Quantity Survey  ·  Level 6
Civil Engineering Works
Chapter 1: Carry out drainage works
📚 6 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • Interpret drainage layouts correctly from working drawings by following standard operating procedures.
  • Carry out drainage earthworks safely and accurately according to project specifications and site conditions.
  • Determine the correct manhole types and sizes based on design requirements and hydraulic specifications.
  • Lay drainage pipes to the specified gradients and alignments following standard operating procedures.
  • Construct drainage pipe bedding and surrounds according to the required specifications.
  • Protect installed drainage pipes safely by following standard operating procedures and manufacturer’s recommendations.

Mastering these skills ensures you can build reliable drainage systems that keep communities safe and infrastructure working smoothly.

Drainage works form a critical component of civil engineering projects, especially in Kenya where seasonal rains can cause significant water accumulation and flooding if not properly managed. Quantity surveyors play a vital role in planning, costing, and supervising drainage installations to ensure efficient water flow and structural durability. This chapter focuses on the practical aspects of carrying out drainage works, emphasizing layout preparation, manhole positioning, and earthworks involved in drainage construction. Mastery of these elements enables quantity surveyors to contribute effectively to sustainable infrastructure development and cost control.

1.1 Drainage Layout

Drainage layout is fundamental to the design and execution of drainage systems. It involves planning the route and components of drainage to safely and efficiently remove surface and subsurface water from construction sites or developed areas. For quantity surveyors, understanding drainage layout ensures accurate measurement, valuation, and scheduling of works, as well as anticipating potential cost implications arising from site conditions. In Kenyan urban and rural settings, proper drainage planning mitigates risks of water damage to roads, buildings, and agricultural lands.

1.1.1 Prepare Drainage Layout

Preparing a drainage layout requires detailed site analysis and technical planning to establish the most effective drainage network. This process integrates topographical data, soil conditions, rainfall patterns, and existing infrastructure to design a system that prevents waterlogging and erosion.

Site Survey and Data Collection

  • Topographic Survey: Mapping the contours and slopes of the site to determine natural water flow directions. This guides the placement of drains to follow gravity, reducing pumping costs.
  • Soil Analysis: Identifying soil permeability and stability to decide on suitable drainage materials and pipe sizes. For example, clayey soils common in Nairobi require more robust drainage channels.
  • Rainfall Data Review: Using historical rainfall records from Kenya Meteorological Department to estimate peak flow volumes the drainage must handle.
  • Existing Infrastructure Assessment: Cataloguing current drainage and utility lines to avoid conflicts and optimize connections.
  • Environmental Constraints: Recognizing protected areas or wetlands that require special drainage considerations to comply with NEMA regulations.

Design Principles and Layout Planning

  • Gravity Flow Optimization: Arranging drains along natural slopes to minimize excavation and mechanical pumping needs.
  • Adequate Pipe Sizing: Calculating pipe diameters based on expected runoff volumes using the Rational Method or other hydrological models.
  • Spacing of Drains: Determining intervals between sub-drains to prevent water accumulation in low-lying areas.
  • Integration with Road and Building Layouts: Ensuring drainage does not interfere with foundations or pavements but instead protects them.
  • Provision for Future Expansion: Designing capacity to accommodate potential urban growth or climate change impacts.

Documentation and Drawings

  • Drainage Layout Plans: Detailed drawings showing pipe routes, manholes, catch basins, and discharge points.
  • Bill of Quantities (BoQ) Preparation: Itemizing materials, labor, and plant needed for each drainage component.
  • Specifications: Defining material standards, installation methods, and testing requirements aligned with Kenya Bureau of Standards (KEBS).

1.1.2 Positioning and Construction of Manhole

Manholes provide access points for inspection, cleaning, and maintenance of underground drainage systems. Their correct positioning and construction ensure system longevity and operational efficiency.

Criteria for Manhole Positioning

  • Change in Direction: Placing manholes where the drainage line changes direction to facilitate inspection and prevent clogging.
  • Junctions and Branches: Situating manholes at pipe intersections to allow easy access to multiple lines.
  • Changes in Gradient or Pipe Size: Positioning manholes where slopes vary or pipe diameters change to monitor flow conditions.
  • Maximum Spacing Limits: Ensuring manholes are not spaced beyond recommended distances (typically 30 meters in urban areas) to allow practical maintenance.
  • Accessibility: Locating manholes in areas accessible to maintenance crews and equipment, avoiding obstruction by buildings or traffic.

Construction Techniques and Materials

  • Excavation and Base Preparation: Digging to required depths and compacting the base to prevent settlement.
  • Manhole Chamber Construction: Using precast concrete rings or cast-in-situ concrete, ensuring water-tight joints to prevent infiltration or exfiltration.
  • Bench and Channel Formation: Shaping the internal floor to direct flow smoothly through the manhole, reducing turbulence and sedimentation.
  • Cover and Frame Installation: Fitting heavy-duty, corrosion-resistant covers with appropriate load ratings, such as ductile iron covers for high-traffic areas.
  • Backfilling and Compaction: Using selected materials to backfill around the manhole, compacted in layers to maintain structural integrity.

