By the end of this chapter, you will be able to:
Mastering these skills ensures you deliver reliable, safe, and user-ready automation systems that meet industry standards and customer expectations.
Compiled by: Paul Nganga
Automation systems in electrical engineering are critical for enhancing operational efficiency, reliability, and safety in various industrial and commercial installations. Commissioning an automation system ensures that all components function according to design specifications before they are fully integrated into the electrical infrastructure. In Kenya, where industries such as manufacturing, power distribution, and water treatment increasingly rely on automated electrical systems, thorough commissioning is essential to avoid costly downtime and ensure compliance with national and international standards.
Conducting a unit test is a foundational step in the commissioning of an electrical automation system. It verifies the functionality of individual components or modules, such as sensors, relays, controllers and drives, before they are integrated into the full system. This approach minimises faults during final commissioning and ensures each unit meets its performance criteria. In a water pumping station or a production line, a faulty relay or sensor found at unit level is far cheaper and safer to correct than the same fault found after the whole panel is energised.
Unit testing is the process of examining the smallest testable parts of an automation system independently to confirm their correct operation. It isolates individual components such as sensors, controllers and actuators so that defects are identified early in the commissioning phase.
Unit testing in electrical automation focuses on validating each device or software module separately, ensuring that it performs its intended function without interference from other parts of the system. Example: testing a programmable logic controller (PLC) input module on a test bench, apart from the other control units, helps detect firmware or hardware problems early.
The primary purpose is to detect and correct faults before integration, which reduces troubleshooting complexity during full system testing. The step confirms that each unit complies with design parameters and operational requirements, improving overall system reliability.
Unit testing covers hardware components such as relays, sensors and circuit breakers, and software modules such as control algorithms and communication settings. It excludes system-wide interactions, which are tested during integration and system testing.
Unit testing lowers the risk of system failure by ensuring component-level reliability. It also shortens commissioning time, reduces the cost of repairs after installation, and improves safety by verifying protective devices before the system is energised.
When a contractor upgrades a substation or a motor control centre, unit testing confirms that each automation relay and control panel module operates correctly before any high-voltage or high-power equipment is energised.
Compliance with regulations and standards is vital when conducting unit tests, to guarantee safety, interoperability and quality. Electrical engineers in Kenya align their testing practice with recognised international standards, manufacturer requirements and national standards. Requirements for a unit test come from three sources, and a competent technician uses them together:
Testing parameters define the criteria and conditions under which unit tests are conducted. They ensure that each component's performance is measured against objective standards rather than judged by appearance or assumption.
Key electrical parameters include voltage, current, resistance and insulation level. Measuring these ensures that devices operate within safe limits, preventing overheating or electrical faults. Example: insulation resistance testing of a motor starter before commissioning a borehole pump reveals leakage paths that could later cause tripping or failure.
This parameter verifies that the unit performs its intended control or measurement function correctly. Example: a temperature sensor must detect and transmit readings accurately within its specified range when checked against a reference instrument.
The speed at which a unit reacts to an input signal is critical in automation. Testing response time ensures, for example, that a protective relay trips within the specified milliseconds to safeguard equipment.
Testing communication parameters verifies the integrity of data transmitted between units and the control system. Protocols such as Modbus or Profibus are checked for correct addressing, packet loss and latency during unit testing.
Units are checked against their rated limits for temperature, humidity and vibration to ensure durability. Example: automation equipment installed in a humid coastal plant must be rated for those conditions to prevent corrosion-related failures.
Unit testing follows a systematic procedure to ensure thorough verification and documentation of results. Following the same sequence every time keeps the testing safe, repeatable and auditable.
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter explored the process of commissioning automation systems, beginning with unit testing which involves verifying individual components against standards such as those from OEMS, IEE, and KEBS while measuring key testing parameters through a defined procedure. It then covered functional testing, where the system's operational capabilities are assessed using specific parameters and systematic steps to ensure all functions perform as intended. The chapter proceeded to system integration tests that focus on the interaction between components, guided by OEMS regulations and rigorous testing criteria to confirm seamless operation of the complete system. Maintaining thorough documentation was emphasized for its role in preserving test results and system details, highlighting various types of records necessary for effective management. End user training was addressed as a critical phase to equip operators with the knowledge required to use the automation system safely and efficiently. The chapter concluded with the final inspection and validation stage, which incorporates safety standards, regulatory compliance, and a detailed checklist to verify system readiness. Finally, the handover process was discussed, involving the preparation of handover documentation and securing final acceptance from the end user to formally complete the commissioning.
