Chapter 4: Prepare variation accounts
📚 4 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • Identify different types of project variations by accurately reviewing contract accounts documents.
  • Determine the correct value of variations using variation orders, bills of quantities, or current market values.
  • Compile variation accounts following the proper work procedures to ensure accuracy and completeness.

Mastering these skills will help you manage project changes confidently and keep finances on track in the real world of project finance management.

Variation accounts are a critical aspect of project finance management for quantity surveyors, reflecting adjustments to the original contract sum due to changes in project scope, design, or external requirements. Managing these variations effectively ensures that all financial implications are accurately captured and communicated, protecting the client’s investment and the contractor’s interests. In Kenya’s dynamic construction environment, variations often arise from regulatory changes, instructions from design professionals, or evolving client needs, requiring quantity surveyors to maintain meticulous records and justifications. This chapter delves into the principal sources of variations and their implications for preparing variation accounts.

4.1 Sources of Variations

Variations in construction projects emerge from multiple sources, each with distinct triggers and impacts on cost and timelines. Understanding these sources enables quantity surveyors to anticipate, quantify, and negotiate adjustments effectively. In Kenya, regulatory frameworks, professional instructions, and client-driven changes frequently prompt variations, making it essential for quantity surveyors to identify and document their origins clearly.

4.1.1 Statutory Authority Requirements

Statutory authority requirements refer to variations arising from compliance with laws, regulations, and directives issued by government bodies or regulatory agencies during the construction process. These authorities may impose new standards, safety protocols, or environmental controls that were not part of the original contract, necessitating adjustments.

Nature of Statutory Authority Requirements

Statutory variations often include changes mandated by county governments, the National Environment Management Authority (NEMA), or the National Construction Authority (NCA). For instance, during a hospital expansion project in Kisumu County, NEMA might require enhanced waste disposal measures to comply with updated environmental regulations, increasing project costs.

  • Regulatory Amendments: Changes in building codes or environmental laws that affect material specifications or construction methods, requiring immediate project adaptation.
  • Permit Conditions: New or revised conditions attached to construction permits that mandate additional works or modifications.
  • Safety and Health Directives: Introduction of new occupational health and safety standards by the Directorate of Occupational Safety and Health Services (DOSHS) that necessitate additional safety installations.
  • Environmental Compliance: Requirements to implement erosion control, water runoff management, or noise mitigation measures due to environmental impact assessments.
  • Utility Authority Instructions: Changes requested by utility providers such as the Kenya Power and Lighting Company (KPLC) for infrastructure relocation or protection during construction.

Impact on Variation Accounts

Statutory variations usually have a direct financial implication because they often require unplanned work or materials.

  • Cost Increases: Additional works mandated by authorities typically involve extra labor, materials, and time, all of which increase the contract sum.
  • Time Extensions: Compliance with new statutory requirements can delay project progress, necessitating adjustments to the project schedule.
  • Documentation Requirements: Quantity surveyors must provide detailed records and justifications for statutory variations to support claims.
  • Dispute Potential: Failure to comply or adequately document statutory variations may lead to disputes between clients and contractors.
  • Risk Management: Early identification of potential statutory changes can mitigate risks and avoid financial surprises.

Identification and Documentation Procedures

Effective management of statutory variations requires prompt recognition and thorough documentation.

  • Monitoring Regulatory Updates: Quantity surveyors must stay informed about changes in laws and regulations relevant to the project location.
  • Official Notices: Statutory authorities often issue formal directives or notices that must be incorporated into project records.
  • Variation Instruction Forms: Use of formal variation instructions to capture statutory changes ensures transparency and traceability.
  • Cost Estimation: Quantification of additional works resulting from statutory requirements, using current rates and market prices.
  • Client Communication: Early communication with the client regarding statutory variations facilitates approval and funding adjustments.

Challenges in Managing Statutory Variations

Managing statutory variations can be complex due to unpredictable timing and scope.

