Building Technology  ·  Level 6
Building Finishes
Chapter 1: Carry out wall finishes
📚 6 Topics
What you will be able to do

By the end of this chapter, you will be able to:

  • Wear the correct personal protective equipment and follow all safety procedures for the job.
  • Assemble all the tiling tools and equipment correctly and efficiently.
  • Screed the tiling surface accurately according to the National Building Code 2024 requirements.
  • Gather and prepare all the tiling materials needed for the job.
  • Set tiles precisely following the specifications on the working drawings.
  • Cut tiles accurately to match the design specifications.
  • Fix tiles securely according to the work specifications.
  • Grout tile joints properly following the National Building Code 2024 requirements.
  • Clean the tiled surface thoroughly to meet job standards.

These skills will help you create strong, beautiful, and safe wall finishes that meet professional standards and impress your clients.

Wall finishes form a critical aspect of building construction, impacting both the aesthetic appeal and durability of structures. In Kenya, where diverse climatic conditions and urban environments demand resilient building materials, understanding how to carry out wall finishes is essential for building technology professionals. This chapter focuses on the protective equipment necessary for safe finishing work and the identification and application of various wall finishes appropriate to local contexts.

1.1 Protective equipment

Protective equipment is fundamental for ensuring the safety and health of workers engaged in wall finishing activities. In Kenya’s construction sites, adherence to safety standards is mandated by the Occupational Safety and Health Act, 2007, which requires appropriate personal protective equipment (PPE) to minimize risks. The correct selection and use of PPE help prevent injuries from chemical exposure, dust, physical impacts, and falls during finishing tasks.

1.1.1 Types of protective equipment

Protective equipment used in wall finishing varies depending on the nature of the work and associated hazards. The main types include:

Eye and face protection

Safety goggles and face shields protect workers from splashes of plaster, paint, and dust particles that can cause eye injuries. For example, employees at a Nairobi county office construction site use goggles when applying cement-based finishes to prevent irritation and damage.

Respiratory protection

Dust masks and respirators safeguard against inhaling harmful dust, silica particles, and fumes from paint solvents. Workers installing gypsum plaster in a hospital renovation project must wear N95 masks to avoid respiratory ailments caused by fine dust.

Hand protection

Gloves made from rubber or leather protect hands from chemical burns, abrasions, and cuts encountered while mixing or applying finishes. In a retail building project in Mombasa, workers use nitrile gloves when handling solvent-based paints to avoid skin irritation.

Head protection

Hard hats shield workers from falling objects or accidental bumps during scaffold work. Construction teams at a university campus use helmets consistently to comply with safety regulations and reduce head injury risks.

Foot protection

Steel-toed boots provide protection from heavy materials and sharp debris on site. At a cooperative housing project in Nakuru, all workers wear boots to prevent foot injuries from nails and bricks.

1.1.2 Uses of protective equipment

The effective use of protective equipment enhances worker safety and compliance with Kenyan safety laws. Proper use involves:

Hazard identification

Workers must assess the specific risks associated with each finishing task to select suitable PPE. For instance, applying chemical-based wall finishes requires gloves and respiratory masks, while sanding dry surfaces demands dust masks and goggles.

Correct fitting and maintenance

PPE must fit well to provide intended protection; loose masks or gloves reduce effectiveness. Regular cleaning and inspection ensure equipment remains functional, such as replacing worn-out respirator filters during a hotel refurbishment in Kisumu.

Training and awareness

Employers should train workers on PPE usage and limitations, reinforcing safety culture on construction sites like county government offices in Eldoret.

Compliance monitoring

Site supervisors conduct routine checks to ensure all workers wear appropriate PPE throughout wall finishing operations.

Emergency preparedness

Availability of first aid and decontamination facilities complements PPE use by enabling prompt response to accidents involving hazardous materials.

The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒1.2 Wall finishing

Wall finishing involves applying surface treatments to walls to improve appearance, protect structural elements, and enhance durability. In Kenyan building projects, finishes must accommodate environmental factors such as humidity and UV exposure, while meetin…

🔒1.3 Tools and Equipment

In the Kenyan building industry, the selection and proper use of tools and equipment are critical to achieving quality wall finishes. Skilled artisans in construction sites across Nairobi, Kisumu, and Mombasa depend on appropriate tools to ensure efficient app…

🔒1.4 Wall Finish Materials

Wall finish materials determine not only the aesthetic appeal of a building but also its durability and resistance to environmental factors. In Kenya’s diverse climatic zones, from the humid coastal region to the cooler highlands, selecting appropriate materia…

