Quantity Survey  ·  Level 6
Project Contracts Management
Chapter 2: Prepare day works accounts
📚 2 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • accurately determine plant costs based on day works
  • correctly calculate material costs from day works records
  • precisely figure out labour costs related to day works
  • confidently calculate profits, overheads, and taxes as percentages of total day work costs

These skills will help you manage project costs effectively and ensure fair and accurate payments in real-world contracts.

Preparing accurate day works accounts is a critical task for Quantity Surveyors managing construction projects in Kenya. Day works arise when work is ordered by the client or their agent on a time and materials basis rather than a fixed price, often due to unforeseen circumstances or variations. Proper determination of plant, materials, and labour costs ensures fair compensation while controlling project expenditure. This chapter focuses on how to systematically evaluate these costs to produce reliable day works accounts that support transparent contract management.

2.1 Determination of Plant, Materials and Labour Costs

Determining costs for plant, materials, and labour is fundamental in preparing day works accounts, as these elements constitute the core inputs to the work performed. Quantity Surveyors in Kenya must adopt precise methods to assess the actual consumption and usage rates, ensuring that costs reflect the true value of resources deployed on site. This process involves understanding contract provisions, market rates, and site conditions to avoid disputes and maintain financial control.

2.1.1 Establishing Plant Costs for Day Works

Plant costs refer to the expenses related to the use of machinery and equipment required to execute construction activities under day works. In Kenya, plant hire rates can vary significantly based on availability, type, and operational efficiency, making accurate cost determination vital to reflect actual usage.

Components Influencing Plant Costs

  • Hire Charges: This is the basic cost paid to rent the equipment, usually expressed as a daily or hourly rate. For example, a contractor working on a county government road project must verify prevailing hire rates for excavators to avoid overcharging.
  • Operating Costs: Includes fuel, lubricants, and operator wages directly linked to the plant’s operation during day works. These costs fluctuate with machine efficiency and site conditions.
  • Maintenance and Repairs: Costs incurred to keep the plant in working order during usage periods, which must be apportioned fairly for day works.
  • Depreciation: Represents the wear and tear or reduction in value of owned plant over time, calculated proportionally for the period used in day works.
  • Idle Time Charges: Sometimes plant may be on site but not in use due to delays; contracts often specify whether idle time is chargeable, requiring careful documentation.

Methods to Calculate Plant Costs

Plant costs are commonly calculated using either the Actual Cost Method, where all expenses are tracked and allocated, or the Schedule of Rates Method, which uses pre-agreed daily or hourly rates. The Quantity Surveyor must ensure that whichever method is applied aligns with contract terms and that records such as logbooks, fuel receipts, and maintenance invoices are maintained.

2.1.2 Assessing Materials Costs in Day Works

Materials used in day works must be valued accurately to reflect the true cost to the project without inflating expenses. Kenyan construction sites often face challenges such as price volatility and supply delays, making careful cost assessment crucial.

Factors Affecting Material Cost Determination

  • Purchase Price Verification: The Quantity Surveyor must confirm actual purchase prices from supplier invoices rather than relying on estimated or catalogue prices.
  • Waste and Loss Allowance: Materials inevitably incur wastage during handling and use; contracts typically specify a percentage allowance that must be applied to avoid overpayment.
  • Transportation and Handling: Costs to deliver materials to site and move them to the point of use are part of the materials cost and must be included in day works accounts.
  • Storage Costs: If materials are stored on site before use, costs such as security and protection from weather should be considered.
  • Quality and Specification Compliance: Materials must meet contract specifications; substandard materials may reduce cost claims or require replacement, impacting the day works valuation.

The Quantity Surveyor should maintain a detailed bill of materials issued for day works with supporting delivery notes and supplier invoices to substantiate costs.

2.1.3 Calculating Labour Costs for Day Works

Labour costs typically constitute a significant portion of day works accounts and require thorough documentation and validation. In Kenya, labour rates can vary by region, skill levels, and union agreements, impacting the final cost determination.

Elements of Labour Cost Calculation

  • Basic Wages: The agreed daily or hourly wage rates for different categories of workers, from skilled artisans to general labourers, must be accurately recorded.
  • Overtime and Shift Allowances: Additional payments for overtime work or night shifts must be included if applicable and supported by time sheets.
  • Social Security and Statutory Contributions: Employers’ contributions to NSSF, NHIF, and other statutory deductions form part of the labour cost and must be accounted for.
  • Subsistence and Transport Allowances: Some contracts allow reimbursement for worker meals and transport, which should be included if expressly provided.
  • Supervision and Management Labour: Costs for supervisory staff directly involved in day works, such as site foremen, must be apportioned appropriately.

