Architecture  ·  Level 6
Construction Project Management
Chapter 1: Organise construction site
📚 3 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • Organise and set up site hoarding correctly to define construction site boundaries while following all safety procedures.
  • Designate site activities clearly and effectively according to the site layout plan.
  • Install site utilities accurately by following the required work procedures step-by-step.

Mastering these skills ensures a safe, efficient, and well-organised construction site, which is essential for successful project management in the trade.

Construction site organisation is a critical phase in architectural project management, influencing safety, efficiency, and overall project success. In Kenya, where urban construction sites often face space constraints and complex regulatory requirements, meticulous site planning ensures smooth workflow and compliance with local standards. This chapter explores the essential elements of organising a construction site, focusing on site hoarding and the designation of site activities. Understanding these aspects equips architecture professionals to manage site logistics effectively, reducing delays and enhancing collaboration among stakeholders.

1.1 Site hoarding erection

Site hoarding is a fundamental element in managing construction sites, serving multiple purposes including security, safety, and public communication. In Kenya, erecting appropriate hoarding is often mandated by county government regulations to protect both the site and the public. Proper hoarding also helps delineate the construction boundary clearly, preventing unauthorized access and minimizing hazards to passersby and neighbouring properties.

1.1.1 Types of hoarding

Site hoarding comes in various forms, each suited for different site conditions and project requirements. The choice of hoarding type impacts not only security but also project image and community relations.

1.1.1.1 Timber hoarding

Timber hoarding is widely used in Nairobi and other urban centres due to its availability and ease of installation. It involves erecting wooden panels, usually plywood or boards, supported by timber or steel posts set in the ground and braced on the site side. Timber hoarding provides a solid physical barrier that can be painted with project information, but it requires maintenance to prevent deterioration from weather. It is normally about 2.4 m high, with lockable gates for vehicles and workers. Example: a contractor building a four-storey SACCO office block in Nyeri enclosed the site with painted plywood hoarding displaying the project signboard and safety notices.

Name Specification Use
Timber posts Treated cypress, 100 × 100 mm, about 3.0 m long Main vertical supports, set about 600 mm into the ground
Rails Treated timber, 50 × 100 mm Horizontal members fixing the panels to the posts
Plywood sheets 2 440 × 1 220 mm, 12 mm thick, exterior grade Solid hoarding panels
Raking struts Treated timber, 50 × 100 mm Bracing the hoarding against wind
Nails and screws Galvanised, 75 to 100 mm Fixing rails and panels
Paint Exterior-grade emulsion or enamel Protecting timber and displaying project information
Steps for erecting timber hoarding
  1. Set out the line: Mark the hoarding line on the site boundary with pegs and a string line, including gate positions.
  2. Dig post holes: Excavate holes about 600 mm deep at the planned post spacing.
  3. Erect the posts: Stand the treated posts in the holes, plumb them and fix them with concrete or rammed soil.
  4. Fix the rails: Nail or screw horizontal rails to the posts at the bottom, middle and top.
  5. Fix the panels: Nail the plywood sheets to the rails, keeping joints tight and the top line level.
  6. Brace the hoarding: Fix raking struts on the site side to resist wind loads.
  7. Hang the gates: Install lockable vehicle and pedestrian gates with strong hinges.
  8. Paint and sign: Paint the hoarding and fix the project signboard and safety signs.
Worked example: posts and plywood sheets

Number of posts = perimeter ÷ post spacing (closed loop)

A site measures 40 m × 30 m, and posts are spaced at 2.4 m.

Perimeter = 2 × (40 + 30) = 140 m

Number of posts = 140 ÷ 2.4

Number of posts = 58.3, rounded up to 59 posts

Number of sheets = perimeter ÷ sheet width (sheets fixed upright)

Number of sheets = 140 ÷ 1.22

Number of sheets = 114.8, rounded up to 115 sheets

1.1.1.2 Steel hoarding

Steel hoarding, often made from corrugated iron sheets or profiled steel panels fixed to steel posts and rails, offers enhanced durability and security compared to timber. It is favoured for large commercial projects such as shopping malls or office complexes, for example, in Nairobi’s Westlands area, where vandalism risks are higher. Steel hoarding is fire-resistant and can be reused across projects, though it is heavier and requires more robust support. Modular steel hoarding systems with bolted panels can be erected and dismantled quickly. Example: a contractor extending a referral hospital erected galvanised steel panel hoarding around the works so the busy hospital compound stayed safe and the panels could be reused on the next project.

