By the end of this chapter, you will be able to:
Mastering these skills ensures your work is accurate and reliable, which is essential for building safe and successful structures in the real world.
Compiled by: John Wachira
Site clearance works are all the activities carried out to prepare a plot for construction by removing everything that would obstruct or endanger the new works, including vegetation, trees and stumps, rubbish, old structures, unwanted services and the topsoil over the building area. Proper clearance gives a safe, open and level site for setting out, excavation and storage, prevents organic material and debris from weakening foundations, and reduces hazards such as hidden pits, snakes and fire. In practice, the site is first surveyed and demarcated, permits are obtained, services are located and disconnected, and clearance then proceeds manually or with machines, followed by safe disposal of the cleared material. Example: before construction of a new dormitory at a secondary school in Kitui, the contractor fenced the site, removed bush and three dead trees, demolished an old pit latrine after filling it with lime and soil, stripped 200 mm of topsoil and stockpiled it for later landscaping of the school compound.
| Name | Specification | Use |
|---|---|---|
| Panga (machete) and slasher | Steel blades about 450 mm to 600 mm | Cutting grass, bush and small shrubs |
| Jembe, mattock and pickaxe | Steel heads on wooden handles | Grubbing up roots, stumps and hard ground |
| Axe and chainsaw | Axe head about 1.5 kg to 2.5 kg; petrol chainsaw with 350 mm to 500 mm bar | Felling trees and cutting trunks and branches |
| Rake, shovel and wheelbarrow | Standard steel tools, wheelbarrow about 65 L to 85 L | Collecting and moving cut vegetation and debris |
| Bulldozer | Tracked machine with front blade and rear ripper | Clearing dense bush, pushing out stumps and stripping topsoil |
| Excavator | Hydraulic excavator with bucket or breaker attachment | Uprooting stumps, demolishing small structures and loading debris |
| Front-end loader and tipper trucks | Loader bucket about 1 m³ to 3 m³; trucks 7 m³ to 20 m³ | Loading and carting away debris and surplus soil |
| Brush cutter or mulcher | Motorised cutter or chipper | Shredding vegetation into mulch for reuse |
| Cable and pipe locator | Electronic detector | Locating buried electricity cables and metal pipes before digging |
| Personal protective equipment | Helmets, gloves, boots, goggles, ear defenders, high visibility vests, chainsaw chaps | Protecting workers during clearance |
| Method | How it is done | Suitable for |
|---|---|---|
| Manual clearance | Workers use pangas, jembes, axes and wheelbarrows | Small sites, light vegetation, areas near existing buildings and sensitive areas |
| Mechanical clearance | Bulldozers, excavators, loaders and trucks | Large sites, dense bush, large trees, demolition and topsoil stripping |
| Chemical clearance | Approved herbicides applied to vegetation or stumps | Persistent weeds and regrowth, used only with approved products and care for the environment |
| Combined clearance | Machines for bulk work, hand labour for edges and around retained features | Most medium and large building sites |
Example: a site for a SACCO office in Nyeri measures 40 m by 25 m. Topsoil 150 mm deep is to be stripped, it bulks by 25% when excavated, and surplus topsoil will be carted away in 10 m³ trucks at Ksh 4,500 per load.
Area to strip = Length × Width
Area = 40 m × 25 m
Area = 1,000 m²
Volume of topsoil = Area × Depth
Volume = 1,000 m² × 0.15 m
Volume = 150 m³
Bulked volume = Volume × 1.25
Bulked volume = 150 m³ × 1.25
Bulked volume = 187.5 m³
Number of truck loads = Bulked volume ÷ Truck capacity (rounded up)
Number of truck loads = 187.5 m³ ÷ 10 m³
Number of truck loads = 18.75, rounded up to 19 loads
Cost of carting away = Number of loads × Cost per load
Cost = 19 × Ksh 4,500
Cost = Ksh 85,500
Create a free account to open more of this chapter.
Free: practical guides, quick cards, workplace scenarios and more.
Create a free accountThis chapter covered essential aspects of performing earthworks, beginning with the interpretation and use of earthwork working drawings to guide site operations accurately. It examined the processes involved in site clearance works, ensuring the area is prepared for subsequent earthmoving activities. The role of cross sections in measuring and planning earthworks was explained to facilitate precise volume calculations. The removal of topsoil was addressed as a critical step to preserve fertile material and prepare the site for construction. Excavation to the required formation or reduced level was detailed, focusing on achieving the specified depth and accuracy. The formation of embankments according to design drawings was discussed to ensure structural stability. Compaction techniques at the formation level were emphasized to enhance soil strength and prevent future settlement. Finally, the chapter highlighted the proper disposal of excess earthwork material to maintain environmental compliance and site safety.
