By the end of this chapter, you will be able to:

  • confidently carry out reconnaissance by following workplace procedures.
  • correctly assemble levelling tools and equipment needed for road surveying.
  • apply surveying levelling principles using the right procedures.
  • accurately record levelling measurements to meet required standards.
  • carry out appropriate site clearance based on the conditions of the site.
  • determine reduced levels precisely according to the ground’s nature.
  • produce a clear mass haul diagram from the contours you have plotted.

These skills are essential for ensuring road surveys are accurate and reliable, helping you contribute to safe and efficient engineering projects.

Road surveys are essential in quantity surveying for accurate cost estimation, project planning, and contract management in infrastructure development. The ability to interpret survey maps and photographs with correct scaling ensures precise measurement of distances and areas, which directly affects quantity take-offs and bill of quantities preparation. Additionally, setting out circular curves correctly on road alignments is fundamental for design accuracy and safety, impacting the construction phase and long-term maintenance. This chapter addresses these critical aspects, equipping quantity survey professionals with the technical skills needed in Kenyan road construction projects.

2.1 Scaling of Survey Maps and Photographs

Scaling is a fundamental concept in engineering surveys, particularly for quantity surveyors who rely on maps and aerial photographs to quantify materials and plan projects. In Kenya, where many road projects span vast and varied terrains, understanding scale enables professionals to translate drawings and images into real-world dimensions accurately. This section explores the principles of scaling, methods of determining scales, and practical applications in quantity surveying.

2.1.1 Principles of Scaling in Survey Maps and Photographs

Scaling refers to the process of representing real-world distances and areas on a smaller, proportional level in maps or photographs. For quantity surveyors, the scale is crucial because it determines how measurements on a plan correspond to actual site dimensions, affecting quantity calculations and cost estimates.

Characteristics of Scaling

  • Ratio Representation: Scale is expressed as a ratio, such as 1:1000, meaning one unit on the map equals 1000 units on the ground. This ratio must be consistently applied to all measurements.
  • Types of Scales: Common types include linear scale, where a graphical bar shows distances, and representative fraction (RF), a numerical ratio. Both are used in Kenyan surveying projects.
  • Accuracy Dependency: The precision of measurements depends on the scale; larger scale maps (e.g., 1:500) provide more detail than smaller scales (e.g., 1:50,000).
  • Distortion Factors: Photographs, especially aerial ones, can have distortions due to camera angle, terrain relief, or lens effects, affecting scale uniformity.
  • Application in Quantity Surveying: Scaling enables estimation of road lengths, embankment volumes, and surface areas, which are critical inputs for bills of quantities in road construction contracts.

2.1.2 Methods of Determining Scale from Maps and Photographs

Determining the scale of existing maps or aerial photos is necessary when original scale information is unavailable or needs verification. Quantity surveyors must be adept at extracting scale for reliable measurements.

Techniques for Scale Determination

  • Ground Control Points (GCPs): Identifying known locations on the map or photo with known coordinates allows calculation of scale by comparing map distances to actual ground distances.
  • Measuring Known Distances: Selecting features such as road sections, rivers, or buildings with known lengths on the ground and measuring their length on the map to derive the representative fraction.
  • Using Scale Bars: Some maps and photographs include a scale bar, a graphical tool that can be measured directly with a ruler to establish the scale.
  • Photogrammetric Methods: Employing stereoscopic pairs of aerial photographs to calculate accurate scales through triangulation, commonly used in detailed Kenyan road surveys.
  • Digital Tools: Geographic Information Systems (GIS) and software like AutoCAD can assist in scaling by importing georeferenced data for precise measurements.

2.1.3 Practical Application of Scaling in Quantity Surveying for Roads

Scaling directly impacts the accuracy of quantity take-offs and cost estimation in road projects. Quantity surveyors use scaled maps and photographs to measure lengths, areas, and volumes for contract preparation and monitoring.

Application Areas

  • Road Length Measurement: Using scaled plans to determine the centerline length of a road for cost estimation of pavement and earthworks.
  • Cut and Fill Volume Estimation: Calculating embankment and excavation volumes by scaling contour maps and cross-sections.
  • Material Quantification: Estimating quantities of materials like gravel, bitumen, and aggregates by measuring scaled surface areas.
  • Planning and Scheduling: Scaling helps in plotting site layouts for access roads, drainage, and construction camps.
  • Dispute Resolution: Accurate scaling assists in verifying claims related to changes in quantities during construction, reducing conflicts between contractors and clients.

2.1.4 Challenges and Solutions in Scaling Survey Maps and Photographs

Scaling is not without challenges, especially in the Kenyan context where terrain variability and technological limitations can affect accuracy. Understanding these challenges and adopting mitigation strategies ensures reliability.

