Building Technology  ·  Level 6
Measurement, Estimation And Costing Of Building Works I
Chapter 3: Record project variations
📚 6 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • Identify and record project variations accurately with the project manager’s approval.
  • Calculate the valuation of variations correctly using standard practices.
  • Perform day work safely and correctly by following proper work procedures.
  • Recognize appraisal items according to the relevant code of practice.
  • Assess appraisal items to determine how much work has been completed.
  • Compile clear and accurate appraisal reports following standard methods.
  • Apply estimation methods correctly according to industry standards.
  • Prepare detailed specifications accurately based on work requirements.
  • Insert rate schedules for items using standard costing rates and site location data.
  • Prepare bills of quantities accurately to meet work requirements.

Mastering these skills will help you manage project changes effectively and ensure accurate costing, which is essential for success in the building trade.

Compiled by: John Wachira

Record keeping of project variations is a critical aspect of building technology in Kenya. Construction projects frequently encounter changes after contract signing due to unforeseen site conditions, client requests, or regulatory adjustments. Proper documentation and management of these variations ensure that the project remains within legal and financial control, preventing disputes and delays. For a building technology professional, understanding the nature, causes, and handling of variations safeguards both the client’s interests and the contractor’s rights.

3.1 Variations

Variations in building projects refer to any modifications or changes to the original scope, design, or specification of works agreed upon in the contract. In Kenya’s construction industry, variations are common due to dynamic project environments and evolving client needs. Managing these variations effectively requires clear identification, valuation, and approval processes to avoid cost overruns and schedule disruptions. This section unpacks the concept of variations, their types, causes, and the procedures for recording and managing them.

3.1.1 Meaning and Types of Variations

Variations are formal alterations to the original contract work, which can impact cost, time, or quality. Understanding the different types of variations enables building professionals to classify them correctly and respond appropriately during project execution.

Meaning of Variations

Variations occur when the client or project circumstances require changes from the initial contract documents. These changes might involve additions, omissions, or substitutions of work items. In the Kenyan context, such variations often arise from changes in government regulations or client preferences during the construction phase at sites like county government offices or university campuses.

Types of Variations

  • Additive Variations: These involve adding new work items or increasing quantities beyond the original scope. For example, adding extra rooms to a hospital wing after initial design completion.
  • Omission Variations: Removing certain work items initially included in the contract, such as excluding landscaping services at a hotel due to budget constraints.
  • Substitution Variations: Replacing specified materials or methods with alternatives, like swapping standard tiles for more durable ceramic tiles in a retail store renovation.
  • Design Variations: Changes to architectural or structural designs, often triggered by client requests or unforeseen site conditions encountered at a county office construction.
  • Time Variations: Adjustments to the project schedule due to changes in scope or delays caused by variations themselves.

3.1.2 Causes and Impacts of Variations

Identifying causes helps anticipate and manage variations before they disrupt project flow. Variations significantly affect project cost, duration, and quality if not controlled properly.

Causes of Variations

  • Incomplete Initial Design: Often, early project designs lack full detail, necessitating changes during construction. For instance, at a university construction site, missing structural details can prompt redesigns and additions.
  • Client-Initiated Changes: Clients may request enhancements or reductions after work has commenced, such as increasing the number of classrooms in a school building.
  • Regulatory Changes: New government policies or building codes introduced mid-project demand compliance modifications. An example is the introduction of stricter fire safety standards affecting hospital construction.
  • Unforeseen Site Conditions: Discovery of unstable soil or underground utilities may require foundation redesign or relocation of services.
  • Errors and Omissions in Contract Documents: Mistakes in drawings or specifications lead to necessary corrections on site.

Impacts of Variations

  • Cost Overruns: Variations often increase project costs due to additional materials, labor, and equipment.
  • Schedule Delays: Time extensions may be necessary to accommodate changes, affecting project completion deadlines.
  • Quality Risks: Substitutions or rushed changes may compromise workmanship or material standards.
  • Contractual Disputes: Poorly managed variations can cause disagreements between client and contractor, sometimes escalating to legal claims.
  • Resource Reallocation: Adjustments in manpower and materials disrupt planned workflows and procurement schedules.

3.1.3 Procedures for Recording Variations

Accurate and timely documentation of variations is essential to managing their effects on project delivery. Kenyan building projects typically follow structured procedures to ensure transparency and accountability.

Initiation and Notification

  • Variations usually start with a formal request from the client or consultant, which must be communicated in writing.
  • The contractor assesses the feasibility, impact on cost and time, and submits a variation proposal.
  • Early notification to all parties avoids misunderstandings and unauthorized work.

Documentation and Approval

  • A variation order document is prepared detailing the nature, scope, and justification for the change.
  • The variation order includes revised quantities, rates, and any time extensions proposed.
  • Approval must be obtained from the client or authorized representative before execution.
  • Proper filing and referencing of variation documents maintain an audit trail.