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Multimeter | Proximity Sensor |
| Test Leads and Jumper Wires | Push Button Switch |
| PLC Module | Indicator Lamp 24V |
| Personal Protective Equipment (Dustcoat, Gloves, Safety Glasses) |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Multimeter | 1 Pc per Candidate |
| 2 | Test Leads and Jumper Wires | Enough per Candidate |
| 3 | PLC Module | 1 Pc per 5 Candidates |
| 4 | Proximity Sensor | 1 Pc per Candidate |
| 5 | Push Button Switch | 1 Pc per Candidate |
| 6 | Indicator Lamp 24V | 1 Pc per Candidate |
| 7 | Personal Protective Equipment (Dustcoat, Gloves, Safety Glasses) | 1 Set per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Conduct Unit Testing on Automation Components | |||
| Wore Personal Protective Equipment (Dustcoat, Gloves, Safety Glasses) (Award 1 mark for correct PPE usage or zero) | 1 | ||
| Prepared clean and safe working area ensuring good housekeeping (Award 1 mark for good housekeeping or zero) | 1 | ||
| Selected and correctly used appropriate tools (Multimeter, Test Leads, Jumper Wires) (Award 1 mark for correct tool use or zero) | 1 | ||
| Identified and labelled each automation component correctly (Proximity Sensor, Push Button, Indicator Lamp) (Award 1 mark per correctly labelled component or zero) | 3 | ||
| Followed correct procedure for unit testing the proximity sensor including voltage and output response (Award marks based on adherence to procedure steps, 5 marks total) | 5 | ||
| Performed unit test on push button switch verifying contact continuity and function (Award marks based on correct testing steps and results, 4 marks total) | 4 | ||
| Tested indicator lamp 24V for correct illumination under test conditions (Award marks for correct wiring and function test, 3 marks total) | 3 | ||
| Sub-Total | 18 | ||
| PRODUCT CHECKLIST | |||
| Unit test report showing correct identification, test parameters, and results for proximity sensor, push button switch, and indicator lamp (Award marks for completeness, accuracy, and clarity of test results) | 7 | ||
| Automation components correctly labelled and connected for testing with no wiring faults (Award marks for neat, correct wiring and labelling) | 5 | ||
| Test results conform to specified test parameters: proximity sensor switching distance 10-15 mm, push button continuity without bounce, indicator lamp illumination at 24V (Award marks for meeting all specified testing parameters) | 5 | ||
| Sub-Total | 17 | ||
| GRAND TOTAL | 35 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Multimeter | PLC Module |
| Insulated Pliers | 9V Bulbs |
| Jumper Wires | Bulb Holders |
| IEC Standard Wiring Colour Code Chart | Personal Protective Equipment (Safety gloves, Helmet, Dustcoat) |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Personal Protective Equipment (Safety gloves, Helmet, Dustcoat) | 1 set per Candidate |
| 2 | Multimeter | 1 Pc per Candidate |
| 3 | PLC Module | 1 Pc per 5 Candidates |
| 4 | Jumper Wires (male to male and male to female) | Enough per Candidate |
| 5 | 9V Bulbs | 3 Pcs per Candidate |
| 6 | Bulb Holders | 3 Pcs per Candidate |
| 7 | Insulated Pliers | 1 Pc per Candidate |
| 8 | IEC Standard Wiring Colour Code Chart | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Observance of Safety and Preparation for Unit Testing | |||
| Wore Personal Protective Equipment (Safety gloves, Helmet, Dustcoat) (Award 1 mark for correct and full PPE use or zero) | 1 | ||
| Ensured clean and safe working area before starting the unit test (Award 1 mark for clean working area or zero) | 1 | ||
| Used insulated pliers and multimeter correctly during testing (Award 1 mark for correct tool use or zero) | 1 | ||
| Sub-Total | 3 | ||
| TASK 2: Compliance with OEMS, IEE, and KEBS Standards During Unit Testing | |||
| Labelled control inputs and outputs correctly as A, B, C, X, Y, Z (Award 1 mark for each correctly labelled input/output or zero) | 6 | ||
| Observed correct IEC wiring colour codes for all cables (Award 1 mark for full compliance or zero) | 1 | ||
| Terminated cables correctly at bulb holders and bulbs (Award 1 mark for each correctly terminated bulb cable or zero) | 3 | ||
| Ensured correct wiring connections at bulbs and bulb holders (Award 1 mark for each correct wiring connection or zero) | 3 | ||
| Simulated and tested PLC program outputs: Output X for no inputs, Output Y for inputs A and B, Output Z for inputs A, B, and C (Award 3 marks each for correct output simulation or zero) | 9 | ||
| Sub-Total | 22 | ||
| PRODUCT CHECKLIST | |||
| Finished unit test results comply with OEMS, IEE, and KEBS standards including correct labelling, wiring colour codes, terminations, and functional PLC outputs (Award up to 10 marks based on completeness and compliance) | 10 | ||
| Sub-Total | 10 | ||
| GRAND TOTAL | 35 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.