Challenges in Scaling

  • Distortion in Aerial Photographs: Relief displacement and camera tilt can cause scale variation across the photo.
  • Inadequate Ground Control Points: Sparse or inaccurately located GCPs reduce the reliability of scale determination.
  • Map Outdatedness: Older maps may not reflect current ground realities, affecting measurement accuracy.
  • Human Error: Misreading scales or measurement errors during scaling can lead to significant quantity miscalculations.
  • Technological Accessibility: Limited access to advanced photogrammetric or GIS tools in some regions hampers precise scaling.

Mitigation Strategies

  • Use multiple GCPs spread evenly over the survey area to improve scale accuracy.
  • Employ digital photogrammetry and GIS software where possible for automated scale correction.
  • Cross-verify measurements using different methods such as ground surveys and scaling from maps.
  • Update base maps regularly through collaboration with national mapping agencies like the Survey of Kenya.
  • Train quantity survey teams in scale interpretation and measurement techniques to reduce human errors.

Practice Questions

  1. Explain the significance of scale in survey maps and photographs for quantity surveying in road projects. (5 marks)
  2. Describe five methods used to determine the scale of a survey map or aerial photograph. (10 marks)
  3. How can scaling errors affect quantity take-offs in road construction? Provide three examples. (6 marks)
  4. Discuss challenges faced in scaling aerial photographs in Kenyan road surveys and suggest practical solutions. (9 marks)
The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒2.2 Setting Circular Curves

Circular curves are integral to road alignment design, allowing smooth transitions between straight sections. For quantity surveyors, understanding the setting out of circular curves is essential to verify design compliance, prepare accurate cost estimates, an…

🔒2.3 Carrying out Traverse Details

In the context of quantity surveying for road projects, carrying out traverse details is fundamental for establishing accurate control points that guide the design and construction phases. Traverse surveys provide the backbone for mapping out the road alignmen…

🔒2.4 Emerging Technologies

Emerging technologies are revolutionizing how quantity surveyors conduct road surveys in Kenya, enhancing accuracy, speed, and safety. These innovations provide new tools and methods that complement traditional surveying techniques, enabling surveyors to handl…

Chapter Summary

This chapter explored essential techniques and considerations in conducting road surveys, beginning with the importance of scaling survey maps and photographs accurately to ensure precise representation of terrain and features. It then detailed the procedures for setting circular curves, a critical aspect in designing smooth and safe road alignments. The process of carrying out traverse details was examined, emphasizing the need for systematic measurement and recording of angles and distances to establish control points. The chapter also introduced emerging technologies that are transforming road surveying practices, including the use of Unmanned Aerial Vehicles or drones for efficient data collection. Aerial data acquisition methods were discussed for their ability to capture extensive and detailed topographic information. The benefits of improved safety and accessibility through these technologies were highlighted, particularly in challenging or hazardous environments. Lastly, mobile mapping systems were presented as advanced tools that integrate various sensors to enhance the speed and accuracy of survey data collection.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. Define the term scaling in the context of survey maps and explain why accurate scaling is important in quantity surveying for road projects. (3 marks)
  2. Identify the primary difference between a simple circular curve and a compound curve in road alignment. (2 marks)
🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Define the term scale in the context of survey maps and explain its significance for quantity surveyors working on road projects in Kenya. (4 marks)
  2. Describe the process of setting out a simple circular curve on a road alignment using chainage and deflection angles. (4 marks)
🔒18 more in this section.

Chapter Practical Activities

Practical 1: Scaling of Survey Maps and Photographs for Road Survey

Quantity Survey · Level 6
Engineering Survey II
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Calculate real ground distances from given survey maps and aerial photographs using appropriate scales and record results accurately.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Metric ruler (30 cm)Survey scale map (scale 1:5000)
ProtractorAerial photograph (scale 1:10000)
CalculatorGraph paper (A4 size)
Pencils (HB)Notebook
Eraser
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Metric ruler (30 cm)1 Pc per Candidate
2Protractor1 Pc per Candidate
3Graph paper (A4 size)2 Sheets per Candidate
4Calculator1 Pc per Candidate
5Pencils (HB)2 Pcs per Candidate
6Eraser1 Pc per Candidate
7Survey scale map (scale 1:5000)1 Sheet per Candidate
8Aerial photograph (scale 1:10000)1 Sheet per Candidate
9Notebook1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: SCALING OF SURVEY MAPS AND PHOTOGRAPHS
Used appropriate PPEs (safety boots, reflective jacket, helmet)
(Award 1 mark each for any correct PPEs)
3
Prepared workspace with all necessary tools and materials assembled
(Award 2 marks for complete assembly of tools and materials)
2
Identified and explained the scale on the survey map (1:5000) and aerial photograph (1:10000)
(Award 1 mark each for correct identification and explanation of each scale)
3
Measured distances accurately on the survey map using a metric ruler
(Award 1 mark each for four correct distance measurements)
4
Measured distances accurately on the aerial photograph using a metric ruler
(Award 1 mark each for four correct distance measurements)
4
Calculated real ground distances correctly using the map scale
(Award 1 mark each for five correct calculations)
5
Calculated real ground distances correctly using the photograph scale
(Award 1 mark each for five correct calculations)
5
Recorded all measurements and calculations neatly and accurately in the notebook
(Award 1 mark each for neatness, accuracy, completeness, and legibility)
4
Cleaned and stored tools and materials properly after completion
(Award 2 marks for proper cleaning and storage)
2
Sub-Total32
PRODUCT CHECKLIST
Accurate measurement of distances on map and photograph within ±2 mm tolerance
(Award 5 marks for all measurements within tolerance)
5
Correct calculation of real ground distances within ±1% error
(Award 8 marks for all calculations accurate within tolerance)
8
Complete, neat, and legible recording of all data and results
(Award 5 marks for complete and neat record keeping)
5
Sub-Total18
GRAND TOTAL50
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Setting Out Circular Curve on Road Alignment

