By the end of this chapter, you will be able to:
These skills are essential for ensuring road surveys are accurate and reliable, helping you contribute to safe and efficient engineering projects.
Road surveys are essential in quantity surveying for accurate cost estimation, project planning, and contract management in infrastructure development. The ability to interpret survey maps and photographs with correct scaling ensures precise measurement of distances and areas, which directly affects quantity take-offs and bill of quantities preparation. Additionally, setting out circular curves correctly on road alignments is fundamental for design accuracy and safety, impacting the construction phase and long-term maintenance. This chapter addresses these critical aspects, equipping quantity survey professionals with the technical skills needed in Kenyan road construction projects.
Scaling is a fundamental concept in engineering surveys, particularly for quantity surveyors who rely on maps and aerial photographs to quantify materials and plan projects. In Kenya, where many road projects span vast and varied terrains, understanding scale enables professionals to translate drawings and images into real-world dimensions accurately. This section explores the principles of scaling, methods of determining scales, and practical applications in quantity surveying.
Scaling refers to the process of representing real-world distances and areas on a smaller, proportional level in maps or photographs. For quantity surveyors, the scale is crucial because it determines how measurements on a plan correspond to actual site dimensions, affecting quantity calculations and cost estimates.
Determining the scale of existing maps or aerial photos is necessary when original scale information is unavailable or needs verification. Quantity surveyors must be adept at extracting scale for reliable measurements.
Scaling directly impacts the accuracy of quantity take-offs and cost estimation in road projects. Quantity surveyors use scaled maps and photographs to measure lengths, areas, and volumes for contract preparation and monitoring.
Scaling is not without challenges, especially in the Kenyan context where terrain variability and technological limitations can affect accuracy. Understanding these challenges and adopting mitigation strategies ensures reliability.
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter explored essential techniques and considerations in conducting road surveys, beginning with the importance of scaling survey maps and photographs accurately to ensure precise representation of terrain and features. It then detailed the procedures for setting circular curves, a critical aspect in designing smooth and safe road alignments. The process of carrying out traverse details was examined, emphasizing the need for systematic measurement and recording of angles and distances to establish control points. The chapter also introduced emerging technologies that are transforming road surveying practices, including the use of Unmanned Aerial Vehicles or drones for efficient data collection. Aerial data acquisition methods were discussed for their ability to capture extensive and detailed topographic information. The benefits of improved safety and accessibility through these technologies were highlighted, particularly in challenging or hazardous environments. Lastly, mobile mapping systems were presented as advanced tools that integrate various sensors to enhance the speed and accuracy of survey data collection.
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Metric ruler (30 cm) | Survey scale map (scale 1:5000) |
| Protractor | Aerial photograph (scale 1:10000) |
| Calculator | Graph paper (A4 size) |
| Pencils (HB) | Notebook |
| Eraser |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Metric ruler (30 cm) | 1 Pc per Candidate |
| 2 | Protractor | 1 Pc per Candidate |
| 3 | Graph paper (A4 size) | 2 Sheets per Candidate |
| 4 | Calculator | 1 Pc per Candidate |
| 5 | Pencils (HB) | 2 Pcs per Candidate |
| 6 | Eraser | 1 Pc per Candidate |
| 7 | Survey scale map (scale 1:5000) | 1 Sheet per Candidate |
| 8 | Aerial photograph (scale 1:10000) | 1 Sheet per Candidate |
| 9 | Notebook | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: SCALING OF SURVEY MAPS AND PHOTOGRAPHS | |||
| Used appropriate PPEs (safety boots, reflective jacket, helmet) (Award 1 mark each for any correct PPEs) | 3 | ||
