Land Survey  ·  Level 6
Engineering Survey 1
Chapter 4: Setting out construction works
📚 11 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • choose the right tools, equipment, and materials for setting out construction works based on the survey's purpose
  • perform a complete site safety assessment following occupational safety and health standards
  • correctly identify existing control points by their types
  • accurately carry out the setting out of construction works according to the survey's objective

Mastering these skills ensures your work is precise and safe, which is essential for successful construction projects in the real world.

Setting out construction works is a critical phase in land surveying that involves transferring design plans from the drawing board to the physical site. This process ensures that structures are built in the correct position, orientation, and dimensions according to engineering specifications. In Kenya, where infrastructural development is rapidly expanding across urban and rural areas, precision in setting out directly affects construction quality and cost efficiency. Surveyors use a combination of specialized tools and equipment to achieve the accuracy required for successful project execution.

4.1 Tools, Equipment and Materials

Surveyors rely on a range of instruments and materials to perform setting out tasks effectively. Each tool has specific functions and operational considerations that influence accuracy and efficiency on site. Understanding the specifications, proper use, and maintenance of these resources is essential for survey professionals working in Kenya’s dynamic construction environment.

4.1.1 Total Station

The total station is a versatile electronic/optical instrument used extensively in modern surveying for measuring angles and distances with high precision. It integrates an electronic theodolite for angle measurement, an electronic distance meter (EDM), and a microprocessor for data handling, making it indispensable for setting out complex construction works.

Components and Specifications

Name Specification Use
Electronic Theodolite Measures horizontal and vertical angles with precision up to 1 second Determines precise angular measurements for layout points
Electronic Distance Meter (EDM) Measures distances using infrared or laser waves, accuracy up to ±1mm + 1ppm Calculates exact distances between instrument and prism
Microprocessor and Data Storage Internal computing and memory for recording measurements and coordinates Enables real-time data processing and reduces manual errors
Display and Control Panel User interface for operating the instrument and inputting commands Facilitates easy control and data retrieval on site
Battery Pack Rechargeable battery providing several hours of operation Ensures portability and continuous field use

Usage in Setting Out

  • The total station is set up on a tripod over a known control point using a tribrach for fine levelling.
  • Reflector prisms are positioned on survey points to reflect EDM signals for distance measurement.
  • Horizontal and vertical angles to the prism are recorded to determine the exact position of points to be marked.
  • Data collected is used to calculate coordinates for construction features such as building corners, road alignments, and excavation limits.
  • Integration with software allows for direct transfer of design coordinates, minimizing transcription errors.

Maintenance and Calibration

  • Regular cleaning of optical lenses with lens tissue prevents measurement inaccuracies caused by dirt or smudges.
  • Calibration checks should be performed periodically, especially after transportation or rough handling, to maintain angular and distance accuracy.
  • Battery health monitoring and charging ensure uninterrupted field operations.
  • Storage in protective cases reduces risk of mechanical damage and environmental exposure.

4.1.2 Reflector Prism

Reflector prisms are essential accessories used with total stations to reflect the EDM signal back to the instrument for distance measurement. Their design and positioning significantly influence measurement accuracy.

Types and Specifications

Name Specification Use
Single Prism Diameter around 5 cm, coated glass surface Reflects distance measurement signals accurately
Mini Prism Smaller size for confined spaces, diameter ~2.5 cm Used in tight locations where full prism is impractical
Prism Pole Telescopic pole with prism mount, adjustable height Positions the prism at desired points for measurement
Target Prism Prism with target markings for visibility Enhances precise alignment over longer distances

Positioning and Use

  • The prism must be held vertically and aligned precisely with the total station’s line of sight to avoid angular errors.
  • For construction setting out, the prism is moved to each design point where measurements are taken to confirm location.
  • The use of prism poles with height adjustment allows the prism center to be set at the exact point elevation required.
  • Survey assistants often hold the prism steady during measurements to prevent movement-induced errors.

