By the end of this chapter, you will be able to:
Mastering these skills ensures you can build safe, reliable railway tracks that keep trains running smoothly and on time.
Civil engineering works related to railway construction form a critical part of infrastructure development in Kenya, directly impacting economic growth and regional connectivity. For quantity surveyors, understanding the technical aspects and classifications of railway tracks is essential for accurate cost estimation, tendering, and project management. This chapter focuses on the types of railway tracks encountered in the Kenyan context, providing a foundation for detailed quantity takeoff and cost analysis. Knowledge of these types supports effective planning and resource allocation in railway projects such as the Standard Gauge Railway and county-level light rail initiatives.
The classification of railway tracks is fundamental in quantity surveying as it influences material specifications, construction methods, and overall project budgeting. Different track types serve varying operational needs and terrain conditions, which affect quantities and costs. In Kenya, railway projects must consider these types in line with local geography, usage demands, and maintenance regimes. Understanding the distinct characteristics of each track type enables quantity surveyors to prepare accurate bills of quantities and anticipate cost implications.
The permanent way refers to the track structure that forms the running surface for trains, including rails, sleepers, ballast, and subgrade. It is designed to endure the dynamic loads imposed by moving trains and environmental stresses over long periods. For quantity surveyors, the permanent way represents the core component of civil works in railway construction, with significant implications on cost through materials and labor requirements.
Quantity surveyors must quantify and price each component accurately, considering local availability and transport costs which vary across Kenyan regions.
Light rail systems and tramways are increasingly used in urban Kenyan settings to alleviate traffic congestion and provide efficient public transport. These tracks differ from heavy rail in construction standards, load capacity, and track geometry.
Quantity surveyors working on urban transport projects must adapt cost estimates to these specialized requirements, including the integration with existing road infrastructure.
Narrow gauge railways have a track gauge typically less than the standard 1,435 mm, historically prevalent in Kenya’s regional and rural rail networks. These tracks are cost-effective for lower traffic volumes and difficult terrains but have limitations in speed and load capacity.
Quantity surveyors must consider these factors when preparing cost analyses for rehabilitation or extension projects involving narrow gauge lines.
The standard gauge track, measuring 1,435 mm between rails, is the preferred choice for modern Kenyan railway projects, including the Standard Gauge Railway (SGR). This track type supports higher speeds, heavier loads, and enhanced safety features.
For quantity surveyors, the standard gauge entails detailed measurement and specification of premium materials and sophisticated construction techniques, reflected in higher but more sustainable project costs.
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter explored the different types of railway tracks, highlighting their unique designs and applications in various railway systems. It detailed the distinctions between permanent way tracks, temporary tracks, and narrow gauge tracks, explaining their suitability for specific operational needs. The construction of railway tracks was examined comprehensively, covering essential steps such as site preparation, laying sleepers, fixing rails, and ensuring proper alignment and stability. Emphasis was placed on the importance of drainage and ballast in maintaining track integrity and safety. The chapter also discussed the role of precise measurement and quality control during construction to ensure long-term durability. Overall, the chapter provided a thorough understanding of both the classification and practical construction processes that underpin effective railway track development.
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape | Railway Track Samples (Standard Gauge and Metre Gauge) |
| Magnifying Glass | |
| Notebook and Pen | |
| Chalk or Marker |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Safety Helmet | 1 Pc per Candidate |
| 2 | Safety Boots | 1 Pair per Candidate |
| 3 | Reflective Safety Jacket | 1 Pc per Candidate |
| 4 | Railway Track Samples (Standard Gauge and Metre Gauge) | 2 Sets per Candidate |
| 5 | Measuring Tape (5m) | 1 Pc per Candidate |
| 6 | Notebook and Pen | 1 Set per Candidate |
| 7 | Magnifying Glass | 1 Pc per Candidate |
| 8 | Chalk or Marker | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: IDENTIFICATION AND CLASSIFICATION OF RAILWAY TRACKS | |||
| Used appropriate PPEs: Safety helmet, Safety boots, Reflective jacket (Award 1 mark for each correctly worn PPE) | 3 | ||
