By the end of this chapter, you will be able to:
Mastering these skills ensures your measurements are precise and reliable, which is essential for successful building projects and professional growth in the trade.
Building a durable and stable structure begins with a well-executed substructure. In architectural practice in Kenya, the substructure forms the critical foundation that supports the entire building above ground. Precise measurement and clear documentation of substructure works ensure that construction proceeds according to design specifications, preventing costly errors and ensuring safety. This chapter delves into the principles of applying substructure works taking off, focusing on key elements such as excavation, blinding, damp-proofing, reinforcement, and foundation components.
Accurate documentation of substructure elements is vital for architects and quantity surveyors to quantify work, estimate costs, and ensure compliance with building regulations. Each element within the substructure has specific measurement principles and construction requirements that impact the overall stability and longevity of the building. In Kenya, adherence to standards stipulated by the National Construction Authority (NCA) and the Building Code is essential when documenting these elements.
Trench excavation is the initial step in preparing the ground for foundation works. It involves removing soil to specified dimensions to accommodate foundation footings or strip foundations. This process requires careful consideration of soil type, depth, and safety to prevent collapse or undermining adjacent structures.
Trench excavation refers to the removal of earth along a narrow, elongated area to form a trench that will receive foundation elements. Its purpose is to create a stable base free from loose or organic materials, ensuring the foundation rests on firm soil. For example, in a Nairobi County government office construction, trench excavation must reach depths that avoid seasonal water table fluctuations to minimize settlement risks.
Measurement involves recording the length, width, and depth of the trench in cubic meters. The width includes allowances for formwork and working space, not just the foundation base width. Depth must be measured from the original ground level to the bottom of the trench, considering any benching or battering slopes as required by site conditions. Kenyan quantity surveyors must verify these dimensions on-site to prevent under- or over-measurement.
Excavation must comply with safety standards to protect workers and prevent collapse. In urban Nairobi, trenches near existing utilities require coordination with service providers to avoid damaging water or electrical lines. Environmental concerns include managing displaced soil and preventing erosion, especially during rainy seasons.
The reducing level (RL) is a critical vertical datum used in setting out foundations. It indicates the height relative to a fixed reference point, guiding excavation and construction levels.
Reducing level is the vertical height assigned to a specific point on site, often relative to mean sea level or a benchmark established by surveyors. It guides excavation depth and ensures uniformity in foundation levels across the site. For instance, at a county hospital expansion project in Kisumu, accurate RLs prevent uneven foundation depths that could cause structural imbalance.
RLs are determined using leveling instruments such as a dumpy level or automatic level. Surveyors establish a reference benchmark, then measure vertical distances to excavation points. These measurements must be precise, as errors in RLs can lead to foundation misalignment.
Once determined, RLs are recorded on site drawings and used to guide excavation and construction teams. Architects and quantity surveyors use RL data to verify that foundation elements are constructed at the correct depth, ensuring compliance with design specifications.
Blinding is a thin layer of concrete placed on the excavated surface before the foundation is constructed. It provides a clean, level base and prevents contamination of structural concrete by soil.
Blinding protects the foundation concrete from dirt, moisture, and loose soil, which can weaken the foundation. It also provides a level working surface for setting out reinforcement and formwork. In a retail complex foundation in Mombasa, blinding ensures that the base is clean and level, facilitating accurate reinforcement placement.
Blinding typically uses lean concrete with a low cement content, such as mix 1:4:8 (cement:sand:aggregate), and is usually 50 to 100 mm thick. The choice of materials and thickness depends on site conditions and structural requirements.
Measurement is by area and thickness to calculate volume in cubic meters. Quantity surveyors must ensure that blinding is accounted for separately from foundation concrete in bills of quantities, reflecting its distinct purpose and cost.
A damp-proof membrane (DPM) is a thin impervious layer placed beneath the floor slab or foundation to prevent moisture migration from the ground.
