By the end of this chapter, you will be able to:
Mastering these skills will help you manage project changes effectively and ensure accurate costing, which is essential for success in the building trade.
Compiled by: John Wachira
Record keeping of project variations is a critical aspect of building technology in Kenya. Construction projects frequently encounter changes after contract signing due to unforeseen site conditions, client requests, or regulatory adjustments. Proper documentation and management of these variations ensure that the project remains within legal and financial control, preventing disputes and delays. For a building technology professional, understanding the nature, causes, and handling of variations safeguards both the client’s interests and the contractor’s rights.
Variations in building projects refer to any modifications or changes to the original scope, design, or specification of works agreed upon in the contract. In Kenya’s construction industry, variations are common due to dynamic project environments and evolving client needs. Managing these variations effectively requires clear identification, valuation, and approval processes to avoid cost overruns and schedule disruptions. This section unpacks the concept of variations, their types, causes, and the procedures for recording and managing them.
Variations are formal alterations to the original contract work, which can impact cost, time, or quality. Understanding the different types of variations enables building professionals to classify them correctly and respond appropriately during project execution.
Variations occur when the client or project circumstances require changes from the initial contract documents. These changes might involve additions, omissions, or substitutions of work items. In the Kenyan context, such variations often arise from changes in government regulations or client preferences during the construction phase at sites like county government offices or university campuses.
Identifying causes helps anticipate and manage variations before they disrupt project flow. Variations significantly affect project cost, duration, and quality if not controlled properly.
Accurate and timely documentation of variations is essential to managing their effects on project delivery. Kenyan building projects typically follow structured procedures to ensure transparency and accountability.
Managing variations effectively is often challenging due to communication gaps, documentation lapses, and conflicting interests. Building professionals must adopt proactive strategies to minimize negative impacts.
Explain the different types of variations encountered in building projects and provide examples relevant to the Kenyan construction industry. (10 marks)
Discuss five common causes of variations in construction projects and how they impact project outcomes in terms of cost and schedule. (10 marks)
Outline the standard procedure for recording and approving variations on a building project, highlighting key documentation involved. (10 marks)
Identify challenges faced in managing project variations and propose mitigation strategies suitable for a county government housing project. (10 marks)
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter explores the concept of variations in building projects, which are changes made to the original scope of work after the contract has been signed. It discusses different methods used to value these variations, ensuring that adjustments in cost and work are fairly assessed. The chapter explains day works as a method where labor, materials, and plant are paid based on actual time and quantities used, typically for unforeseen tasks. Contract rates are examined as predetermined prices agreed upon in the contract for specific work items, providing a basis for valuing variations related to those items. Star rates are introduced as special rates applied to new or altered work that does not fit into the original contract schedule. Lastly, the chapter covers pro-rata rates, which adjust existing contract rates proportionally when the scope or quantity of work changes. Together, these topics provide a comprehensive understanding of how project variations are recorded and valued in building works.
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring tape 30 meters | Site notebook |
| Pencil | Original building plan drawings |
| Eraser | Personal Protective Equipment (helmet, safety boots, dust coat) |
| Digital camera or smartphone with camera |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring tape 30 meters | 1 Pc per Candidate |
| 2 | Site notebook | 1 Pc per Candidate |
| 3 | Pencil | 1 Pc per Candidate |
| 4 | Eraser | 1 Pc per Candidate |
| 5 | Digital camera or smartphone with camera | 1 Pc per Candidate |
| 6 | Original building plan drawings | 1 Set per Candidate |
| 7 | Personal Protective Equipment (helmet, safety boots, dust coat) | 1 Set per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Site Inspection and Identification of Variations | |||
| Wore Personal Protective Equipment (helmet, safety boots, dust coat) (Award 1 mark each for helmet, safety boots, and dust coat worn) | 3 | ||
| Reviewed original building plans prior to inspection (Award 2 marks for thorough review or zero) | 2 | ||
| Measured key dimensions on site (length, width, height) and compared with plans (Award 2 marks each for correctly measuring length, width, and height) | 6 | ||
| Noted and described any deviations or variations from original plans (Award up to 5 marks for accurate and complete identification of variations) | 5 | ||
| Photographed areas of variation clearly and appropriately (Award 4 marks for clear, relevant photos or zero) | 4 | ||
| Recorded all findings legibly and systematically in site notebook (Award 3 marks for neat, complete records or zero) | 3 | ||
| Sub-Total | 23 | ||
| TASK 2: Preparation of Variation Record Report | |||
| Prepared a clear variation record sheet listing all variations with descriptions (Award 5 marks for complete and clear variation record or zero) | 5 | ||
| Included measurements and photographic references in report (Award 4 marks for inclusion of measurements and photos or zero) | 4 | ||
| Reported the possible cost or impact of each variation briefly (Award 3 marks for reasonable cost impact notes or zero) | 3 | ||
| Presented the report neatly and logically organized (Award 3 marks for neat presentation or zero) | 3 | ||
| Sub-Total | 15 | ||
| PRODUCT CHECKLIST | |||
| Recorded length variation: measured 6.3m instead of 6.0m (Award 3 marks for correct measurement and record or zero) | 3 | ||
| Recorded width variation: measured 4.8m instead of 5.0m (Award 3 marks for correct measurement and record or zero) | 3 | ||
| Recorded height variation: wall height 2.7m instead of 3.0m (Award 3 marks for correct measurement and record or zero) | 3 | ||
| Accurate and complete variation description for at least three variations (Award 5 marks for clarity and completeness or zero) | 5 | ||
| Variation record report includes photographic evidence linked to each variation (Award 3 marks for photographic evidence or zero) | 3 | ||
| Report is neat, legible, and logically arranged (Award 3 marks for overall presentation or zero) | 3 | ||
| Sub-Total | 20 | ||
| GRAND TOTAL | 58 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Calculator | Contract document with rates |
| Scale ruler | Variation order document |
| Pen | Field book |
| Pencil |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Contract document with rates | 1 set per Candidate |
| 2 | Variation order document | 1 per Candidate |
| 3 | Calculator | 1 per Candidate |
| 4 | Scale ruler | 1 per Candidate |
| 5 | Field book | 1 per Candidate |
| 6 | Pen and pencil | 1 each per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Valuation Calculation and Reporting | |||
| Wore appropriate Personal Protective Equipment (PPE) if applicable (Award 1 mark each for correctly worn PPE items; max 2 marks) | 2 | ||
| Interpreted contract rates accurately from contract document (Award 5 marks for correct identification and interpretation of rates) | 5 | ||
| Extracted and recorded variation quantities correctly from variation order (Award 3 marks for each correct quantity extracted; total 6 marks) | 6 | ||
| Applied contract rates correctly to the variation quantities (Award 7 marks for correct application of rates to quantities) | 7 | ||
| Prepared clear and accurate valuation calculations in the field book (Award 4 marks for neat, clear, and correct calculations) | 4 | ||
| Compiled a summary valuation report with totals and clear presentation (Award 5 marks for completeness and clarity of report) | 5 | ||
| Sub-Total | 29 | ||
| PRODUCT CHECKLIST | |||
| Accurate valuation of increased concrete slab area (25m²) at correct contract rate (Award 5 marks for correct calculation matching contract rate) | 5 | ||
| Accurate valuation of additional brickwork area (15m²) at correct contract rate (Award 5 marks for correct calculation matching contract rate) | 5 | ||
| Overall total variation value correctly computed and clearly presented (Award 7 marks for correct summation and clear presentation) | 7 | ||
| Sub-Total | 17 | ||
| GRAND TOTAL | 46 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.