By the end of this chapter, you will be able to:
Mastering these skills will help you keep industrial machines running smoothly and efficiently, making you a valuable asset in any automation environment!
Industrial automation is a critical area within electronics engineering, especially in Kenya's growing manufacturing and processing sectors. Installing machine systems involves integrating various electronic and mechanical components to create automated production lines that improve efficiency and safety. This chapter focuses on essential terminology that electronics engineers must understand to effectively install, maintain, and troubleshoot automated machinery in industrial environments such as Nairobi’s manufacturing plants and county assembly workshops.
Understanding key terms in industrial automation is fundamental for electronics engineers to communicate effectively, design solutions, and implement systems that meet operational requirements. This section breaks down important terminology relevant to machine system installation, ensuring clarity in technical discussions and documentation.
Automation refers to the use of control systems, such as computers or robots, and information technologies to handle different processes and machinery with minimal human intervention. In Kenya’s electronics engineering sector, automation is central to enhancing productivity in industries like food processing and packaging.
A machine system in industrial automation consists of interconnected components that work together to perform specific tasks. Electronics engineers must understand these components to install and configure systems correctly.
Installation and commissioning are distinct but interrelated stages in bringing an automated machine system into operational readiness.
PLCs are central to industrial automation, acting as the brains of machine control systems. Kenyan electronics engineers must be proficient in their operation and programming.
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter explored key concepts essential for installing machine systems within industrial automation. It began by clarifying important terms that form the foundation for understanding machine installation processes. The discussion then moved to conveyors, detailing various types such as belt, roller, chain and mat, rubber, vibrating, and pneumatic conveyors, along with the accessories that support their operation. Following this, the chapter examined indexers and synchronous machines, including rotary cam indexers, synchronous chassis pallets, walking beams, and pick and place mechanisms, highlighting their roles in coordinated machine movements. The final section focused on part feeders, describing vibratory bowls and feeders, step and rotary feeders, as well as escapements and parts handling techniques that ensure efficient component delivery. Together, these topics provide a comprehensive overview of the equipment and mechanisms involved in setting up automated industrial systems.
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Multimeter | Electrical Connection Wires |
| PLC Trainer Kit | Labeling Tags |
| Marker Pen | Block Diagram Sheet |
| Instruction Manual |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Personal Protective Equipment (Dustcoat/Overall) | 1 Set per Candidate |
| 2 | Multimeter | 1 Pc per Candidate |
| 3 | PLC Trainer Kit with Inputs and Outputs | 1 Pc per Candidate |
| 4 | Electrical Connection Wires (0.5 m Red, 0.5 m Blue, 0.5 m Black) | 1 Set per Candidate |
| 5 | Labeling Tags and Marker Pen | 1 Set per Candidate |
| 6 | Block Diagram Sheet A3 Size | 1 Pc per Candidate |
| 7 | Instruction Manual on Industrial Automation Terms | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Preparation and Safety | |||
| Wore Personal Protective Equipment (Dustcoat/Overall) (Award 1 mark for correct PPE use, zero if not) | 1 | ||
| Applied good housekeeping practice at the workstation (Award 1 mark for neat and organized workspace) | 1 | ||
| Identified and used the correct tools and equipment (Multimeter, PLC Trainer Kit) (Award 1 mark each for correct identification and appropriate use) | 2 | ||
| Sub-Total | 4 | ||
| TASK 2: Demonstration and Explanation | |||
| Correctly identified and defined five industrial automation terms: Sensor, Actuator, PLC, HMI, and SCADA (Award 1 mark per correct term definition) | 5 | ||
| Demonstrated practical example for each term using the PLC trainer kit (Award 1 mark per correct demonstration linked to the term) | 5 | ||
| Used correct color codes for wiring connections (Award 2 marks for observing color coding standards) | 2 | ||