Name Specification Use
Steel posts Square hollow section 50 × 50 mm or 75 × 75 mm, about 3.0 m long Vertical supports set in concrete
Steel rails Angle or hollow section, 40 × 40 mm Horizontal members carrying the sheets
Corrugated or profiled sheets Galvanised or pre-painted, 28 to 30 gauge, 2.4 m long Solid cladding panels
Self-drilling screws or bolts Galvanised, with washers Fixing sheets to rails
Welding machine and grinder Site welding set and angle grinder Joining and cutting steel members
Concrete 1:2:4 mix Bedding post bases
Steps for erecting steel hoarding
  1. Set out the line: Mark the hoarding line and gate positions with pegs and string.
  2. Excavate post holes: Dig holes about 600 mm deep at the planned post spacing.
  3. Set the posts: Stand the steel posts, plumb and align them, and concrete the bases.
  4. Fix the rails: Weld or bolt the horizontal rails to the posts once the concrete has set.
  5. Fix the sheets: Screw or bolt the sheets to the rails, overlapping by one corrugation.
  6. Install gates: Hang steel gates with heavy-duty hinges, locks and stops.
  7. Protect against corrosion: Paint welds and cut edges with anti-rust primer and finishing paint.
  8. Add signage: Fix project boards, safety signs and lighting where required.
Worked example: corrugated sheets and cost

Number of sheets = perimeter ÷ effective cover width

The same 140 m perimeter is clad with sheets giving 0.8 m effective cover each.

Number of sheets = 140 ÷ 0.8

Number of sheets = 175 sheets

Cost of sheets = number of sheets × price per sheet

Each sheet costs Ksh 1,100.

Cost = 175 × 1,100

Cost = Ksh 192,500

1.1.1.3 Mesh hoarding

Mesh hoarding consists of welded wire mesh or chain link fencing, typically used where visibility into the site is necessary for monitoring or aesthetic reasons. It is common in public infrastructure projects like county government offices where transparency and surveillance are priorities. Mesh hoarding is less secure than solid panels and usually supplemented with security patrols. Temporary mesh panels standing in heavy concrete or plastic feet and clamped together can be erected very quickly without digging. Example: a contractor adding classrooms to an occupied primary school used clamped mesh panels with shade netting to keep pupils away from the works while teachers could still see in.

Name Specification Use
Mesh panels Welded mesh, about 3.5 m × 2.0 m, galvanised frame Temporary freestanding fencing
Chain link fencing Galvanised wire, 2.0 to 2.4 m high, in rolls Long fence runs on posts
Panel feet Concrete or recycled plastic blocks Supporting freestanding panels
Couplers and clamps Galvanised steel Joining adjacent panels
Shade netting UV-stabilised polythene Reducing dust and screening views
Stabiliser struts Steel struts with weights Bracing panels against wind
Steps for erecting mesh hoarding
  1. Set out the line: Mark the fence line, gates and pedestrian walkways.
  2. Place the feet: Lay panel feet at the panel spacing along the line.
  3. Stand the panels: Insert panel legs into the feet and stand them upright.
  4. Clamp the panels: Join adjacent panels with couplers at top and bottom.
  5. Fit stabilisers: Add bracing struts and weights at regular intervals and at corners.
  6. Attach netting and signs: Fix shade netting and warning signs to the mesh.
  7. Install gates: Fit gate panels with locks for site access.
  8. Inspect regularly: Check daily for displaced panels, loose clamps and gaps.
Worked example: number of mesh panels

Number of panels = perimeter ÷ panel width (closed loop)

The 140 m perimeter is enclosed with panels 3.5 m wide.

Number of panels = 140 ÷ 3.5

Number of panels = 40 panels, with 40 feet

Composite hoarding

Composite hoarding combines materials such as timber frames with metal or mesh panels to balance security, cost, and aesthetics. It can be customised with safety signage and project branding, enhancing public perception. For example, a private university expansion project in Kisumu employed composite hoarding to maintain a professional site appearance while ensuring safety.