Valuation and Payment

  • Variations are valued based on contract rates, market prices, or negotiated sums.
  • The quantity surveyor or estimator calculates additional costs or credits for omissions.
  • Payment adjustments are agreed upon and incorporated into interim payment certificates.
  • Disputes over valuation require mediation or arbitration as per contract terms.

3.1.4 Challenges in Managing Variations and Mitigation Strategies

Managing variations effectively is often challenging due to communication gaps, documentation lapses, and conflicting interests. Building professionals must adopt proactive strategies to minimize negative impacts.

Challenges in Managing Variations

  • Delayed Approvals: Slow client response stalls variation implementation, leading to project delays.
  • Inadequate Documentation: Poor record-keeping causes confusion and disputes over scope and cost.
  • Cost Escalation Disputes: Differences in valuation methods create conflicts between contractor and client.
  • Scope Creep: Uncontrolled accumulation of minor changes inflates project scope beyond budget.
  • Communication Breakdowns: Lack of clear channels between project teams hampers variation handling.

Mitigation Strategies

  • Establish Clear Variation Procedures: Define roles, documentation requirements, and timelines in the contract.
  • Prompt Communication: Use formal channels and regular meetings to discuss and resolve variation issues.
  • Detailed Record Keeping: Maintain comprehensive logs, variation order registers, and supporting documents.
  • Engage Quantity Surveyors Early: Accurate cost estimates prevent surprises and support negotiations.
  • Train Project Teams: Enhance awareness of variation impacts and management protocols among site staff.

Practice Questions

  1. Explain the different types of variations encountered in building projects and provide examples relevant to the Kenyan construction industry. (10 marks)

  2. Discuss five common causes of variations in construction projects and how they impact project outcomes in terms of cost and schedule. (10 marks)

  3. Outline the standard procedure for recording and approving variations on a building project, highlighting key documentation involved. (10 marks)

  4. Identify challenges faced in managing project variations and propose mitigation strategies suitable for a county government housing project. (10 marks)

The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒3.2 Methods of valuing variations

In building projects across Kenya, variations commonly arise due to changes in design, unforeseen site conditions, or client requests. Accurately valuing these variations is critical for maintaining project budgets and ensuring fair compensation for contractor…

🔒3.3 Day Works

Day works represent a critical contractual arrangement in building projects, particularly in Kenya where unforeseen site conditions or urgent client requests often necessitate adjustments to the original scope. This method allows payment for work executed base…

🔒3.4 Contract rates

Contract rates form a fundamental part of building project management in Kenya. These rates represent the agreed prices for specific works or materials as stipulated in the contract between the client and the contractor. Understanding contract rates is crucial…

🔒3.5 Star rates

In building technology, star rates are critical for establishing unit rates that reflect the true cost of work items under specific conditions. Star rates are especially relevant in Kenya where variations in site conditions, material availability, and labour p…

🔒3.6 Pro-rata rates

In building projects, variations are common due to changes in design, unforeseen site conditions, or client requests. When such variations involve quantities or works not explicitly priced in the original contract, pro-rata rates provide a method to fairly ass…

Chapter Summary

This chapter explores the concept of variations in building projects, which are changes made to the original scope of work after the contract has been signed. It discusses different methods used to value these variations, ensuring that adjustments in cost and work are fairly assessed. The chapter explains day works as a method where labor, materials, and plant are paid based on actual time and quantities used, typically for unforeseen tasks. Contract rates are examined as predetermined prices agreed upon in the contract for specific work items, providing a basis for valuing variations related to those items. Star rates are introduced as special rates applied to new or altered work that does not fit into the original contract schedule. Lastly, the chapter covers pro-rata rates, which adjust existing contract rates proportionally when the scope or quantity of work changes. Together, these topics provide a comprehensive understanding of how project variations are recorded and valued in building works.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. What is a variation in the context of building contracts? (2 marks)
  2. List three common reasons why variations occur during building projects. (3 marks)
🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Define project variations in building works and explain why they must be properly recorded during construction at a county government hospital project. (4 marks)
  2. List and briefly describe four common methods of valuing variations used in building contracts in Kenya. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Identify and Record Variations on Site for a Residential Extension