| Sub-Total | 12 | ||
| TASK 3: Diagram and Labelling | |||
| Drew the block diagram correctly showing PLC inputs and outputs (Award 2 marks for accurate block diagram with inputs and outputs) | 2 | ||
| Labeled components and connections clearly for identification (Award 3 marks for neat and complete labeling) | 3 | ||
| Sub-Total | 5 | ||
| PRODUCT CHECKLIST | |||
| Block diagram sheet dimension 420mm x 297mm (A3 size) verified (Award 2 marks if dimensions match exactly) | 2 | ||
| Correctness and clarity of block diagram with all five terms represented (Award 3 marks for clear and correct diagram with all terms) | 3 | ||
| Neatness and completeness of wiring and labeling on PLC trainer kit (Award 4 marks for tidy wiring and clear labeling) | 4 | ||
| Sub-Total | 9 | ||
| GRAND TOTAL | 30 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Adjustable spanner | Belt conveyor frame sections |
| Screwdriver set | Conveyor belt 3000mm x 500mm |
| Hammer | Drive pulley |
| Spirit level | Idler rollers |
| Measuring tape | Motor (0.75 kW, 3-phase) |
| Pliers | Motor mounting bracket |
| Wire stripper | Fasteners (bolts, nuts, washers) |
| Electric drill | Conveyor belt tensioning device |
| Electrical wiring cable (1.5 mm²) | |
| Cable ties | |
| Safety guards |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Belt conveyor frame sections | 1 set per Candidate |
| 2 | Conveyor belt 3000mm x 500mm | 1 Pc per Candidate |
| 3 | Drive pulley | 1 Pc per Candidate |
| 4 | Idler rollers | 6 Pcs per Candidate |
| 5 | Motor (0.75 kW, 3-phase) | 1 Pc per Candidate |
| 6 | Motor mounting bracket | 1 Pc per Candidate |
| 7 | Fasteners (bolts, nuts, washers) | 1 bag per 3 Candidates |
| 8 | Conveyor belt tensioning device | 1 Pc per Candidate |
| 9 | Electrical wiring cable (1.5 mm², 5 m) | 1 roll per 5 Candidates |
| 10 | Cable ties | 1 pack per Candidate |
| 11 | Safety guards | 1 set per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Installation Process | |||
| Wore Personal Protective Equipment (dustcoat, gloves, safety boots) (Award 2 marks if all PPE worn correctly, zero if not) | 2 | ||
| Identified and used correct tools and equipment for assembly (Award 1 mark each for correct use of adjustable spanner, spirit level, and electric drill) | 3 | ||
| Set out and positioned conveyor frame accurately as per drawing (Award up to 4 marks for correct positioning and leveling) | 4 | ||
| Assembled frame sections and fixed securely using appropriate fasteners (Award 1 mark for each correctly fitted frame section and secure fixing) | 5 | ||
| Fitted drive pulley and idler rollers correctly on the frame (Award 2 marks for correct drive pulley fitting, 2 marks for idler rollers) | 4 | ||
| Mounted and secured the motor with correct alignment (Award 4 marks for correct motor mounting and alignment) | 4 | ||
| Installed conveyor belt and adjusted tensioning device properly (Award 5 marks for correct belt fitting and tension adjustment) | 5 | ||
| Connected electrical wiring safely and tidily using cable ties (Award 3 marks for proper electrical connection and cable management) | 3 | ||
| Fitted safety guards as per safety standards (Award 3 marks for complete and secure fitting of safety guards) | 3 | ||
| Applied good housekeeping practice after installation (Award 2 marks for cleaning work area and proper tool storage) | 2 | ||
| Labelled the conveyor system components for identification (Award 2 marks for clear and correct labelling) | 2 | ||
| Observed colour coding on electrical wiring (Award 2 marks if wiring colour code correctly observed) | 2 | ||
| Tested functionality of installed conveyor system (Award 5 marks for smooth running without abnormal noise or belt slippage) | 5 | ||
| Sub-Total | 44 | ||
| PRODUCT CHECKLIST | |||
| Conveyor length is 3000mm ±10mm and width is 500mm ±5mm (Award 4 marks if dimensions are within tolerance, zero if outside) | 4 | ||
| Frame sections are square and level (spirit level used) (Award 4 marks if frame is square and level) | 4 | ||
| Belt is aligned correctly and runs centrally on rollers (Award 4 marks if belt alignment is correct) | 4 | ||
| Fasteners are tight and components firmly fixed (Award 3 marks if all fasteners are secure) | 3 | ||
| Electrical connections are neat with correct wire colour coding (Award 3 marks for neat wiring and correct colour code) | 3 | ||
| Safety guards are firmly fixed and cover all moving parts (Award 4 marks if safety guards are properly fitted) | 4 | ||
| Sub-Total | 22 | ||
| GRAND TOTAL | 66 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.