Care and Handling

  • Avoid scratching or chipping the prism glass surface as it diminishes reflectivity and accuracy.
  • Clean the prism regularly with a soft cloth and appropriate cleaning fluid.
  • Store prisms in cushioned cases to protect against shocks and environmental damage.
  • Inspect mounting fixtures to ensure the prism remains firmly attached to poles.

4.1.3 Level

The level is a surveying instrument used to establish horizontal planes and determine height differences between points. It is fundamental in setting out for foundations, floor levels, and drainage gradients.

Types and Features

Name Specification Use
Dumpy Level Fixed telescope with spirit bubble, magnification ~20x Provides horizontal line of sight for levelling
Automatic Level Self-levelling mechanism with compensator Improves efficiency by reducing setup time
Digital Level Electronic sensor displays digital readings Offers enhanced accuracy and data recording

Application in Construction Setting Out

  • Levels are set up on tripods at stable locations with clear sightlines to levelling staffs.
  • They are used to transfer benchmark elevations to new points on site, ensuring structural elements are built to correct heights.
  • For example, during road construction, levels help in setting out the road profile by establishing cut and fill points.
  • In building works, levels ensure the foundation slab is uniformly horizontal to avoid structural defects.

Maintenance Practices

  • Level tubes should be checked regularly to ensure the bubble is centered and the instrument is properly calibrated.
  • Optical components must be kept clean and free from dust or moisture.
  • Avoid sudden shocks or vibrations which can misalign internal components.
  • Store the level in a padded case when not in use to prevent damage.

4.1.4 Levelling Staff

The levelling staff is a graduated rod used in conjunction with a level to measure vertical distances or height differences on site. It is a simple but vital tool for accurate levelling.

Design and Specifications

Name Specification Use
Telescopic Staff Sections extendable up to 5 meters, graduated in millimeters and centimeters Measures vertical height differences over various distances
Wooden Staff Rigid, fixed length with painted graduations for visibility Used in stable conditions for basic levelling
Aluminium Staff Lightweight and durable with clear markings Suitable for frequent field use

Usage Techniques

  • The staff is held vertically on the point to be levelled, with the base firmly on the ground.
  • The surveyor reads the staff graduations through the level’s telescope to determine the height difference.
  • In uneven terrain, the staff can be extended or retracted to obtain clear readings.
  • Accurate levelling requires the staff to be held steady and plumb, often assisted by a second person.

Care and Preservation

  • Wooden staffs should be kept dry and protected from warping.
  • Aluminium and telescopic staffs need regular cleaning to maintain clear graduations.
  • Avoid dropping or bending the staff which can cause measurement errors.
  • Store in protective tubes or cases to prevent damage during transportation.

4.1.5 Pegs

Pegs are physical markers used to delineate points on the ground during setting out. They serve as reference points for construction crews to follow design outlines.

Types and Materials

Name Specification Use
Wooden Pegs Typically hardwood, 20-30 cm length, pointed ends Mark boundary corners and control points
Plastic Pegs Durable, weather-resistant, various colours for visibility Used where longevity and visibility are important
Metal Pegs Steel or aluminium, often with nails for securing Provide robust markers for long-term projects

Placement and Function

  • Pegs are driven into the ground at precise coordinates obtained from survey measurements.
  • They mark key points such as building corners, road alignments, and excavation limits.
  • Different colours or markings on pegs can indicate various construction phases or types of works.
  • Pegs act as visual guides for machine operators and manual workers during construction.

Handling and Maintenance

  • Pegs should be firmly fixed to withstand environmental conditions and site activities.
  • Inspect pegs regularly to ensure they remain visible and correctly positioned.
  • Replace damaged or displaced pegs promptly to avoid layout errors.
  • Use protective coatings on wooden pegs to prolong their lifespan.

4.1.6 Hammer/Mallet

Hammers and mallets are basic tools used primarily to drive pegs into the ground during setting out. Their choice depends on site conditions and materials used for pegs.