Labour costs are generally supported by attendance registers, pay slips, and payroll records. The Quantity Surveyor must ensure that these documents are consistent and reflect actual hours worked on day works activities.

2.1.4 Integrating Plant, Materials, and Labour Costs into Day Works Accounts

Accurate day works accounts require integrating costs of plant, materials, and labour into a coherent and verifiable document that aligns with contract requirements. This integration is essential for transparent contract administration and dispute avoidance.

Steps in Preparing Integrated Day Works Accounts

  1. Collect Supporting Documentation: Gather invoices, hire agreements, payroll records, delivery notes, and site diaries related to day works.
  2. Verify Quantities and Usage: Cross-check quantities of materials issued, plant hours logged, and labour hours recorded against site records and supervision reports.
  3. Apply Contract Rates and Allowances: Use contract-specific rates, allowances for waste, idle time, and statutory contributions as stipulated.
  4. Calculate Individual Cost Components: Compute plant, materials, and labour costs separately using verified data and agreed formulas.
  5. Summarise Total Day Works Cost: Aggregate the individual components into a final day works account, ensuring all calculations are transparent and traceable.
  6. Present for Approval and Payment: Submit the day works account to the client or contract administrator for review and approval, accompanied by supporting evidence.

Example: At a county hospital expansion project, the Quantity Surveyor compiled day works accounts for unforeseen drainage repairs by meticulously recording plant usage from excavator logbooks, material deliveries from supplier invoices, and labour attendance from site registers, ensuring the client paid only for verified work.

Practice Questions

  1. Explain the key components that influence plant costs in day works and how each affects the final cost. (10 marks)
  2. Describe the procedures a Quantity Surveyor should follow to verify materials costs for day works in a construction project. (12 marks)
  3. Discuss the elements that constitute labour costs in day works and the importance of accurate documentation. (10 marks)
  4. Outline the step-by-step process of integrating plant, materials, and labour costs into a day works account for submission. (12 marks)
The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒2.2 Determination of profits and overheads

The accurate determination of profits and overheads is a critical aspect in preparing day works accounts within quantity surveying practice in Kenya. Profits and overheads represent the contractor’s entitlement beyond direct costs, covering business expenses a…

Chapter Summary

This chapter focused on the preparation of day works accounts within project contracts management. It began by examining the determination of plant, materials and labour costs, highlighting how accurate cost assessment ensures fair compensation for resources used on site. The chapter then explored the calculation of profits and overheads, emphasizing the importance of including these elements to maintain the financial viability of the contractor. Understanding how to quantify both direct costs and indirect expenses allows for transparent and justifiable day works claims. The content underscored the need for precise record-keeping and cost allocation in managing day works effectively. By mastering these processes, project managers and contractors can safeguard project budgets while ensuring timely payment for additional work executed.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. Which of the following is NOT typically included in the calculation of plant costs for day works accounts? (2 marks)
    a) Depreciation
    b) Fuel and lubricants
    c) Labour wages
    d) Maintenance and repairs

  2. Explain how the hire rate for plant equipment is determined in the context of day works accounts. (3 marks)

🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Explain the key components involved in determining plant costs when preparing day works accounts for a construction project at a county government office. (4 marks)
  2. Describe how materials costs should be recorded and verified in day works accounts for a hotel refurbishment project in Mombasa. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Calculate Daily Operating Cost of a 10-Ton Excavator for Day Works

Quantity Survey · Level 6
Project Contracts Management
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Calculate the daily operating cost of a 10-ton excavator including depreciation and running costs based on the provided data sheet.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
CalculatorPlant Cost Data Sheet
Pen and PaperReference Tables for Depreciation and Running Costs
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Calculator1 Pc per Candidate
2Pen and Paper1 Set per Candidate
3Plant Cost Data Sheet1 Pc per Candidate
4Reference Tables for Depreciation and Running Costs1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: CALCULATION OF DAILY OPERATING COST
Identified and used appropriate PPE as per safety regulations
(Award 1 mark each for helmet, safety boots, and reflective vest)
3
Assembled all required tools and reference materials
(Award 0.5 marks for each correctly assembled item, max 2 marks)
2
Correctly identified depreciation rate from the data sheet
(Award 5 marks for correct depreciation rate calculation)
5
Accurately computed running costs including fuel, maintenance, and operator costs
(Award 2 marks each for fuel, maintenance, and operator costs calculations)
6
Summed depreciation and running costs to obtain total daily operating cost
(Award 4 marks for accurate total cost calculation)
4
Presented calculations clearly and logically
(Award 3 marks for neat and logical presentation)
3
Verified all figures for accuracy and consistency
(Award 2 marks for thorough verification)
2
Cleaned and stored tools and materials properly after use
(Award 2 marks for correct cleaning and storage)
2
Sub-Total27
PRODUCT CHECKLIST
Daily operating cost calculated correctly within ±5% tolerance
(Award 8 marks for correct final cost calculation within tolerance)
8
All components of cost (depreciation, fuel, maintenance, operator) correctly identified and included
(Award 1 mark each for depreciation, fuel, maintenance, operator, and total cost inclusion)
5
Calculation presented in clear, logical format with units and labels
(Award 5 marks for clarity and completeness of presentation)
5
Sub-Total18
GRAND TOTAL45
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Measurement and Quantification of Materials Used in Day Works for a 3m x 2m Wall Section