Temporary hoarding

Temporary hoarding is designed for short-term projects or phases, using lightweight materials like plywood or plastic panels. It is quick to assemble and dismantle, suitable for small-scale residential developments or minor renovations in town centres. Despite being temporary, it must still comply with safety standards to protect workers and the public.

Practice Questions

  1. Explain the advantages and disadvantages of metal hoarding in urban construction sites in Kenya. (10 marks)
  2. Describe how mesh hoarding can be effectively used in public sector projects. (8 marks)
  3. List and explain four types of site hoarding commonly used in Kenyan construction sites. (12 marks)
The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒1.2 Site activities designation

Organising site activities involves logical zoning and scheduling of different construction phases to optimise workflow and resource allocation. For architecture professionals managing construction projects in Kenya, clear demarcation of site activities preven…

🔒1.3 Site utilities installation

Site utilities installation is a critical phase in construction project management, especially in architectural projects where functional and sustainable site infrastructure supports both construction activities and long-term building operation. In the Kenyan…

Chapter Summary

This chapter focused on the organisation of a construction site, beginning with the erection of site hoarding, where timber, steel, and mesh hoardings were examined as common types used to secure and demarcate the site. The designation of site activities was discussed in detail, covering preconstruction tasks such as excavation, backfilling, site clearing, installations, landscaping, site surveys, permit acquisition, procurement, and resource mobilization. Further attention was given to site preparation, including clearing, grading, layout, levelling, and excavation for foundations and utilities. The process of foundation construction was explored, highlighting excavation, formwork, reinforcement placement, and concrete pouring and curing. Structural construction phases were outlined with emphasis on masonry work, roof construction, and steel erection. Finally, the installation of site utilities was addressed, emphasizing critical considerations such as safety, quality of workmanship, regulatory compliance, cost management, and the coordination of activities to ensure efficient and effective utility provision throughout the construction process.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. Which type of site hoarding offers the best long-term durability and security on a construction site? (2 marks)
  2. Describe two key safety considerations when installing site utilities. (3 marks)
🔒26 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Describe three types of site hoarding commonly used in architectural construction projects in Kenya and explain one advantage of each type. (4 marks)
  2. Explain the importance of site clearing in the preconstruction phase of a building project. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Erect timber site hoarding 20m by 1.8m high around designated area

Architecture · Level 6
Construction Project Management
PRACTICAL ASSESSMENT
TIME: 5 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Erect a timber site hoarding 20,000mm long by 1800mm high.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Builder's stringTimber posts 100mm x 100mm x 1800mm
PegsTimber boards 150mm x 25mm x 2000mm
Tape measureNails 75mm
Spirit levelConcrete mix (cement, sand, aggregate)
Hammer
Hand saw
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Timber posts 100mm x 100mm x 1800mm12 Pcs per Candidate
2Timber boards 150mm x 25mm x 2000mm30 Pcs per Candidate
3Nails 75mm1 kg per Candidate
4Concrete mix (cement, sand, aggregate)1 bag per 3 Candidates
5Builder's string1 roll per Candidate
6Pegs8 Pcs per Candidate
7Tape measure 30m1 Pc per Candidate
8Spirit level 600mm1 Pc per Candidate
9Hammer1 Pc per Candidate
10Hand saw1 Pc per Candidate
11PPE: Safety boots, Gloves, Hard hat1 set per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Site preparation and hoarding erection
Wore correct PPE: Safety boots, Gloves, Hard hat
(Award 4 marks for correct and full PPE use, 0 if not)
4
Measured and marked out 20m hoarding length on site using tape measure and pegs
(Award 3 marks each for accurate measurement and marking, 0 if incorrect)
6
Set out and fixed timber posts vertically at 2m centres with concrete foundation
(Award 2 marks for each correctly positioned and concreted post, 0 if missing or poorly fixed)
8
Cut timber boards to length and fixed horizontally to posts using nails
(Award 2 marks for each side fixed with neat nails and correct spacing, 0 if poor fixing)
8
Ensured hoarding is level and plumb using spirit level
(Award 3 marks each for level and plumb accuracy, 0 if off)
6
Cleared site of debris and left hoarding tidy and safe
(Award 3 marks for complete cleanup and safe site, 0 if not)
3
Sub-Total35
PRODUCT CHECKLIST
Hoarding length is 20,000mm ±50mm
(Award 5 marks if length within tolerance, 0 if outside)
5
Hoarding height is 1800mm ±20mm
(Award 5 marks if height within tolerance, 0 if outside)
5
Posts spaced at 2000mm ±50mm centres
(Award 4 marks if spacing consistent and correct, 0 if poor spacing)
4
Hoarding vertical posts are plumb within 3 degrees
(Award 4 marks if plumb accuracy met, 0 if tilted)
4
Timber boards fixed uniformly with no gaps or protruding nails
(Award 4 marks for neat fixing and uniform joints, 0 if poor finish)
4
Concrete footings securely fixed and hardened
(Award 3 marks for solid and complete footings, 0 if weak or missing)
3
Sub-Total25
GRAND TOTAL60
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Designate construction site zones for activities as per permit requirements