DPM prevents rising damp that can damage finishes and structural elements. It is crucial in Kenya’s humid coastal regions, where moisture ingress can cause mold growth and corrosion. For example, in coastal hotels in Mombasa, DPMs extend the durability of floor finishes and internal walls.
Common materials include polyethylene sheets, bitumen-based membranes, or rubberized asphalt. Thickness typically ranges from 0.15 to 0.5 mm depending on the product. Selection depends on site conditions, cost, and compatibility with other materials.
Measurement is by area in square meters, including overlaps and laps. Installation requires careful sealing at joints and edges to maintain continuity. Quantity surveyors must document the DPM type and area accurately for procurement and quality control.
Reinforcement bars (rebars) strengthen concrete foundations, providing tensile strength that concrete alone cannot resist.
Rebars resist tensile stresses caused by loads and prevent cracking. In Nairobi’s high-rise residential buildings, proper reinforcement ensures foundation integrity under variable loading conditions.
Common rebars are made of mild steel or high-yield steel, with diameters ranging from 6 mm to 25 mm. Kenyan Standard KS EAS 18 specifies mechanical properties and dimensions to ensure quality.
Rebar measurement is by weight (kilograms) or length (meters), depending on contract requirements. Accurate cutting schedules and bending details are essential for cost estimation and minimizing wastage.
BRC (British Reinforcement Concrete) mesh is a prefabricated steel reinforcement used for slabs and sometimes in foundations to distribute loads evenly.
BRC mesh consists of welded steel bars arranged in a grid pattern, providing uniform reinforcement. In county government office floor slabs, BRC mesh accelerates construction and ensures consistent load distribution.
Mesh sizes vary, commonly 150 mm x 150 mm spacing, with bar diameters from 6 mm to 12 mm. Kenyan projects follow KS EAS 18 and manufacturer guidelines for installation.
Measured by area (square meters), BRC mesh must be handled carefully to avoid bending or damage. Documentation includes mesh type, size, and quantity for accurate billing.
The damp proof course (DPC) is a horizontal barrier in walls near the ground level that prevents moisture rising from the foundation into the walls.
DPC protects walls and finishes from dampness, which can cause structural deterioration and health hazards. In schools around Nakuru, DPC ensures classrooms remain dry and comfortable.
Materials include bituminous felt, polyethylene sheets, or slate. Installation requires continuous, unbroken layers at least 150 mm above ground level.
Measured by length and width, DPC is included in walling bills of quantities. Accurate documentation ensures correct quantities and prevents moisture-related defects.
Foundation strips are continuous concrete footings supporting walls, distributing structural loads safely to the ground.
Foundation strips spread loads from walls over a wider soil area to prevent settlement. In county hospitals, well-designed foundation strips ensure longevity despite heavy equipment loads.
Dimensions depend on soil bearing capacity and wall load, often ranging from 450 mm to 900 mm wide and 150 mm to 300 mm thick. Kenyan architects must consider local soil tests when specifying sizes.
Measured in cubic meters, foundation strips require length, width, and thickness for volume calculation. Correct measurement avoids cost overruns due to underestimation.
Foundation walls transfer loads from the superstructure to the foundation strip or footing.
Foundation walls may be concrete, masonry, or stone, depending on design and materials availability. For example, in rural cooperative housing projects, stone foundation walls are common due to local material access.
Walls must be constructed with durable materials and proper mortar mix to resist moisture and soil pressure. Kenyan building codes require minimum compressive strength and proper curing.
Measured by length, height, and thickness to calculate volume or area. Detailed records ensure accurate cost estimation and quality control.
Hard core fill consists of compacted inert materials used to provide a stable base beneath floors or slabs.
It improves load distribution, prevents settlement, and facilitates drainage beneath floors. For instance, in hotel foundations in Kisii, hard core fill prevents water pooling and supports heavy loads.
Materials include crushed stone, gravel, or broken concrete. Compaction to specified density is crucial for performance, with Kenyan standards requiring at least 95% Proctor density.
Measured in cubic meters, hard core fill quantities depend on excavation depth and slab thickness. Proper site preparation and compaction records are essential for compliance.