  • Unforeseen Regulatory Changes: Sudden amendments may disrupt project planning and budgeting.
  • Compliance Costs: High costs for meeting new statutory requirements can strain project finances.
  • Coordination Difficulties: Aligning statutory directives with ongoing works requires careful coordination among stakeholders.
  • Documentation Gaps: Incomplete records can weaken variation claims.
  • Legal Interpretations: Ambiguities in regulations may lead to differing interpretations and disputes.

4.1.2 Engineer/Architect Instructions

Engineer or architect instructions are a common source of variations, reflecting changes or clarifications issued by the project’s design professionals during construction. These instructions can arise from design improvements, error corrections, or unforeseen site conditions.

Types of Engineer/Architect Instructions

Instructions from engineers or architects typically fall into several categories, each impacting project scope and cost differently.

  • Design Modifications: Changes to drawings or specifications to enhance functionality or aesthetics, such as altering room layouts in a university building.
  • Site Condition Adjustments: Instructions responding to unexpected soil conditions or obstructions discovered during excavation.
  • Quality Improvements: Upgrading materials or finishes following professional recommendations to meet higher standards.
  • Error Corrections: Rectifications of design errors or omissions identified after construction has commenced.
  • Additional Work Orders: Requests for extra works not originally specified, such as additional drainage works in a hotel project.

Authority and Communication of Instructions

The authority to issue instructions and the manner of communication are critical to managing variations effectively.

  • Contractual Authority: Engineers or architects usually have delegated authority within the contract to issue variation instructions.
  • Formal Documentation: Instructions must be issued in writing, often using official variation order forms, to be valid.
  • Timely Communication: Prompt issuance of instructions helps minimize delays and cost escalations.
  • Clarification Process: Quantity surveyors often liaise with design professionals to clarify scope and quantify costs.
  • Record Keeping: Maintaining a log of all instructions ensures accountability and supports variation claims.

Financial Implications of Instructions

Engineer or architect instructions directly affect the project budget and require careful financial assessment.

  • Measurement and Valuation: Quantity surveyors measure additional or omitted works and apply contract rates or negotiate new rates.
  • Adjustment of Contract Sum: Variation accounts must reflect the net financial effect of all instructions.
  • Contingency Use: Some projects allocate contingency funds to cover minor instruction-related variations.
  • Claim Negotiations: Disputes may arise over valuation or scope, requiring negotiation or adjudication.
  • Impact on Cash Flow: Timely valuation and payment of instructed variations preserve contractor cash flow.

Practical Considerations for Quantity Surveyors

  • Site Visits: Regular site inspections enable early detection of instruction-related changes.
  • Coordination with Project Team: Close collaboration with engineers, architects, and contractors ensures accurate scope definition.
  • Documentation Accuracy: Precise measurement and description of variations reduce disputes.
  • Client Reporting: Transparent reporting to the client about the nature and cost of instructions supports decision-making.
  • Risk Assessment: Evaluating the impact of instructions on project timelines and budgets guides effective management.

4.1.3 Client Requirements

Client requirements are a dynamic source of variations as clients may request changes to project scope, quality, or design based on evolving needs or preferences. These variations often reflect strategic or operational priorities and can significantly influence project outcomes.

Nature of Client-Initiated Variations

Clients may initiate variations for various reasons, reflecting changes in business strategy or operational demands.

  • Scope Expansion: Adding new facilities or features, such as increasing the number of classrooms in a school project.
  • Design Changes: Altering aesthetic elements or layouts based on client preferences or feedback.
  • Material Upgrades: Requesting higher quality or alternative materials to enhance durability or appearance.
  • Phased Implementation: Adjusting project delivery schedules or sequencing to align with client operational plans.
  • Budget Revisions: Modifying project scope to fit revised budget allocations or funding availability.

Client Decision-Making and Variation Approval

The client’s role in approving and authorizing variations is central to effective project financial management.

  • Formal Variation Requests: Clients typically submit formal variation requests or change orders to initiate changes.
  • Approval Processes: Variations require client approval, often involving multiple stakeholders or committees.
  • Budget Impact Analysis: Clients assess the financial implications before sanctioning variations.
  • Communication Channels: Clear communication between clients and quantity surveyors ensures mutual understanding.
  • Documentation Compliance: Proper documentation supports audit trails and contractual compliance.