| Collected and assembled all required tools and materials before inspection (Award 2 marks for assembling all listed tools and materials) | 2 | ||
| Inspected railway track samples carefully using magnifying glass and measuring tape (Award 1 mark for each correctly identified feature: rail gauge, sleeper type, fastening method) | 3 | ||
| Measured and recorded the gauge width of each railway track sample accurately (Award 1 mark for each correct measurement recorded for two samples) | 3 | ||
| Classified each railway track sample correctly as standard gauge or metre gauge (Award 1.5 marks for each correct classification) | 3 | ||
| Identified types of sleepers used (wooden, concrete, steel) on the samples (Award 1 mark for each correct sleeper type identified) | 2 | ||
| Noted fastening types (spikes, clips, bolts) used on the railway tracks (Award 1 mark for each correct fastening type identified) | 2 | ||
| Recorded all observations neatly and clearly in the notebook (Award 2 marks for complete and legible records) | 2 | ||
| Cleaned and returned all tools and samples to the designated storage area (Award 2 marks for proper cleaning and storage) | 2 | ||
| Maintained safety and cleanliness throughout the inspection process (Award 1 mark for adherence to safety and cleanliness) | 1 | ||
| Sub-Total | 23 | ||
| PRODUCT CHECKLIST | |||
| Accurately identified and classified all railway track types with correct gauge measurements (Standard gauge 1435mm ± 5mm, Metre gauge 1000mm ± 5mm) (Award 5 marks for correct gauge measurement for each track type) | 10 | ||
| Correctly identified sleeper types and fastening methods as per samples (Award 2.5 marks each for correct sleeper and fastening identification) | 5 | ||
| Neat and complete record of inspection observations matching the actual samples (Award 4 marks for full and clear documentation) | 4 | ||
| Demonstrated understanding of classification criteria during oral questioning (Award up to 3 marks based on accuracy and completeness of answers) | 3 | ||
| Sub-Total | 22 | ||
| GRAND TOTAL | 45 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape (30m) | Lime Powder |
| Theodolite or Total Station | Safety Helmet |
| Tripod Stand | Safety Boots |
| Plumb Bob | Reflective Safety Jacket |
| Profile Boards | |
| Builder’s Line (50 m) | |
| Hammer (3kg) | |
| Wooden Pegs (30 x 30 x 600 mm) | |
| Marker Pens |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape (30m) | 1 Pc per Candidate |
| 2 | Theodolite or Total Station | 1 Pc per 5 Candidates |
| 3 | Tripod Stand | 1 Pc per Candidate |
| 4 | Plumb Bob | 1 Pc per Candidate |
| 5 | Profile Boards | 4 Pcs per Candidate |
| 6 | Builder’s Line (50 m) | 1 Roll per Candidate |
| 7 | Lime Powder | 0.5 Kg per Candidate |
| 8 | Hammer (3kg) | 1 Pc per 4 Candidates |
| 9 | Wooden Pegs (30 x 30 x 600 mm) | 20 Pcs per Candidate |
| 10 | Safety Helmet | 1 Pc per Candidate |
| 11 | Safety Boots | 1 Pair per Candidate |
| 12 | Reflective Safety Jacket | 1 Pc per Candidate |
| 13 | Marker Pens | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: SETTING OUT RAILWAY TRACK ALIGNMENT | |||
| Identified and used appropriate PPEs including helmet, safety boots, and reflective jacket (Award 1 mark each for helmet, boots, jacket) | 3 | ||
| Assembled and positioned theodolite or total station on tripod correctly (Award 1 mark each for correct setup, plumbness, and stable positioning) | 3 | ||
| Prepared and cleared site area sufficiently for setting out (Award 2 marks for proper clearing and preparation) | 2 | ||
| Measured and marked the baseline of 100m accurately using measuring tape and pegs (Award 1 mark each for correct measurement, pegging, and marking) | 3 | ||
| Set out 1435mm gauge using builder’s line and profile boards at correct intervals (Award 1 mark each for correct gauge width, line tension, profile board placement, and pegging) | 4 | ||
| Transferred alignment points accurately from theodolite to ground with correct use of plumb bob (Award 1 mark each for correct observation, plumb bob use, pegging, and marking) | 4 | ||
| Marked the track alignment on ground clearly with lime powder and marker pens (Award 1 mark each for clarity, accuracy, and completeness of markings) | 3 | ||
| Cleaned the working area after completion (Award 2 marks for thorough cleaning) | 2 | ||
| Cleaned and stored tools and equipment properly after use (Award 2 marks for proper cleaning and storage) | 2 | ||
| Sub-Total | 26 | ||
| PRODUCT CHECKLIST | |||
| Linear measurements within ±50 mm tolerance over 100m baseline (Award 5 marks for full compliance, lesser marks for partial) | 5 | ||
| Railway track alignment parallel to the datum line as per layout plan (Award 4 marks for correct parallelism) | 4 | ||
| Gauge width accurately set at 1435 mm ±10 mm (Award 5 marks for correct gauge width) | 5 | ||
| Layout is squared with correct diagonals and profile boards placed correctly (Award 2 marks for squareness, 3 marks for profile board placement) | 5 | ||
| Complete and clear marking of railway track alignment on ground (Award 4 marks for complete and neat marking) | 4 | ||
| Sub-Total | 23 | ||
| GRAND TOTAL | 49 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.