The floor bed is the layer on which the floor finish is laid, often consisting of sand and cement mix.
It provides a smooth, level surface for floor finishes and protects underlying structural elements. In university lecture halls, a well-prepared floor bed ensures even tile installation.
Typically a 25 to 50 mm thick mix of cement and sharp sand, the floor bed must be durable and well-bonded. Material quality directly affects floor finish durability.
Measured by area and thickness for volume calculation. Accurate documentation helps in procurement and quality assurance.
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter provided a comprehensive overview of the principles involved in applying substructure works taking off. It began by detailing the documentation required for key substructure elements such as trench excavation, reducing level, blinding, damp-proof membrane, reinforcement bars, BRC mesh, damp proof course, foundation strip, foundation walling, hard core fill, and floor bed. The focus then shifted to the quantification of these elements, explaining how to accurately measure and calculate the volumes and areas necessary for each component to ensure proper resource allocation and cost estimation. Following quantification, the chapter addressed the booking process for the same substructure elements, emphasizing the importance of precise recording and organization of measurements in the building works context. Through this structured approach, students gain the skills to document, quantify, and book substructure works effectively, laying a solid foundation for accurate project planning and execution in construction.
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Computer with Microsoft Excel software | Architectural plan (A3 size) |
| Scientific calculator | Structural drawings |
| Stationery: pencils, erasers, rulers, pens | Bill of Quantities abstract sheets |
| Dimension sheets | |
| Billing sheets | |
| CESMM/SMM reference booklet |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Architectural plan (A3 size) | 1 set per Candidate |
| 2 | Structural drawings | 1 set per Candidate |
| 3 | Bill of Quantities abstract sheets | 2 sheets per Candidate |
| 4 | Dimension sheets | 2 sheets per Candidate |
| 5 | Billing sheets | 2 sheets per Candidate |
| 6 | CESMM/SMM reference booklet | 1 per 3 Candidates |
| 7 | Computer with Microsoft Excel software | 1 per Candidate |
| 8 | Scientific calculator | 1 per Candidate |
| 9 | Stationery: pencils, erasers, rulers, pens | Set per Candidate |
| 10 | Printer with printing paper | Shared among 5 Candidates |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Identification and preparation of documents | |||
| Identified all relevant documents used to prepare BOQ: Bill paper, CESMM/SMM, Abstract Paper (Award 1 mark each or zero x 3 = 3 Marks) | 3 | ||
| Observed occupational safety and health precautions in the computer lab: Ventilation, Lighting, Sanitation (Award 1 mark each or zero x 3 = 3 Marks) | 3 | ||
| Sub-Total | 6 | ||
| TASK 2: Interpretation and transfer of dimensions | |||
| Interpreted the architectural and structural plans: Dimensions, substructure elements (Award 2 marks each or zero x 2 = 4 Marks) | 4 | ||
| Transferred the scaled dimensions into the dimension paper: 9000mm length (Award 2 marks) | 2 | ||
| Transferred the scaled dimensions into the dimension paper: 6000mm width (Award 2 marks) | 2 | ||
| Sub-Total | 8 | ||
| TASK 3: Calculations and documentation | |||
| Transferred calculations from dimension paper to abstract paper: Volume and Area of strip foundations (Award 2 marks each or zero x 2 = 4 Marks) | 4 | ||
| Transferred calculations from abstract paper to billing paper: Volume (concrete), Area (hardcore filling), Length (formwork) (Award 2 marks each or zero x 3 = 6 Marks) | 6 | ||
| Sub-Total | 10 | ||
| TASK 4: Use of Microsoft Excel software | |||