🔒1.5 Wall Background

In the Kenyan building industry, the quality of wall finishes depends significantly on the condition of the wall background. Proper preparation and treatment of the wall background ensure durability, aesthetic appeal, and structural integrity of the finishes a…

🔒1.6 Execution Wall Finishes

The execution of wall finishes is a critical phase in building construction that transforms prepared surfaces into visually appealing and protective layers. In Kenya, wall finishes range from decorative plastering in hotels to durable paint coatings in county…

Chapter Summary

This chapter explored the essential protective equipment required for wall finishing tasks, detailing various types and their specific uses to ensure worker safety. It then examined the different methods of wall finishing, highlighting their applications in enhancing both the appearance and durability of walls. The chapter further identified the key tools and equipment involved, explaining their types and appropriate uses in the finishing process. A comprehensive overview of wall finish materials was provided, outlining the common types used in construction. Preparation of the wall background was discussed thoroughly, including the necessary steps and procedures to create a suitable surface for finishing. Finally, the chapter covered the execution of wall finishes, describing the various types and the step-by-step procedures required to achieve quality results in wall finishing projects.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. Identify four types of protective equipment commonly used during wall finishing works. (4 marks)
  2. Explain the main purpose of using protective equipment on a building site during wall finishing. (2 marks)
🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with model answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Identify four types of protective equipment commonly used by building finishers in Kenya and explain their primary use on site. (4 marks)
  2. Describe two methods of wall finishing suitable for internal walls in a commercial building. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Identify and select appropriate wall finish materials for given scenarios

Building Technology · Level 6
Building Finishes
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Identify and select appropriate wall finish materials for a 2.4m x 3.0m interior wall and a 2.4m x 3.0m exterior wall as per the provided specifications.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring tapeCement
Brushes (paint and varnish)Sand
Putty knifeWater
Emulsion paint
Wall putty
Varnish
Gloss paint
PVC wall cladding sheets
Ceramic wall tiles
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Cement bags1 bag per 5 Candidates
2Sand (fine and coarse)1 barrow per 3 Candidates
3WaterSufficient quantity per Candidate
4Emulsion paint 5 liters1 can per 5 Candidates
5Wall putty 2 kg1 pack per 5 Candidates
6Varnish 1 liter1 bottle per 5 Candidates
7Gloss paint 2.5 liters1 can per 5 Candidates
8PVC wall cladding sheets 300mm x 300mm samples1 set per Candidate
9Ceramic wall tiles 300mm x 300mm samples1 set per Candidate
10Brushes (paint and varnish)1 pc per Candidate
11Putty knife1 pc per Candidate
12Measuring tape1 pc per Candidate
13Safety gloves1 pair per Candidate
14Dust mask1 pc per Candidate
15Safety boots1 pair per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Identification and selection of wall finish materials
Wore PPEs (safety boots, gloves, dust mask)
(Award 1 mark each for safety boots, gloves, and dust mask correctly worn)
3
Measured wall dimensions accurately using measuring tape
(Award 3 marks for accurate measurement within ±5mm tolerance)
3
Identified at least five different wall finish materials from the samples
(Award 1 mark for each correct material identified, max 5 marks)
5
Selected suitable wall finish materials for interior wall with justification
(Award 2 marks each for correct selection, explanation of suitability, and application method)
6
Selected suitable wall finish materials for exterior wall with justification
(Award 2 marks each for correct selection, explanation of suitability, and application method)
6
Handled materials and tools safely and correctly during identification and selection
(Award 3 marks for safe and correct handling)
3
Sub-Total26
PRODUCT CHECKLIST
Accuracy of measured wall dimensions (2400mm x 3000mm)
(Award 4 marks for measurements within ±5mm tolerance)
4
Correctness and appropriateness of selected materials for interior wall
(Award 6 marks for correct and justified selection matching interior wall finish requirements)
6
Correctness and appropriateness of selected materials for exterior wall
(Award 6 marks for correct and justified selection matching exterior wall finish requirements)
6
Presentation and neatness of material samples and selection notes
(Award 4 marks for neat and clear presentation)
4
Completeness of task (100% completion)
(Award 4 marks if task is 100% complete; 3 marks for 75%; 2 marks for 50%; 1 mark for less than 50%)
4
Sub-Total24
GRAND TOTAL50
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Prepare Wall Background for Finishing on a 1.5m x 2.0m Masonry Wall