Types and Specifications

Name Specification Use
Claw Hammer Steel head, wooden or fiberglass handle, weight ~0.5-1 kg Drives nails and small pegs, also used for minor demolition
Wooden Mallet Wooden head and handle, lighter weight Drives wooden pegs gently without splitting them
Rubber Mallet Rubber head with wooden or plastic handle Used where non-damaging strikes are needed

Usage in Survey Setting Out

  • The hammer or mallet is used to embed pegs securely into the ground, ensuring stability against movement.
  • Wooden mallets are preferred for wooden pegs to avoid damaging the peg heads.
  • On hard or rocky soils, steel hammers provide the necessary force to drive pegs.
  • Proper striking technique reduces the risk of bending or breaking pegs during installation.

Care and Storage

  • Inspect handles for cracks or splinters and replace damaged tools to prevent accidents.
  • Keep hammer heads free from rust by cleaning and oiling as needed.
  • Store tools in dry environments to extend lifespan and maintain usability.
  • Use toolboxes or racks on site to organize and prevent loss.

4.1.7 GNSS Receiver

Global Navigation Satellite System (GNSS) receivers have revolutionized land surveying by enabling precise positioning using satellite signals. They are increasingly used in setting out construction works for efficient and accurate location determination.

Features and Specifications

Name Specification Use
GNSS Receiver Multi-constellation (GPS, GLONASS, Galileo), sub-centimeter accuracy with RTK correction Determines real-time coordinates for points on site
Data Collector Handheld device integrated with receiver for data input and storage Facilitates field data management and processing
Antenna High-sensitivity antenna for satellite signal reception Ensures reliable satellite connection even in obstructed environments

Application in Construction Setting Out

  • GNSS receivers provide rapid and accurate point positioning without the need for intervisible stations.
  • Real Time Kinematic (RTK) technology allows corrections from base stations to achieve centimetre-level accuracy.
  • Surveyors use GNSS to stake out control points, alignments, and boundaries efficiently over large or inaccessible sites.
  • For example, in road construction projects, GNSS expedites the marking of curves, gradients, and checkpoints with minimal manpower.

Operational Considerations and Maintenance

  • Proper antenna placement and clear sky visibility are crucial for optimal satellite signal reception.
  • Battery management is essential to avoid data loss during field operations.
  • Regular firmware updates and calibration maintain receiver accuracy and functionality.
  • Store receivers and data collectors in protective cases to prevent damage from dust, moisture, or impact.

4.1.8 Measuring Tape

Measuring tapes remain fundamental tools in setting out for quick and direct linear measurements. Their simplicity complements high-tech instruments by providing reliable distance checks and short-range measurements.

Types and Specifications

Name Specification Use
Steel Tape Lengths from 20m to 100m, width ~12-19mm, graduated in millimeters Measures distances accurately on site
Fiberglass Tape Lightweight, flexible, weather-resistant, lengths up to 50m Used in rough terrain and where metal tapes may corrode
Cloth Tape Flexible, less durable, used for short measurements Suitable for indoor or protected environments

Usage in Survey Setting Out

  • Tapes are used to measure offsets from baseline control points to mark construction features.
  • They verify distances between pegs and support layout checks during construction.
  • Measuring tapes assist in setting out temporary works such as scaffolding and formworks.
  • Surveyors use tapes for quick spot checks when electronic instruments are unavailable or impractical.

Maintenance and Handling

  • Steel tapes should be cleaned after use and rewound carefully to prevent kinks or bends.
  • Fiberglass tapes require proper drying if exposed to moisture to avoid mildew.
  • Avoid pulling tapes excessively tight to prevent stretching and measurement errors.
  • Store tapes in protective cases or reels to maintain their condition and accuracy.