Quality Control and Safety Considerations

  • Alignment and Level Checks: Verifying manhole placement matches design coordinates and gradients.
  • Water Tightness Testing: Conducting tests to identify leakage points before backfilling.
  • Safety Barriers: Erecting temporary fencing and signage during construction to protect workers and the public.
  • Compliance with Standards: Adhering to KEBS and OSHA guidelines for manhole construction and worker safety.
The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒1.2 Carry Out Drainage Earthworks

Earthworks for drainage involve excavation, filling, and compaction to create trenches and beds for drainage pipes and associated structures. These activities require precise execution to maintain design profiles and prevent future settlement or failure. Prepa…

🔒1.3 Determination of Manhole Types and Sizes

In quantity surveying for civil engineering drainage works, accurately determining the types and sizes of manholes is crucial for effective project costing, scheduling, and compliance with local standards. Manholes serve as access points for inspection, cleani…

🔒1.4 Perform Drainage Pipe Laying

Drainage pipe laying is a critical activity in civil engineering works that directly affects the efficiency and durability of the drainage system. Quantity surveyors must understand the technical and practical aspects of pipe laying to prepare accurate cost pl…

🔒1.5 Carry out drainage pipe bedding and surrounds

In quantity surveying for civil engineering projects, understanding the correct procedures for drainage pipe bedding and surrounds is essential. Proper bedding supports the drainage pipes, ensuring structural integrity and durability, while surrounds protect t…

🔒1.6 Protection of drainage pipes

Protecting drainage pipes is a key responsibility for quantity surveyors overseeing civil engineering works. Damage during or after installation can lead to leaks, blockages, or structural failure, increasing costs and project delays. In Kenya’s diverse enviro…

Chapter Summary

This chapter has provided a comprehensive guide on carrying out drainage works in civil engineering projects. It began by explaining how to prepare a drainage layout, including the critical steps involved in positioning and constructing manholes to ensure efficient water flow and accessibility. The chapter then explored the process of drainage earthworks, detailing the excavation and ground preparation necessary to support the drainage system. It described how to determine appropriate manhole types and sizes based on site conditions and design requirements. The discussion continued with the proper techniques for laying drainage pipes, emphasizing alignment and gradient control. Attention was given to carrying out pipe bedding and surrounds to provide stability and prevent damage. Finally, the chapter addressed methods for protecting drainage pipes from external forces and environmental factors, ensuring the longevity and functionality of the drainage infrastructure.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. What are the key considerations when preparing a drainage layout for a commercial building in Nairobi? (3 marks)
  2. Identify three factors that influence the positioning of manholes in a drainage system. (3 marks)
🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Explain the key considerations when preparing a drainage layout for a commercial building site in Nairobi. (4 marks)
  2. Describe the factors influencing the positioning of manholes in a drainage system for a county government office. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Prepare detailed drainage layout plan for a residential site

Quantity Survey · Level 6
Civil Engineering Works
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Prepare a detailed drainage layout plan for a 20m x 15m residential site showing pipe runs, manholes, and drainage slopes as per the provided site dimensions.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring Tape (30m)Lime Powder
Builder's SquarePegging Nails (150mm)
Spirit LevelPersonal Protective Equipment (Helmet, Safety Boots, Reflective Jacket, Gloves)
Chalk Line Reel
Profile Boards
Mason's Hammer
Plumb Bob
Markers/Pens
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Measuring Tape (30m)1 Pc per Candidate
2Builder's Square1 Pc per 4 Candidates
3Spirit Level1 Pc per Candidate
4Chalk Line Reel1 Pc per Candidate
5Lime PowderSufficient per Candidate
6Markers/Pens1 Pc per Candidate
7Profile Boards4 Pcs per Candidate
8Mason's Hammer1 Pc per 4 Candidates
9Pegging Nails (150mm)20 Pcs per Candidate
10Plumb Bob1 Pc per Candidate
11Personal Protective Equipment (Helmet, Safety Boots, Reflective Jacket, Gloves)1 Set per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: SITE PREPARATION AND SETTING OUT
Identified and used PPEs in line with occupational safety and health regulations
(Award 1 mark for each PPE donned: Helmet, Safety Boots, Reflective Jacket, Gloves, and general safety awareness)
5
Assembled required tools and materials correctly before starting the layout
(Award 0.5 marks for each correctly assembled tool/material, up to 3 marks)
3
Prepared and cleared site area sufficiently for layout work
(Award 2 marks for proper clearance and preparation of site)
2
Set out the drainage layout using correct procedures and positioned pegs accurately according to site dimensions
(Award 2 marks for correct pegging of length, 2 marks for width, 2 marks for diagonal checks)
6
Used builder’s line and profile boards to transfer and mark out drainage points and pipe runs
(Award 1 mark for each correctly transferred corner/point, total 5 points)
5
Marked the plan layout on the ground clearly and accurately using lime powder
(Award 1 mark for each correctly marked corner, total 4 marks)
4
Cleaned the working area after completion of layout
(Award 2 marks for neatness and clearing of debris)
2
Cleaned and stored tools and equipment correctly after use
(Award 1 mark each for cleaning and proper storage)
2
Sub-Total29
PRODUCT CHECKLIST
Drainage layout plan shows correct site dimensions (20m length ±50mm, 15m width ±50mm) with accurate pipe runs and manhole positions marked
(Award 3 marks for correct length and width dimensions, 2 marks for correctly positioned pipe runs and manholes)
5
Layout is parallel to datum line and well squared with correct diagonal measurements (±50mm tolerance)
(Award 2 marks for parallelism, 3 marks for squareness with correct diagonals)
5
Profile boards are correctly placed and levelled according to layout plan
(Award 1 mark for each correctly placed and levelled profile board, total 4 marks)
4
Complete set out of drainage layout as per procedure with clear and legible markings
(Award 2 marks for 50% completion, 3 marks for 50-75% completion, 7 marks for above 75% completion)
7
Sub-Total21
GRAND TOTAL50
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Set out drainage layout on site