| Correctly set up Microsoft Excel workbook for BOQ preparation (Award 2 marks) | 2 | ||
| Keyed data from billing sheet into relevant Excel columns (Award 3 marks) | 3 | ||
| Used Excel formulas to verify quantities: Auto sum, Average, Multiplication (Award 2 marks each or zero x 3 = 6 Marks) | 6 | ||
| Saved the Excel project file with appropriate project title (Award 2 marks) | 2 | ||
| Printed the BOQ document and prepared the booklet for handover (Award 2 marks) | 2 | ||
| Switched off the computer correctly after completion (Award 2 marks) | 2 | ||
| Sub-Total | 17 | ||
| PRODUCT CHECKLIST | |||
| Completed Bill of Quantities document containing: Item column, Description column, Unit column, Rate column, Amount column (Award 2 marks each or zero x 3 = 6 Marks) | 6 | ||
| Accurate transfer and matching of scaled dimensions (9000mm length and 6000mm width) in documentation (Award 2 marks each or zero x 2 = 4 Marks) | 4 | ||
| Correct calculation and presentation of quantities for all substructure elements (Award 5 marks) | 5 | ||
| Sub-Total | 15 | ||
| GRAND TOTAL | 56 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Tape measure 30m | Working drawing showing trench dimensions |
| Builder's square | |
| Mason's line and pegs | |
| Spade | |
| Pick axe | |
| Spirit level 600mm | |
| Plumb bob | |
| Safety helmet | |
| Safety boots | |
| Gloves | |
| Marking paint |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Tape measure 30m | 1 Pc per Candidate |
| 2 | Builder's square | 1 Pc per Candidate |
| 3 | Mason's line and pegs | 1 Set per Candidate |
| 4 | Spade | 1 Pc per Candidate |
| 5 | Pick axe | 1 Pc per Candidate |
| 6 | Spirit level 600mm | 1 Pc per Candidate |
| 7 | Plumb bob | 1 Pc per Candidate |
| 8 | Safety helmet | 1 Pc per Candidate |
| 9 | Safety boots | 1 Pair per Candidate |
| 10 | Gloves | 1 Pair per Candidate |
| 11 | Working drawing showing trench dimensions | 1 Pc per Candidate |
| 12 | Marking paint | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Prepare and mark out trench | |||
| Wears appropriate PPE (helmet, boots, gloves) (Award 2 marks for all PPE worn correctly or zero) | 2 | ||
| Identifies and uses working drawing for trench dimensions (Award 2 marks for correct use or zero) | 2 | ||
| Measures and marks out trench length 4500mm accurately (Award 3 marks for length within ±10mm or zero) | 3 | ||
| Measures and marks out trench width 600mm accurately (Award 3 marks for width within ±10mm or zero) | 3 | ||
| Sets mason’s line and pegs correctly to define trench edges (Award 2 marks for correct line and pegs or zero) | 2 | ||
| Checks squareness of trench corners using builder’s square (Award 3 marks for squareness within ±5mm or zero) | 3 | ||
| Sub-Total | 15 | ||
| TASK 2: Excavate trench to specified depth | |||
| Uses spade and pick axe safely and effectively for excavation (Award 3 marks for safe and proper use or zero) | 3 | ||
| Excavates trench to 1200mm depth within ±20mm tolerance (Award 4 marks for correct depth or zero) | 4 | ||
| Maintains trench width and length during excavation (Award 3 marks for consistent dimensions within ±10mm or zero) | 3 | ||
| Uses spirit level and plumb bob to check trench bottom level and vertical faces (Award 3 marks for level and plumb within ±10mm or zero) | 3 | ||
| Sub-Total | 13 | ||
| PRODUCT CHECKLIST | |||
| Trench length is 4500mm ±10mm as per drawing (Award 3 marks for correct length or zero) | 3 | ||
| Trench width is 600mm ±10mm as per drawing (Award 3 marks for correct width or zero) | 3 | ||
| Trench depth is 1200mm ±20mm as per drawing (Award 4 marks for correct depth or zero) | 4 | ||
| Trench corners are square within 5mm tolerance (Award 3 marks for squareness or zero) | 3 | ||
| Trench faces and bottom are vertical and level within tolerance (Award 3 marks for plumb and level or zero) | 3 | ||
| Sub-Total | 16 | ||
| GRAND TOTAL | 44 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.