Quantity Survey · Level 6
Project Contracts Management
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Measure and quantify materials used in the construction of a 3m long by 2m high masonry wall section for day works account preparation.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring Tape (5m)Safety Helmet
Spirit LevelSafety Boots
Builder's SquareReflective Safety Jacket
Plumb Bob
Notebook and Pen
Calculator
Chalk/Lime for marking
Shovel
Wheelbarrow
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Measuring Tape (5m)1 Pc per Candidate
2Spirit Level1 Pc per Candidate
3Builder's Square1 Pc per 3 Candidates
4Plumb Bob1 Pc per Candidate
5Notebook and Pen1 Set per Candidate
6Calculator1 Pc per Candidate
7Chalk/Lime for markingSufficient per Candidate
8Shovel1 Pc per 4 Candidates
9Wheelbarrow1 Pc per 4 Candidates
10Safety Helmet1 Pc per Candidate
11Safety Boots1 Pair per Candidate
12Reflective Safety Jacket1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: PREPARATION AND PPE
Candidate dons all required PPE (Helmet, Safety boots, Reflective jacket)
(Award 1 mark each for correctly worn PPE)
3
Assembles all required tools and materials before starting measurement
(Award 0.5 mark per correctly assembled tool/material, total 6 items minimum)
3
Prepares and clears the work area for measurement
(Award 2 marks for clear and safe work area)
2
Uses chalk/lime to mark measurement points on the masonry wall
(Award 2 marks for accurate and visible markings)
2
Sets out measurement points accurately using measuring tape, spirit level, builder's square, and plumb bob
(Award 1 mark for each tool used correctly and measurement set out accurately)
5
Sub-Total15
TASK 2: MEASUREMENT AND QUANTIFICATION
Measures length, height, and thickness of the masonry wall section accurately within ±10mm tolerance
(Award 4 marks for measurements within tolerance)
4
Quantifies quantity of bricks used by counting or estimating actual brick units
(Award 4 marks for accurate quantification of bricks)
4
Quantifies quantity of mortar used by measuring volume of sand and cement consumed
(Award 4 marks for accurate mortar volume calculation)
4
Records all measurements and quantities clearly and legibly in the notebook
(Award 3 marks for clear and complete records)
3
Calculates total material costs using given unit rates
(Award 4 marks for correct calculations of material costs)
4
Sub-Total19
PRODUCT CHECKLIST
Measurements of masonry wall section match specified dimensions (3000mm length x 2000mm height x 115mm thickness) within ±10mm tolerance
(Award 5 marks for all dimensions within tolerance)
5
Quantified material quantities (bricks, sand, cement) correspond logically to the measured wall volume and workmanship
(Award 5 marks for accurate and consistent material quantities)
5
Material cost calculations are accurate and correspond to quantities measured
(Award 5 marks for correct cost computations)
5
Sub-Total15
GRAND TOTAL49
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Calculate Labour Costs for Day Works Based on Attendance and Wage RatesPractical 3
🔒Preparation of a Detailed Day Works Cost Sheet for Construction Plant, Materials, and LabourPractical 4
🔒Determine overhead costs applicable to day worksPractical 5
🔒Calculate profit margins on day works accountsPractical 6
🔒Preparation of a Final Day Works Account Including Profits and OverheadsPractical 7
🔒Reconcile Day Works Accounts with Site Records for Construction ProjectPractical 8
🔒Assess the impact of plant utilization on day works costs for a temporary site office foundationPractical 9
🔒Preparation of Day Works Account for Site ScenarioPractical 10
Flashcards 19 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

17 more in this section.

Create a free account
Test Yourself 20 questions Start quiz ▾
0%
0 / 2
🔒

18 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • accurately determine plant costs based on day works
  • correctly calculate material costs from day works records
  • precisely figure out labour costs related to day works
  • confidently calculate profits, overheads, and taxes as percentages of total day work costs