1.1 Project Scope Define
Defining the project scope means stating clearly and in writing what an interior design project will deliver and what it will not: the spaces involved, the work to be done, the products and services to be provided, the standards to be met, and the limits of time, budget and responsibility. A well-defined scope gives the client, designer, contractors and suppliers a shared understanding of the project, forms the basis for planning, costing and contracts, and protects everyone against misunderstandings and uncontrolled growth of work. Example: for the refurbishment of a SACCO's ground-floor banking hall, the scope statement lists new counters, partitions, ceilings, lighting, flooring and loose furniture for the hall and two offices, excludes the upper floors and external signage, and states that work must be done over weekends so the SACCO can keep serving members.
1.1.1 Elements of a scope statement
A scope statement is the document that records the project scope. It must be specific enough that anyone reading it knows exactly what is included. Example: a designer for a dental practice's new branch writes a scope statement that names every room to be fitted out and the equipment the client will supply separately.
Elements
- Project objectives: The goals the project must achieve, such as creating a welcoming, efficient reception that seats 20 patients.
- Project description: A short description of the spaces, size and nature of the work.
- Deliverables: The tangible outputs, such as concept designs, drawings, specifications, furniture, finishes and the completed fit-out.
- Inclusions: The specific work and items included in the project.
- Exclusions: Work and items clearly not included, to avoid assumptions.
- Constraints: Limits such as budget, completion date, working hours and building rules.
- Assumptions: Conditions taken as true for planning, such as access to the site on agreed dates.
- Acceptance criteria: How completed work will be checked and approved.
- Responsibilities: Who does what, including client-supplied items and other consultants.
1.1.2 Project scope and product scope
Scope has two related parts: the product scope describes what the finished interior will be, while the project scope describes the work needed to produce it. Both must be defined. Example: for a university hostel common room, the product scope is the finished lounge with seating, study tables and a kitchenette, while the project scope includes surveying, designing, procuring, installing and handing over.
| Aspect |
Product scope |
Project scope |
| Meaning |
Features and characteristics of the finished interior |
Work required to deliver the finished interior |
| Examples |
Number of workstations, finishes, lighting levels, furniture |
Surveys, design, approvals, procurement, installation, handover |
| Measured against |
Client requirements and specifications |
Project plan, schedule and budget |
| Main question |
What will be delivered? |
How will it be delivered? |
1.1.3 Sources of information for defining scope
Scope is built from information gathered from the client and other sources. Missing information leads to gaps that cause changes and disputes later. Example: a designer for an insurance company's new floor reviews the client's brief, staff numbers, brand guidelines and building rules before writing the scope.
Sources of scope information
- Client brief: The client's stated needs, goals, preferences and budget.
- Client meetings and interviews: Discussions with the client and key users to clarify needs.
- Existing drawings and surveys: Plans and measurements of the space.
- Building owner or landlord rules: Restrictions on alterations, working hours and finishes.
- Regulations and standards: Fire, accessibility, health and safety requirements.
- Organisation's policies and brand: Corporate standards for furniture, colours and signage.
- Previous similar projects: Lessons and benchmarks from comparable projects.
1.1.4 Work breakdown structure
A work breakdown structure (WBS) divides the total scope into smaller, manageable parts called work packages. It ensures no work is forgotten and provides a framework for scheduling, costing and assigning responsibility. Example: the WBS for a hotel restaurant fit-out breaks the project into design, procurement, site works, furniture and handover, each divided further into specific tasks.
Example of a WBS for an office fit-out
| Level 1 |
Level 2 work packages |
| 1 Design |
1.1 Concept design, 1.2 Design development, 1.3 Working drawings, 1.4 Specifications |
| 2 Approvals |
2.1 Client approval, 2.2 Landlord approval, 2.3 Authority approvals |
| 3 Procurement |
3.1 Tendering, 3.2 Contractor appointment, 3.3 Furniture orders |
| 4 Site works |
4.1 Partitions, 4.2 Ceilings, 4.3 Electrical and lighting, 4.4 Flooring, 4.5 Painting |
| 5 Furniture and fittings |
5.1 Joinery, 5.2 Loose furniture, 5.3 Accessories and signage |
| 6 Handover |
6.1 Snagging, 6.2 Cleaning, 6.3 Documentation, 6.4 Final handover |
Principles for preparing a WBS
- Cover 100% of the scope: Every item of work must appear in the WBS, and nothing outside the scope.
- Use deliverable-based packages: Organise packages around outputs rather than people.
- Break down to manageable size: Divide work until each package can be estimated, scheduled and assigned.
- Avoid overlap: Each piece of work appears in only one package.
- Number packages: Use a numbering system for easy reference.
1.1.5 Procedure for defining project scope
Defining scope follows a logical sequence from gathering requirements to getting the client's formal approval. Example: a designer for a family-owned pharmacy chain follows these steps to agree the scope for refurbishing three branches.
- Receive the client's brief: Record the client's needs, goals, budget and timeframe.