Practice Questions

  1. Explain the main components of a total station and their respective functions in setting out construction works. (10 marks)

  2. Discuss the importance of proper positioning and handling of reflector prisms during distance measurements on site. (8 marks)

  3. Describe the role of a level and levelling staff in establishing horizontal planes for construction projects. (10 marks)

  4. Compare the uses of wooden pegs and plastic pegs in setting out construction works, highlighting their advantages and disadvantages. (10 marks)

  5. Outline the steps a surveyor should follow to ensure accurate measurements using a GNSS receiver during setting out. (12 marks)

The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒4.2 Site Safety Assessment

Site safety assessment is a critical preliminary step in setting out construction works in Kenya. Land surveyors often operate in dynamic environments where heavy machinery, uneven terrain, and active construction activities pose significant risks. Conducting…

🔒4.3 Identification of Existing Control Points

Control points are fixed, surveyed positions on the ground used as references to establish locations during surveying. Understanding the different types helps surveyors select appropriate points for their projects. - Horizontal Control Points: These provide pr…

🔒4.4 Meaning of Setting Out

Setting out is a fundamental process in land surveying that involves transferring the design of a construction project from plans and drawings to the physical ground. This practice ensures that the positions of various elements such as buildings, roads, and in…

🔒4.5 Purpose and Importance of Setting Out

Setting out is critical to the success of any construction project because it connects design intentions with physical execution. In Kenya’s fast-growing urban and rural infrastructure sectors, precise setting out ensures that projects meet regulatory standard…

🔒4.6 Methods of setting out

Setting out construction works is a critical phase in land surveying that involves transferring design information onto the ground to guide construction activities. In Kenya, where infrastructure development is rapidly expanding, accurate setting out ensures t…

🔒4.7 Setting out vertical curves

In land surveying for construction projects in Kenya, setting out vertical curves is a critical task that ensures smooth transitions between different gradients on roads, railways, or drainage systems. Vertical curves provide a gradual change in slope, improvi…

🔒4.8 Setting out horizontal curves

Horizontal curves are essential elements in the alignment of roads, railways, and other linear engineering works, ensuring changes in direction are smooth and safe. In Kenya, land surveyors play a vital role in setting out these curves accurately, especially i…

🔒4.9 Setting out buildings & Structures

Setting out buildings and structures is a critical phase in land surveying that translates architectural and engineering designs into precise physical points on the construction site. In Kenya, where construction projects vary from urban high-rise offices in N…

🔒4.10 Setting out trenches

Trenches are essential in construction for foundations, drainage, and utility installations. Accurate setting out of trenches ensures they follow design alignments, depths, and gradients, which is vital for structural stability and service functionality. In Ke…

🔒4.11 Setting out slope stakes

Setting out slope stakes is a critical task in engineering surveys related to construction works, particularly for earthworks such as cuttings and embankments. In the Kenyan context, accurate slope staking ensures that excavations and fills are formed to the c…

Chapter Summary

This chapter covered the essential tools, equipment, and materials used in setting out construction works, including total stations with orals, reflector prisms, levels, levelling staffs, pegs, hammers or mallets, GNSS receivers, and measuring tapes. It emphasized the importance of conducting thorough site safety assessments before commencing any setting out activities to ensure a secure working environment. The identification of existing control points was highlighted as a crucial step for accurate referencing during the layout process. The meaning of setting out was defined as the process of transferring design plans onto the ground to guide construction. The chapter explained the purpose and importance of setting out in ensuring precise and efficient execution of construction projects. Various methods of setting out were explored, such as by coordinates, using theodolites and levels, and by offset techniques. Detailed procedures for setting out vertical and horizontal curves were provided, followed by guidance on setting out buildings and structures, trenches, and slope stakes to ensure alignment and grading conform to design specifications.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. What is the primary function of a total station in setting out construction works? (2 marks)
  2. Describe the role of a reflector prism when using a total station. (2 marks)
🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Describe the primary function of a total station in setting out construction works and explain how it improves accuracy compared to traditional methods. (4 marks)
  2. Explain the role of a reflector prism in surveying and how its proper placement affects measurement precision on a construction site. (4 marks)
🔒18 more in this section.
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 19 questions Start quiz ▾
0%
0 / 2
🔒

17 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • choose the right tools, equipment, and materials for setting out construction works based on the survey's purpose
  • perform a complete site safety assessment following occupational safety and health standards
  • correctly identify existing control points by their types
  • accurately carry out the setting out of construction works according to the survey's objective

Tick each one you can genuinely do.

So, are you there yet?

You're competent when you can confidently do 50% or more of what this chapter promised.

Sign in to record how you're doing.