Building Technology · Level 6
Measurement, Estimation And Costing Of Building Works I
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Inspect the 6m x 5m residential extension site and record all variations from the original plans.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring tape 30 metersSite notebook
PencilOriginal building plan drawings
EraserPersonal Protective Equipment (helmet, safety boots, dust coat)
Digital camera or smartphone with camera
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Measuring tape 30 meters1 Pc per Candidate
2Site notebook1 Pc per Candidate
3Pencil1 Pc per Candidate
4Eraser1 Pc per Candidate
5Digital camera or smartphone with camera1 Pc per Candidate
6Original building plan drawings1 Set per Candidate
7Personal Protective Equipment (helmet, safety boots, dust coat)1 Set per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Site Inspection and Identification of Variations
Wore Personal Protective Equipment (helmet, safety boots, dust coat)
(Award 1 mark each for helmet, safety boots, and dust coat worn)
3
Reviewed original building plans prior to inspection
(Award 2 marks for thorough review or zero)
2
Measured key dimensions on site (length, width, height) and compared with plans
(Award 2 marks each for correctly measuring length, width, and height)
6
Noted and described any deviations or variations from original plans
(Award up to 5 marks for accurate and complete identification of variations)
5
Photographed areas of variation clearly and appropriately
(Award 4 marks for clear, relevant photos or zero)
4
Recorded all findings legibly and systematically in site notebook
(Award 3 marks for neat, complete records or zero)
3
Sub-Total23
TASK 2: Preparation of Variation Record Report
Prepared a clear variation record sheet listing all variations with descriptions
(Award 5 marks for complete and clear variation record or zero)
5
Included measurements and photographic references in report
(Award 4 marks for inclusion of measurements and photos or zero)
4
Reported the possible cost or impact of each variation briefly
(Award 3 marks for reasonable cost impact notes or zero)
3
Presented the report neatly and logically organized
(Award 3 marks for neat presentation or zero)
3
Sub-Total15
PRODUCT CHECKLIST
Recorded length variation: measured 6.3m instead of 6.0m
(Award 3 marks for correct measurement and record or zero)
3
Recorded width variation: measured 4.8m instead of 5.0m
(Award 3 marks for correct measurement and record or zero)
3
Recorded height variation: wall height 2.7m instead of 3.0m
(Award 3 marks for correct measurement and record or zero)
3
Accurate and complete variation description for at least three variations
(Award 5 marks for clarity and completeness or zero)
5
Variation record report includes photographic evidence linked to each variation
(Award 3 marks for photographic evidence or zero)
3
Report is neat, legible, and logically arranged
(Award 3 marks for overall presentation or zero)
3
Sub-Total20
GRAND TOTAL58
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Valuation of Project Variations Using Contract Rates

Building Technology · Level 6
Measurement, Estimation And Costing Of Building Works I
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Calculate and prepare a valuation report for a project variation involving an increased concrete slab area of 25m² and additional brickwork of 15m² using the given contract rates.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
CalculatorContract document with rates
Scale rulerVariation order document
PenField book
Pencil
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Contract document with rates1 set per Candidate
2Variation order document1 per Candidate
3Calculator1 per Candidate
4Scale ruler1 per Candidate
5Field book1 per Candidate
6Pen and pencil1 each per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Valuation Calculation and Reporting
Wore appropriate Personal Protective Equipment (PPE) if applicable
(Award 1 mark each for correctly worn PPE items; max 2 marks)
2
Interpreted contract rates accurately from contract document
(Award 5 marks for correct identification and interpretation of rates)
5
Extracted and recorded variation quantities correctly from variation order
(Award 3 marks for each correct quantity extracted; total 6 marks)
6
Applied contract rates correctly to the variation quantities
(Award 7 marks for correct application of rates to quantities)
7
Prepared clear and accurate valuation calculations in the field book
(Award 4 marks for neat, clear, and correct calculations)
4
Compiled a summary valuation report with totals and clear presentation
(Award 5 marks for completeness and clarity of report)
5
Sub-Total29
PRODUCT CHECKLIST
Accurate valuation of increased concrete slab area (25m²) at correct contract rate
(Award 5 marks for correct calculation matching contract rate)
5
Accurate valuation of additional brickwork area (15m²) at correct contract rate
(Award 5 marks for correct calculation matching contract rate)
5
Overall total variation value correctly computed and clearly presented
(Award 7 marks for correct summation and clear presentation)
7
Sub-Total17
GRAND TOTAL46
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Valuation of Project Variations Using Day Works MethodPractical 3
🔒Variation Valuation Using Star RatesPractical 4
🔒Valuation of Partially Completed Variation Works Using Pro-Rata RatesPractical 5
🔒Prepare Variation Record Sheet with Multiple Valuation MethodsPractical 6
🔒Interpret Working Drawings to Identify Variation Impact on Residential Wall ExtensionPractical 7
🔒Calculate Variation Costs from Revised Working DrawingsPractical 8
🔒Measure quantities for day works valuation of labor and materialsPractical 9
🔒Compile a Variation Cost Report for Client SubmissionPractical 10
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 16 questions Start quiz ▾
0%
0 / 2
🔒

14 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Identify and record project variations accurately with the project manager’s approval.
  • Calculate the valuation of variations correctly using standard practices.
  • Perform day work safely and correctly by following proper work procedures.
  • Recognize appraisal items according to the relevant code of practice.
  • Assess appraisal items to determine how much work has been completed.
  • Compile clear and accurate appraisal reports following standard methods.
  • Apply estimation methods correctly according to industry standards.
  • Prepare detailed specifications accurately based on work requirements.
  • Insert rate schedules for items using standard costing rates and site location data.
  • Prepare bills of quantities accurately to meet work requirements.

Tick each one you can genuinely do.

So, are you there yet?

You're competent when you can confidently do 50% or more of what this chapter promised.