- Clarify requirements: Hold meetings to clarify uncertainties and priorities.
- Review the existing space and constraints: Note the size, condition and limits of the space and building rules.
- List deliverables: Identify all design documents and physical outputs to be provided.
- Define inclusions and exclusions: State clearly what is and is not part of the project.
- Record constraints and assumptions: Write down budget, time and other limits, and assumptions made.
- Prepare the work breakdown structure: Divide the scope into work packages.
- Set acceptance criteria: Agree how work will be checked and approved.
- Write the scope statement: Combine all information into one clear document.
- Obtain client sign-off: Have the client approve the scope statement in writing.
1.1.6 Scope creep and scope control
Scope creep is the gradual, uncontrolled addition of work to a project without matching changes to budget or time. It is one of the most common causes of overruns in interior projects. Scope control prevents this by handling every change through an agreed process. Example: during a restaurant fit-out, the owner keeps asking for "small" extras such as extra shelving and lighting, which together add two weeks and Ksh 400,000 until the designer introduces formal change requests.
Causes of scope creep
- Unclear initial scope: Vague statements leave room for differing expectations.
- Client changes of mind: New ideas or preferences during the project.
- Missed requirements: Needs not identified at the start.
- Informal agreements: Accepting changes verbally on site.
- Gold plating: Adding features the client did not request.
Steps for controlling scope changes
- Receive the change request in writing: Record what is requested and why.
- Assess the impact: Work out the effect on cost, time, quality and other work.
- Present the impact to the client: Explain the consequences clearly.
- Obtain approval or rejection: Get the client's written decision.
- Update project documents: Amend the scope, drawings, schedule and budget.
- Communicate the change: Inform the team, contractors and suppliers.
Worked example: effect of a scope change on cost
New project cost = original cost + cost of added scope
An office fit-out is priced at Ksh 4,800,000. The client adds a 25 m² meeting room at Ksh 38,000 per m².
Cost of added scope = 25 × 38,000 = Ksh 950,000
New project cost = 4,800,000 + 950,000 = Ksh 5,750,000
Percentage increase = (950,000 ÷ 4,800,000) × 100 ≈ 19.8%
The rest of this chapter
🔒Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free account 🔒1.2 Site Analysis
Site analysis is the systematic study of the space where an interior project will take place, carried out before detailed planning and design so that the project is based on real conditions rather than assumptions. It records the size, shape and condition of t…
🔒1.3 Importance of work schedules
A work schedule is a plan that lists the activities of a project in their order, with start and finish dates, durations, the people or trades responsible and the links between activities. In interior design projects, where many trades such as partitioning, ele…
🔒1.4 Types of work schedule
Work schedules come in several types, each suited to different purposes, levels of detail and audiences. Some types differ in their format, such as bar charts, network diagrams and milestone lists; some differ in the period they cover, from the whole project t…
🔒1.5 Contract requirements
Contract requirements are the conditions, documents and terms that must be in place for an interior design project to be legally binding and properly managed. A contract sets out what each party must do, how much will be paid and when, how long the work will t…
🔒1.6 Project timelines
A project timeline is the planned sequence of a project's phases and activities laid out against calendar dates, from the first meeting with the client to handover and beyond. It shows how long each stage will take, which stages overlap or depend on one anothe…
🔒1.7 Project management flowchart
A project management flowchart is a diagram that shows the sequence of stages, activities, decisions and approvals in a project using standard symbols connected by arrows. It gives everyone involved a clear picture of how the project moves from the client's fi…
🔒1.8 Emerging trends on project management
Emerging trends in project management are the new technologies, methods and priorities changing how interior design projects are planned, run and delivered. Artificial intelligence and automation now take over routine tasks, build schedules and predict risks f…
🔒1.9 Prepare work methodology
A work methodology, often called a method statement, is a document that explains how an interior design project will be carried out: the sequence of work, the methods and equipment used, the people responsible, how quality and safety will be achieved, how risk…
🔒1.10 Project Resources
Project resources are everything a project needs to be completed: money, time, people, materials, equipment, information and facilities. In interior design projects the key resources are the budget that pays for the work, the time available to complete it and…
🔒1.11 Monitor Interior Design Project
Monitoring an interior design project means continuously checking actual performance against the plan, covering progress, people, materials, time and money, so that problems are spotted early and corrected before they become serious. The project manager collec…
🔒1.12 Project Quality Control
Project quality control is the process of checking that materials, workmanship and finished work meet the standards set out in the drawings, specifications, contract and applicable regulations. It involves agreeing quality standards in advance, approving sampl…
🔒1.13 Risk factors and Mitigation Strategies
Risk factors are conditions or events that could harm an interior design project by increasing its cost, delaying it, lowering its quality, causing injury or damaging relationships. They arise from many sources, including the client, the design, the site, supp…
🔒1.14 Project Report
A project report is a formal document that records what was planned, what was done, how well it was done and what should be maintained or learned from an interior design project. Reports are prepared at key stages and at the end of the project for the client,…