| Prepared workspace with all necessary tools and materials assembled (Award 2 marks for complete assembly of tools and materials) | 2 | ||
| Identified and explained the scale on the survey map (1:5000) and aerial photograph (1:10000) (Award 1 mark each for correct identification and explanation of each scale) | 3 | ||
| Measured distances accurately on the survey map using a metric ruler (Award 1 mark each for four correct distance measurements) | 4 | ||
| Measured distances accurately on the aerial photograph using a metric ruler (Award 1 mark each for four correct distance measurements) | 4 | ||
| Calculated real ground distances correctly using the map scale (Award 1 mark each for five correct calculations) | 5 | ||
| Calculated real ground distances correctly using the photograph scale (Award 1 mark each for five correct calculations) | 5 | ||
| Recorded all measurements and calculations neatly and accurately in the notebook (Award 1 mark each for neatness, accuracy, completeness, and legibility) | 4 | ||
| Cleaned and stored tools and materials properly after completion (Award 2 marks for proper cleaning and storage) | 2 | ||
| Sub-Total | 32 | ||
| PRODUCT CHECKLIST | |||
| Accurate measurement of distances on map and photograph within ±2 mm tolerance (Award 5 marks for all measurements within tolerance) | 5 | ||
| Correct calculation of real ground distances within ±1% error (Award 8 marks for all calculations accurate within tolerance) | 8 | ||
| Complete, neat, and legible recording of all data and results (Award 5 marks for complete and neat record keeping) | 5 | ||
| Sub-Total | 18 | ||
| GRAND TOTAL | 50 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring Tape 30m | Pegging Nails |
| Theodolite or Total Station | Chalk Powder / Lime |
| Plumb Bob | |
| Range Poles | |
| Hammer | |
| Field Book and Pencil | |
| Calculator |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Measuring Tape 30m | 1 Pc per Candidate |
| 2 | Theodolite or Total Station | 1 Pc per Candidate |
| 3 | Plumb Bob | 1 Pc per Candidate |
| 4 | Range Poles | 4 Pcs per Candidate |
| 5 | Pegging Nails | 20 Pcs per Candidate |
| 6 | Hammer | 1 Pc per 4 Candidates |
| 7 | Chalk Powder / Lime | Sufficient per Candidate |
| 8 | Field Book and Pencil | 1 Set per Candidate |
| 9 | Calculator | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: SETTING OUT CIRCULAR CURVE | |||
| Identified and used appropriate PPE (helmet, reflective vest, safety boots) (Award 1 mark each for any correct PPE donned) | 3 | ||
| Assembled and prepared survey instruments and tools correctly (Award 1 mark each for correct assembly of Theodolite, measuring tape, and range poles) | 3 | ||
| Cleared and prepared the site adequately for setting out (Award 2 marks for proper site clearance and demarcation) | 2 | ||
| Correctly set up the instrument (theodolite/total station) over the designated point (Award 1 mark each for centering, leveling, and focusing) | 3 | ||
| Accurately measured and pegged the tangent points and curve points using the given radius and chainage (Award 2 marks for each correctly pegged tangent and curve point, total 4 points) | 8 | ||
| Used chalk powder/lime to mark the curve on the ground clearly (Award 3 marks for clear, continuous marking of the curve) | 3 | ||
| Recorded all measurements accurately in the field book (Award 1 mark for each correctly recorded chainage, radius, and offsets) | 3 | ||
| Cleaned and stored tools and instruments properly after completion (Award 2 marks for proper cleaning and storage) | 2 | ||
| Observed accuracy and precision throughout the setting out process (Award 2 marks for 75% accuracy, 4 marks for 100% accuracy) | 4 | ||
| Sub-Total | 31 | ||
| PRODUCT CHECKLIST | |||
| Circular curve set out with radius 1500mm ±50mm (Award 4 marks for radius within ±50mm tolerance) | 4 | ||
| Curve length marked as 75m ±50mm (Award 4 marks for length within ±50mm tolerance) | 4 | ||
| Pegging points correctly placed at tangent and curve points with ±50mm tolerance (Award 5 marks for all pegs within tolerance) | 5 | ||
| Curve is smooth and continuous with no abrupt deviations (Award 3 marks for smoothness and continuity) | 3 | ||
| Markings are clearly visible and durable on the ground (Award 3 marks for clear and lasting markings) | 3 | ||
| Sub-Total | 19 | ||
| GRAND TOTAL | 50 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.