tiles, vinyl, timber, carpet or a floor coating. It gives the floor its appearance, resistance to wear, slip resistance, ease of cleani…

Chapter Summary

This chapter explored the essential protective equipment required for floor finishing work, detailing various types and their specific uses to ensure safety and efficiency on site. It then examined the floor finishing process, describing the methods involved, the necessary tools and equipment, and the different types of floor finishes along with their practical applications. A focused discussion on the tools and equipment used in floor finishing followed, highlighting their various types and functions. The chapter proceeded to outline the floor finishing materials, explaining the different types available and the preparation steps needed before application. Attention was given to floor backgrounds, covering the types of backgrounds suitable for different finishes and the procedures for preparing these surfaces. Finally, the chapter detailed the application of floor finishes, emphasizing the techniques required to achieve durable and aesthetically pleasing results. This comprehensive coverage equips learners with the knowledge to execute floor finishing tasks effectively while maintaining safety and quality standards.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. Identify four types of protective equipment commonly used during floor finishing works. (4 marks)
  2. Explain the primary purpose of using protective equipment in floor finishing operations. (2 marks)
🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. State objectives of plastering in building finishes and explain how these objectives improve floor durability in a Nairobi County government office. (4 marks)
  2. List materials commonly used for cladding floors and describe the suitability of each material for a hotel lobby floor finish. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Identify and select appropriate floor finishing materials for a residential room floor

Building Technology · Level 6
Building Finishes
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Identify and select appropriate floor finishing materials for a 3m by 4m residential bedroom floor as per the given specifications.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Tape measureCeramic floor tiles 300mm x 300mm
TrowelVinyl floor sheets 3m x 4m
Spirit levelTimber floor planks 100mm x 20mm x 3m
Rubber malletFloor adhesive
Sand
Cement
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Ceramic floor tiles 300mm x 300mm12 Pcs per Candidate
2Vinyl floor sheets 3m x 4m1 sheet per Candidate
3Timber floor planks 100mm x 20mm x 3m10 Planks per Candidate
4Floor adhesive (tile and vinyl glue)1 kg per Candidate
5Sand1 barrow per 5 Candidates
6Cement1 bag per 10 Candidates
7Trowel1 Pc per Candidate
8Tape measure1 Pc per Candidate
9Spirit level1 Pc per Candidate
10Rubber mallet1 Pc per 5 Candidates
11Safety gloves1 Pair per Candidate
12Safety boots1 Pair per Candidate
13Dust mask1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Identification and Selection of Floor Finishing Materials
Wore PPEs (safety gloves, boots, dust mask).
(Award 1 mark for each PPE worn = 3 Marks)
3
Measured the floor area accurately using tape measure.
(Award 3 marks for correct measurement of 3m x 4m)
3
Identified and listed at least three types of floor finishes suitable for the floor.
(Award 1 mark for each correct material identified up to 4 marks)
4
Selected appropriate floor finishing materials based on floor type and use.
(Award 5 marks for correct material selection with justification)
5
Demonstrated correct handling and preparation of materials for floor finishing.
(Award 5 marks for proper handling and preparation)
5
Used tools correctly to demonstrate the application process (dry-laying tiles, laying vinyl, arranging timber planks).
(Award 2 marks for each correct tool use demonstration)
6
Sub-Total26
PRODUCT CHECKLIST
Correct identification and selection of floor finishing materials matching the floor size (3m x 4m).
(Award 10 marks for completeness, appropriateness and accuracy)
10
Clean, safe and organized presentation of selected materials and tools.
(Award 4 marks for neatness and organization)
4
Sub-Total14
GRAND TOTAL40
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Prepare floor background for finishing on a 2.5m x 2.5m concrete slab