Quantity Survey · Level 6
Engineering Survey II
PRACTICAL ASSESSMENT
TIME: 4 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Set out a circular curve of radius 150m and length 75m on road alignment using chainage and curve parameters.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
Measuring Tape 30mPegging Nails
Theodolite or Total StationChalk Powder / Lime
Plumb Bob
Range Poles
Hammer
Field Book and Pencil
Calculator
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Measuring Tape 30m1 Pc per Candidate
2Theodolite or Total Station1 Pc per Candidate
3Plumb Bob1 Pc per Candidate
4Range Poles4 Pcs per Candidate
5Pegging Nails20 Pcs per Candidate
6Hammer1 Pc per 4 Candidates
7Chalk Powder / LimeSufficient per Candidate
8Field Book and Pencil1 Set per Candidate
9Calculator1 Pc per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: SETTING OUT CIRCULAR CURVE
Identified and used appropriate PPE (helmet, reflective vest, safety boots)
(Award 1 mark each for any correct PPE donned)
3
Assembled and prepared survey instruments and tools correctly
(Award 1 mark each for correct assembly of Theodolite, measuring tape, and range poles)
3
Cleared and prepared the site adequately for setting out
(Award 2 marks for proper site clearance and demarcation)
2
Correctly set up the instrument (theodolite/total station) over the designated point
(Award 1 mark each for centering, leveling, and focusing)
3
Accurately measured and pegged the tangent points and curve points using the given radius and chainage
(Award 2 marks for each correctly pegged tangent and curve point, total 4 points)
8
Used chalk powder/lime to mark the curve on the ground clearly
(Award 3 marks for clear, continuous marking of the curve)
3
Recorded all measurements accurately in the field book
(Award 1 mark for each correctly recorded chainage, radius, and offsets)
3
Cleaned and stored tools and instruments properly after completion
(Award 2 marks for proper cleaning and storage)
2
Observed accuracy and precision throughout the setting out process
(Award 2 marks for 75% accuracy, 4 marks for 100% accuracy)
4
Sub-Total31
PRODUCT CHECKLIST
Circular curve set out with radius 1500mm ±50mm
(Award 4 marks for radius within ±50mm tolerance)
4
Curve length marked as 75m ±50mm
(Award 4 marks for length within ±50mm tolerance)
4
Pegging points correctly placed at tangent and curve points with ±50mm tolerance
(Award 5 marks for all pegs within tolerance)
5
Curve is smooth and continuous with no abrupt deviations
(Award 3 marks for smoothness and continuity)
3
Markings are clearly visible and durable on the ground
(Award 3 marks for clear and lasting markings)
3
Sub-Total19
GRAND TOTAL50
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Traverse Survey and Plotting of Road AlignmentPractical 3
🔒Operate UAV for Aerial Survey of Road CorridorPractical 4
🔒Processing and interpreting UAV aerial survey data for road alignmentPractical 5
🔒Road Survey Data Collection Using Mobile Mapping SystemsPractical 6
🔒Application of GNSS Technology in Road SurveyingPractical 7
🔒Implement Safety and Accessibility Measures During Road SurveyPractical 8
🔒Combining Traverse and Curve Setting for Road AlignmentPractical 9
🔒Integrate UAV and Traverse Data for Road Survey LayoutPractical 10
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 18 questions Start quiz ▾
0%
0 / 2
🔒

16 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • confidently carry out reconnaissance by following workplace procedures.
  • correctly assemble levelling tools and equipment needed for road surveying.
  • apply surveying levelling principles using the right procedures.
  • accurately record levelling measurements to meet required standards.
  • carry out appropriate site clearance based on the conditions of the site.
  • determine reduced levels precisely according to the ground’s nature.
  • produce a clear mass haul diagram from the contours you have plotted.

Tick each one you can genuinely do.

So, are you there yet?

You're competent when you can confidently do 50% or more of what this chapter promised.