Architecture · Level 6
Construction Project Management
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Designate and mark out site zones including storage, site office, parking, and sanitation areas on a 40m by 30m site as per the provided site plan.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Builder's stringCartridge A3 paper
PegsLime powder
Tape measure
HB pencil
Eraser
300mm30000mmSECTION A-A40000mm30000mmPLANDesignate construction site zo…40000 x 30000 x 300 mmNTS
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Builder's string30 m per Candidate
2Pegs20 Pcs per Candidate
3Tape measure1 Pc per Candidate
4HB pencil2 Pcs per Candidate
5Eraser1 Pc per Candidate
6Cartridge A3 paper1 Sheet per Candidate
7Lime powder1 Kg per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Preparation and PPE
Wore the correct PPE: Safety boots, gloves, helmet
(Award 4 marks for correct PPE worn)
4
Collected all required tools and materials
(Award 2 marks for having all tools/materials ready)
2
Sub-Total6
TASK 2: Site plan sketching
Sketched site boundary of 40m by 30m accurately on A3 paper
(Award 5 marks for correct scaled sketch)
5
Marked and labelled site zones: storage, site office, parking, and toilets on the sketch
(Award 7 marks for correct labelling and positioning)
7
Sub-Total12
TASK 3: Site marking on ground
Measured and marked all four site boundaries on ground with lime and pegs
(Award 2 marks for each correctly measured and marked side)
8
Marked out positions of storage, site office, parking, and toilet zones on ground approximately as per sketch
(Award 2.5 marks for each correctly positioned zone)
10
Sub-Total18
TASK 4: Final site zone labelling
Placed pegs with labels at each zone to identify site storage, office, parking, and toilets
(Award 1.5 marks for each correctly labelled zone)
6
Sub-Total6
PRODUCT CHECKLIST
Site plan sketch dimensions are 40,000 mm length and 30,000 mm width accurate within 5% tolerance
(Award 5 marks for correct site plan dimensions)
5
Zones marked on ground correspond with sketch and permit requirements
(Award 10 marks for correct zone layout and compliance)
10
Sub-Total15
GRAND TOTAL57
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Conduct Site Survey and Investigation for a 40m by 25m Construction SitePractical 3
🔒Procure and mobilize materials and equipment for site setupPractical 4
🔒Prepare and clear construction site for excavationPractical 5
🔒Excavate foundation and utilities trenches to specified dimensionsPractical 6
🔒Perform Backfilling and Compaction of Excavated TrenchPractical 7
🔒Construct a strip foundation 1200mm wide, 450mm deep and 3m longPractical 8
🔒Build formwork and place reinforcement for a 3000mm x 450mm x 150mm beamPractical 9
🔒Pour and Cure a Concrete Slab 2500mm x 2000mm x 150mmPractical 10
🔒Construct a 3m long load-bearing masonry wallPractical 11
🔒Construct a timber roof structure for a single-storey buildingPractical 12
🔒Erect a steel portal frame 6000mm span x 3000mm heightPractical 13
🔒Install site utilities including water, electrical conduits and drainage systemPractical 14
🔒Coordinate construction site activities ensuring safety and quality compliancePractical 15
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 19 questions Start quiz ▾
0%
0 / 2
🔒

17 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Organise and set up site hoarding correctly to define construction site boundaries while following all safety procedures.
  • Designate site activities clearly and effectively according to the site layout plan.
  • Install site utilities accurately by following the required work procedures step-by-step.

Tick each one you can genuinely do.

So, are you there yet?

You're competent when you can confidently do 50% or more of what this chapter promised.

Sign in to record how you're doing.