Building Technology · Level 6
Building Finishes
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Prepare the 2.5m x 2.5m concrete floor slab background by cleaning, leveling, and applying a cement-sand screed to make it ready for vinyl floor finishing.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
BroomSand (fine)
ShovelCement (OPC)
Spirit levelWater
Straight edge
Trowel
Bucket
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Concrete floor slab 2.5m x 2.5m1 per Candidate
2Broom1 pc per Candidate
3Shovel1 pc per 5 Candidates
4Spirit level1 pc per Candidate
5Straight edge 2.5m1 pc per Candidate
6Trowel1 pc per Candidate
7Bucket 20 litres1 pc per Candidate
8WaterSufficient for dampening
9Sand (fine)1 barrow per 5 Candidates
10Cement (OPC)1 bag per 10 Candidates
11Rubber gloves1 pair per Candidate
12Safety boots1 pair per Candidate
13Dust coat/overall1 pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Floor background preparation
Wore PPEs (overall/dust coat, gloves, safety boots)
(Award 0.5 mark for each PPE worn correctly = 2 Marks)
2
Cleaned the floor slab surface, removing all loose debris and dust
(Award 3 marks for thorough cleaning = 3 Marks)
3
Checked floor levelness using spirit level and straight edge
(Award 3 marks for correct use and identification of uneven areas = 3 Marks)
3
Mixed cement-sand mortar in ratio 1:3 with appropriate water to uniform consistency
(Award 4 marks for correct batching, mixing and consistency = 4 Marks)
4
Applied mortar screed evenly over the floor slab using trowel and straight edge
(Award 5 marks for uniform spreading and leveling = 5 Marks)
5
Used spirit level and straight edge to check and correct screed levelness
(Award 3 marks for correct leveling and adjustments = 3 Marks)
3
Finished the screed surface smooth and uniform using trowel
(Award 3 marks for smooth finish without hollows or bumps = 3 Marks)
3
Cleaned the work area and removed waste materials
(Award 2 marks for thorough cleaning = 2 Marks)
2
Cleaned and stored tools properly after use
(Award 2 marks for cleaning and correct storage = 2 Marks)
2
Sub-Total27
PRODUCT CHECKLIST
Screed thickness uniformity at 15mm ±2mm
(Award 3 marks for uniform thickness within tolerance = 3 Marks)
3
Floor levelness within ±3mm over 2.5m length
(Award 4 marks for levelness within tolerance = 4 Marks)
4
Surface smoothness, no visible cracks or hollows
(Award 3 marks for smooth and defect-free surface = 3 Marks)
3
Edges straight and well finished
(Award 2 marks for neat and straight edges = 2 Marks)
2
Completeness: 100% complete award 4 marks; 75% complete award 3 marks; 50% complete award 2 marks; below 50% award 1 mark
(Award marks as per completeness scale = 4 Marks)
4
Sub-Total16
GRAND TOTAL43
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Apply screed as floor finish on a prepared concrete floorPractical 3
🔒Lay ceramic floor tiles 300mm x 300mm on prepared floor backgroundPractical 4
🔒Apply Floor Paint Finish on Concrete Floor 3m x 3mPractical 5
🔒Install vinyl floor finish on a prepared floor surfacePractical 6
🔒Lay Terrazzo Floor Finish 2.0m x 2.0mPractical 7
🔒Use of floor finishing tools and equipment to apply and smooth a cement screed floor finishPractical 8
🔒Set out floor tile layout for a 3m by 4m roomPractical 9
🔒Apply floor adhesive for tile laying on a 1.5m x 1.5m floor sectionPractical 10
🔒Mix and apply cement-based floor finish 2m x 2mPractical 11
🔒Prepare and install wooden floor finish 3m x 3mPractical 12
🔒Apply Protective Floor Coating on a Finished Concrete Floor 3m x 3mPractical 13
🔒Inspection and Rectification of Floor Finish Defects on a 3m x 3m Floor SectionPractical 14
🔒Apply epoxy floor finish on a 2.5m x 2.5m concrete floor areaPractical 15
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 18 questions Start quiz ▾
0%
0 / 2
🔒

16 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Wear the correct personal protective equipment safely and follow all job safety procedures.
  • Correctly assemble all terrazzo tools and equipment needed for the floor finishing job.
  • Accurately screed the terrazzo surface to meet the National Building Code requirements.

Tick each one you can genuinely do.

So, are you there yet?

You're competent when you can confidently do 50% or more of what this chapter promised.