Chapter 9: Apply coordinating principle
📚 13 Topics

Compiled by: Esther Mutahi

9.1 Creating Work schedules

Coordination is the management function that brings the efforts of different people, sections and resources together so that they move towards the same goal at the same time. One of the most practical tools an office administrator uses to coordinate work is the work schedule. A work schedule is a written or digital plan that shows which tasks will be done, who will do them, when each task starts and ends, and what resources each task needs. It turns the plans made at the planning stage into a timetable that every member of staff can follow.

Example: the administration office of a logistics company prepares a weekly schedule showing who answers the reception desk each morning, who processes delivery notes, who updates the fleet register and who prepares the Friday management report. Each person can see their own duties and how their work connects with the work of others.

Meaning of a work schedule

A work schedule answers five questions for every task: what is to be done, by whom, when, for how long and with what resources. It differs from a work plan in its level of detail. A work plan sets out objectives and the activities needed to reach them over a period, while a work schedule fixes those activities to dates, times and named people. In an office, schedules are kept as printed rotas on a notice board, as tables in a spreadsheet, or in shared calendars and task tools that every member of staff can open.

Types of work schedules used in offices

Offices use different schedules depending on the kind of work and the period covered.

  • Daily schedule: lists the tasks for one day, often hour by hour. A personal assistant may keep a daily schedule of the managing director's appointments, calls and meetings.
  • Weekly schedule: spreads routine duties across the days of the week, such as banking on Monday, filing on Wednesday and stock taking of stationery on Friday.
  • Monthly or periodic schedule: covers tasks that recur at longer intervals, such as payroll preparation, statutory returns and monthly board papers.
  • Shift or duty rota: shows which staff cover which hours when an office runs beyond normal working hours, such as a reception that opens from 7.00 am to 7.00 pm.
  • Project schedule: covers one-off assignments with a start and end date, such as moving the office to new premises or organising an annual general meeting.
  • Leave schedule: shows when each member of staff will be on annual leave so that duties remain covered throughout the year.

Information needed before creating a work schedule

Before drawing up a schedule, the administrator gathers the facts the schedule will rest on.

  • Objectives and deadlines: the targets set in the work plan and the dates by which outputs are due, such as the date a tender document must be submitted.
  • Task list: every activity that must be done, broken down into units small enough to assign to one person.
  • Staff availability: working hours, leave dates, training days and any part-time arrangements.
  • Skills of staff: who is able to do each task, for example who can operate the accounting software or take minutes in shorthand.
  • Resources: equipment, rooms, vehicles and budget needed for each task, such as the boardroom, the franking machine or the office van.
  • Dependencies: tasks that cannot start until another is finished, such as dispatching letters only after they have been signed.

The steps for turning this information into a finished schedule, and the tools used to draw it up, follow later in this chapter.

The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒9.2 Importance of work schedules in coordinating management

A work schedule is one of the main instruments through which a manager coordinates people and resources. Without a schedule, each member of staff decides alone what to do and when, so tasks clash, equipment is double-booked and deadlines are missed. With a sch…

🔒9.3 Steps in creating work schedules

Creating a work schedule is a logical process that moves from what must be achieved to who will do what and when. Following the steps in order prevents the common faults of forgotten tasks, impossible deadlines and overloaded staff. The process begins with dec…

🔒9.4 Techniques and tools for creating work schedules

Techniques are the methods used to arrange tasks in time, while tools are the charts, documents and software that display the schedule. The right choice depends on the size of the work: a one-day duty rota needs only a simple table, while a project such as rel…

🔒9.5 Individual roles identification

Coordination works only when every person knows the part they play in the whole. Identifying individual roles means stating clearly what each level of management and each employee contributes to bringing work together, so that no task is left without an owner…

🔒9.6 Monitoring

Monitoring is the continuous watching of work in progress to confirm that it is going according to plan and that the efforts of different people remain in step. In coordination, monitoring tells the manager where one task is running late and threatening anothe…

🔒9.7 Employees' roles

Coordination is not only the work of managers. Every employee is a link in the chain of activities, and a delay or error by one person affects the people whose work follows. Employees coordinate by doing their own work well, by sharing information with colleag…

🔒9.8 Characteristics of effective coordination

Effective coordination has features that distinguish it from simply giving orders. It brings together the efforts of different people and sections so that they act as one, and it runs through every management function: planning, organising, staffing, directing…

🔒9.9 Rewarding Teams

Rewarding teams means recognising and compensating a group of employees for what they achieve together, rather than only rewarding each person for their own output. Where work is coordinated across several people, results depend on cooperation: a report is rea…

🔒9.10 Team dynamics and rewards

Team dynamics are the patterns of interaction, behaviour and relationships among the members of a team. They decide how a team makes decisions, shares work, handles disagreement and supports its members. Two teams with equally skilled members can perform very…

🔒9.11 Elements of team dynamics

The elements of team dynamics are the building blocks that decide whether a team works well together. When these elements are strong, members coordinate their work naturally; when one is weak, the whole team suffers. The three elements below are central to eve…

🔒9.12 Definition of terms

Teams in modern offices take different forms depending on who their members are and how they work together. Understanding the terms used for these teams helps the administrator choose the right team for a task and coordinate it properly. A team, in this sense,…

🔒9.13 The psychology of motivation

Motivation is the inner drive that causes a person to act, to choose a direction and to keep going until a goal is reached. The psychology of motivation studies why people behave as they do at work and what makes them put in effort. For a manager who rewards t…