Building Technology · Level 6
Building Finishes
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Prepare the wall background of a 1500mm x 2000mm masonry wall by cleaning, smoothing, and priming it for finishing.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Masonry brushPrimer paint
Wire brushWater
Trowel
Bucket
Sandpaper
Paint brush
Tape measure
Spirit level
Plumb bob
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Overall (work suit)1 Pc per Candidate
2Safety gloves1 Pair per Candidate
3Safety boots1 Pair per Candidate
4Safety helmet1 Pc per Candidate
5Masonry brush1 Pc per Candidate
6Wire brush1 Pc per Candidate
7Trowel1 Pc per Candidate
8Bucket1 Pc per Candidate
9Water container with tap1 Pc per 5 Candidates
10Sandpaper (medium grit)1 Sheet per Candidate
11Primer paint (ready-mixed)1 Litre per 2 Candidates
12Paint brush (3 inch)1 Pc per Candidate
13Pre-existing masonry wall 1500mm by 2000mm1 Pc per Candidate
14Tape measure1 Pc per Candidate
15Spirit level1 Pc per Candidate
16Plumb bob1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Wall Background Preparation
Wore PPEs (overall, gloves, safety boots, safety helmet)
(Award 0.5 mark for each PPE worn = 2 Marks)
2
Cleaned the wall surface removing dust, dirt, loose particles using masonry and wire brushes
(Award 1 mark for each cleaning method applied correctly = 3 Marks)
3
Smoothed the wall surface using sandpaper to remove unevenness and rough patches
(Award 3 marks for uniform smoothing without damage)
3
Lightly dampened the wall surface with water using a brush or spray
(Award 2 marks for uniform dampening without pooling)
2
Applied primer coat uniformly on the wall surface using a paint brush
(Award 4 marks for even coverage and correct application technique)
4
Used spirit level and plumb bob to check wall verticality and surface flatness
(Award 2 marks for correct use and reading)
2
Cleaned and stored all tools correctly after use
(Award 2 marks for thorough cleaning and proper storage)
2
Cleaned the working area free from debris and waste
(Award 2 marks for complete cleaning)
2
Sub-Total20
PRODUCT CHECKLIST
Wall dimensions verified as 1500mm width and 2000mm height
(Award 3 marks for correct measurements within ±5mm tolerance)
3
Wall surface is smooth and free of dust, dirt, and loose particles
(Award 3 marks for uniform smoothness and cleanliness)
3
Primer coat is uniform, fully covering the wall without runs or missed patches
(Award 4 marks for even, neat primer application)
4
Wall is plumb and level as checked with spirit level and plumb bob
(Award 3 marks for plumbness and flatness within tolerance)
3
Overall completeness: 100% complete award 4 marks; 75% complete award 3 marks; 50% complete award 2 marks; below 50% award 1 mark
(Award marks according to completeness percentage)
4
Sub-Total17
GRAND TOTAL37
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Apply plaster as a wall finish on a 1.2m x 1.2m masonry wallPractical 3
🔒Apply Paint Finish on a 1.5m x 2m Wall SectionPractical 4
🔒Apply wall tiles on a prepared masonry wall surfacePractical 5
🔒Apply wallpaper as a wall finish on a 2.4m x 2.4m wallPractical 6
🔒Use hand tools to prepare and finish a plastered wall section 1200mm x 1800mmPractical 7
🔒Operate power tools for sanding and cutting wall finishing tasksPractical 8
🔒Mix and Prepare Plastering Mortar for Wall FinishesPractical 9
🔒Apply Protective Varnish Coating on Interior Wall 1500mm x 1200mmPractical 10
🔒Identify and Use Appropriate Personal Protective Equipment During Wall FinishingPractical 11
🔒Repair and patch wall surfaces before finishingPractical 12
🔒Apply Textured Wall Finishes on a 1.5m x 1.5m Wall SectionPractical 13
🔒Set out and mark wall finishing areas for plastering on a masonry wallPractical 14
🔒Clean and maintain wall finishing tools and equipmentPractical 15
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 20 questions Start quiz ▾
0%
0 / 2
🔒

18 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Wear the correct personal protective equipment and follow all safety procedures for the job.
  • Assemble all the tiling tools and equipment correctly and efficiently.
  • Screed the tiling surface accurately according to the National Building Code 2024 requirements.
  • Gather and prepare all the tiling materials needed for the job.
  • Set tiles precisely following the specifications on the working drawings.
  • Cut tiles accurately to match the design specifications.
  • Fix tiles securely according to the work specifications.
  • Grout tile joints properly following the National Building Code 2024 requirements.
  • Clean the tiled surface thoroughly to meet job standards.

Tick each one you can genuinely do.

Prove it — in the simulator

Sample simulation — try how the simulator works. A version built for this chapter's practical is coming.

Prepare Kenyan PilauLocked ▸

Free: practical guides, quick cards, workplace scenarios and more.

Now — are you there yet?

You're competent when you can confidently do 50% or more of what this chapter promised.

Sign in to record how you're doing.