Financial and Contractual Effects of Client Variations

Client-driven variations affect contract sums and project delivery, requiring careful financial control.

  • Variation Costing: Quantity surveyors must accurately quantify and value client-requested changes.
  • Contract Amendments: Variations often require formal contract amendments or supplementary agreements.
  • Payment Terms: Adjusted payment schedules may be negotiated to accommodate variation costs.
  • Risk Allocation: Contracts specify whether variations entail cost or time risk borne by the client or contractor.
  • Dispute Resolution: Clear contractual provisions help resolve disagreements over client variations.

Managing Client Expectations and Communication

Effective communication and expectation management are vital when handling client variations.

  • Client Briefing: Educating clients on the financial and time implications of variations facilitates informed decisions.
  • Regular Updates: Providing periodic cost and progress reports maintains transparency.
  • Negotiation Skills: Quantity surveyors often mediate between clients and contractors to reach agreeable terms.
  • Change Control Systems: Implementing formal change control procedures prevents unauthorized variations.
  • Post-Variation Review: Assessing the impact of variations on project success informs future client engagements.

Practice Questions

  1. Explain five types of statutory authority requirements that can lead to variations in a construction project and discuss their implications on project cost and schedule. (10 marks)

  2. Describe the process by which engineer or architect instructions are issued and managed in Kenyan construction projects, highlighting the role of the quantity surveyor. (10 marks)

  3. Discuss how client requirements can lead to variations during a project and explain the contractual and financial considerations that must be addressed. (10 marks)

The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒4.2 Determination of causes of variations

In Quantity Surveying, accurately identifying the causes of variations is fundamental to managing project costs and ensuring fair settlements. Variations arise from changes during construction that deviate from the original contract scope, often impacting the…

🔒4.3 Determination of value of variations

Determining the value of variations is a critical task for quantity surveyors tasked with preparing variation accounts. This process involves quantifying the cost implications of changes to the original contract works, ensuring that clients and contractors are…

🔒4.4 Conditions governing variations

In quantity surveying, variations represent changes to the original contract scope, which affect costs and timelines. Understanding the conditions that govern variations is crucial for quantity surveyors managing construction projects in Kenya, as improper han…

🔒5 Prepare financial claims

Financial claims are critical documents prepared by quantity surveyors to recover payments for works executed, including variations and other adjustments. Accurate claim preparation ensures that contractors receive timely and fair compensation, while clients m…

Chapter Summary

This chapter explored the process of preparing variation accounts within project finance management. It began by identifying the primary sources of variations, including statutory authority requirements, instructions from engineers or architects, and evolving client needs. Understanding these sources is essential for accurately managing changes during a project lifecycle. The chapter then discussed how to determine the causes of variations, which involves thorough investigation and documentation to establish the origin and justification for each change. Following this, methods for determining the value of variations were examined, focusing on quantifying the financial impact of changes to ensure fair compensation or cost adjustments. The chapter also outlined the conditions governing variations, emphasizing contractual terms and procedural requirements that must be met before variations are accepted and processed. Finally, it addressed the preparation of financial claims related to variations, guiding how to compile and present claims for approval and payment. Together, these topics provide a comprehensive framework for effectively managing variations in project finance.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. Identify three common sources of variations in construction projects and explain how each can impact the project cost. (6 marks)
  2. Which statutory authority requirement could lead to a variation in a project, and why must a quantity surveyor consider it carefully? (2 marks)
🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Identify three common sources of variations in construction projects and explain how statutory authority requirements can lead to variations in Quantity Surveying. (4 marks)
  2. Explain the role of engineer or architect instructions in initiating variations during a project and provide an example relevant to road construction in Kenya. (4 marks)
🔒18 more in this section.
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 17 questions Start quiz ▾
0%
0 / 2
🔒

15 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Identify different types of project variations by accurately reviewing contract accounts documents.
  • Determine the correct value of variations using variation orders, bills of quantities, or current market values.
  • Compile variation accounts following the proper work procedures to ensure accuracy and completeness.