Quantity Survey · Level 6
Civil Engineering Works
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Set out the drainage layout on site using profile boards and pegs according to the approved plan with dimensions 20m by 15m.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring Tape (30m)Lime for marking
Builder's LineWooden Pegs (30cm length)
Profile Boards (timber 50mm x 100mm x 1.5m)PPE: Helmet, Safety Boots, Reflective Jacket
Spirit Level
Plumb Bob
Hammer
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Measuring Tape (30m)1 Pc per Candidate
2Builder's Line1 Pc per Candidate
3Profile Boards (timber 50mm x 100mm x 1.5m)4 Pcs per Candidate
4Lime for marking1 Kg per Candidate
5Spirit Level1 Pc per Candidate
6Plumb Bob1 Pc per Candidate
7Hammer1 Pc per 4 Candidates
8Wooden Pegs (30cm length)20 Pcs per Candidate
9PPE: Helmet, Safety Boots, Reflective Jacket1 Set per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: SETTING OUT DRAINAGE LAYOUT
Identified and used appropriate PPE (Helmet, Safety Boots, Reflective Jacket)
(Award 1 mark each for any correct PPE used)
3
Assembled tools and materials required for setting out
(Award 0.5 marks for each correctly assembled tool/material, total 6 items)
3
Prepared the site by clearing and marking sufficient area for the drainage layout
(Award 2 marks for correct site preparation)
2
Set out the layout correctly using profile boards, pegs and builder's line according to the 20m x 15m plan
(Award 2 marks for each correctly positioned side and corner peg)
8
Transferred dimensions accurately to profile boards with builder's line
(Award 1 mark per correctly transferred corner, total 6 marks)
6
Marked the layout on the ground clearly using lime at all corners and drainage points
(Award 1 mark for each correctly marked corner, total 4 corners)
4
Ensured layout is squared by checking diagonals within ±50 mm tolerance
(Award 3 marks for correct squareness within tolerance)
3
Cleaned the working area after layout completion
(Award 2 marks for thorough cleaning)
2
Cleaned and stored tools and equipment properly after use
(Award 2 marks for correct cleaning and storage)
2
Sub-Total33
PRODUCT CHECKLIST
Layout dimensions set out accurately to 20m by 15m with ±50 mm tolerance
(Award 5 marks for full dimensional accuracy)
5
Layout is squared with diagonals equal within ±50 mm tolerance
(Award 4 marks for correct squareness)
4
Profile boards and pegs placed correctly and firmly according to the plan
(Award 3 marks for correct positioning and firmness)
3
Layout clearly marked on ground with lime at all corners and drainage points
(Award 3 marks for clear and complete marking)
3
Layout is parallel to the datum line established
(Award 2 marks for correct parallel alignment)
2
Sub-Total17
GRAND TOTAL50
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Position and construct manhole base 750mm x 750mm x 300mmPractical 3
🔒Construct Manhole Walls and Install CoverPractical 4
🔒Excavate and prepare drainage trenches for pipe installationPractical 5
🔒Perform drainage pipe laying with correct alignment and slopePractical 6
🔒Carry out drainage pipe bedding and surroundsPractical 7
🔒Protect drainage pipes during constructionPractical 8
🔒Check and adjust drainage pipe levels and alignmentPractical 9
🔒Backfill Trenches After Pipe Laying and BeddingPractical 10
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 18 questions Start quiz ▾
0%
0 / 2
🔒

16 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Interpret drainage layouts correctly from working drawings by following standard operating procedures.
  • Carry out drainage earthworks safely and accurately according to project specifications and site conditions.
  • Determine the correct manhole types and sizes based on design requirements and hydraulic specifications.
  • Lay drainage pipes to the specified gradients and alignments following standard operating procedures.
  • Construct drainage pipe bedding and surrounds according to the required specifications.
  • Protect installed drainage pipes safely by following standard operating procedures and manufacturer’s recommendations.

Tick each one you can genuinely do.