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Measuring tape (30 meters) | Earthwork working drawing (A3 size) |
| Scale ruler (metric) | Field book |
| Pencil | Graph paper (A4 size) |
| Eraser | |
| Calculator |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Earthwork working drawing (A3 size) | 1 per Candidate |
| 2 | Measuring tape (30 meters) | 1 per Candidate |
| 3 | Scale ruler (metric) | 1 per Candidate |
| 4 | Pencil | 1 per Candidate |
| 5 | Eraser | 1 per Candidate |
| 6 | Calculator | 1 per Candidate |
| 7 | Field book | 1 per Candidate |
| 8 | Graph paper (A4 size) | 1 per Candidate |
| 9 | Safety boots | 1 pair per Candidate |
| 10 | Dust coat/overall | 1 per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Interpretation and Site Preparation Planning | |||
| Wore Personal Protective Equipment (safety boots, dust coat/overall) (Award 1 mark for each PPE donned as per workplace procedures) | 3 | ||
| Identified and interpreted key features on the earthwork working drawing (cut and fill areas, spot levels, slopes) (Award marks for correctly identifying all key features) | 8 | ||
| Measured and scaled distances and dimensions from the drawing accurately using scale ruler (Award marks for accuracy within ±5mm on scale measurements) | 7 | ||
| Calculated cut and fill volumes using the given spot levels and site dimensions (Award marks for correct calculation method and results) | 10 | ||
| Recorded all measurements and calculations neatly and accurately in the field book (Award marks for neatness, completeness and accuracy) | 4 | ||
| Prepared a written report summarizing the earthwork quantities and site preparation recommendations (Award marks for clarity, completeness and correct interpretation) | 8 | ||
| Sub-Total | 40 | ||
| PRODUCT CHECKLIST | |||
| Accurate interpretation of earthwork working drawing dimensions (50m length, 30m width) (Award 4 marks for correct dimension interpretation) | 4 | ||
| Correct calculation of cut volume (within ±5% tolerance) (Award 6 marks for correct cut volume calculation) | 6 | ||
| Correct calculation of fill volume (within ±5% tolerance) (Award 6 marks for correct fill volume calculation) | 6 | ||
| Complete and legible site report including all required details (Award 4 marks for completeness and legibility) | 4 | ||
| Sub-Total | 20 | ||
| GRAND TOTAL | 60 | ||
Type: Individual
| Tools & Equipment | Materials |
|---|---|
| Panga | |
| Shovel | |
| Wheelbarrow | |
| Rake | |
| Measuring tape (10 meters) | |
| Marking paint/chalk | |
| Tarpaulin sheet | |
| Pencil | |
| Eraser | |
| Calculator |
| S/N | Item | Quantity |
|---|---|---|
| 1 | Safety boots | 1 Pair per Candidate |
| 2 | Dust coat/Overall | 1 Pc per Candidate |
| 3 | Gloves | 1 Pair per Candidate |
| 4 | Panga | 1 Pc per Candidate |
| 5 | Shovel | 1 Pc per Candidate |
| 6 | Wheelbarrow | 1 Pc per 5 Candidates |
| 7 | Rake | 1 Pc per Candidate |
| 8 | Measuring tape (10 meters) | 1 Pc per Candidate |
| 9 | Marking paint/chalk | 1 Pc per Candidate |
| 10 | Tarpaulin sheet | 1 Pc per Candidate |
| 11 | Field book | 1 Pc per Candidate |
| 12 | Pencil | 1 Pc per Candidate |
| 13 | Eraser | 1 Pc per Candidate |
| 14 | Calculator | 1 Pc per Candidate |
| Items to be Evaluated | Marks Available | Marks Obtained | Comments |
|---|---|---|---|
| TASK 1: Site Clearance and Topsoil Stripping | |||
| Wore Personal Protective Equipment including safety boots, dust coat, and gloves (Award 1 mark for each PPE donned as per workplace procedures) | 3 | ||
| Cleared the working area free from all vegetation and debris within the 10m x 10m site (Award 2 marks for clearing vegetation, 2 marks for debris removal, and 2 marks for general tidiness) | 6 | ||
| Measured and marked the 10m by 10m site boundaries accurately using measuring tape and marking paint (Award 1 mark for each correct boundary marking) | 4 | ||
| Stripped topsoil uniformly to a depth of 150mm using shovel and wheelbarrow to transport stripped soil (Award 3 marks for correct depth, 2 marks for uniformity, and 2 marks for proper disposal using wheelbarrow and tarpaulin) | 7 | ||
| Collected and stacked stripped topsoil neatly on tarpaulin sheet outside the cleared area (Award 3 marks for neat stacking and correct location) | 3 | ||
| Used rake to level the stripped area ensuring removal of roots and small debris (Award 3 marks for thorough raking and leveling) | 3 | ||
| Recorded measurements and observations accurately in the field book (Award 2 marks for correct site dimensions and 2 marks for depth recording) | 4 | ||
| Cleaned and stored tools properly after completion of the task (Award 3 marks for proper cleaning and storage) | 3 | ||
| Maintained safety and hygiene throughout the task execution (Award 2 marks for safe and hygienic working practices) | 2 | ||
| Sub-Total | 35 | ||
| PRODUCT CHECKLIST | |||
| Site cleared of all vegetation and debris within 10m x 10m boundary (Award 5 marks for complete clearance as per specification) | 5 | ||
| Topsoil stripped uniformly to 150mm depth across entire site (Award 7 marks for uniform depth and clean stripping) | 7 | ||
| Stripped topsoil stacked neatly on tarpaulin sheet outside cleared area (Award 3 marks for neat stacking and correct location) | 3 | ||
| Site boundaries clearly marked and measurements accurate within ±50mm (Award 5 marks for accurate site layout) | 5 | ||
| Overall site ready for subsequent earthworks as per specifications (Award 5 marks for readiness and compliance to specifications) | 5 | ||
| Sub-Total | 25 | ||
| GRAND TOTAL | 60 | ||
At the start of this chapter we promised you would be able to:
Tick each one you can genuinely do.
So, are you there yet?
You're competent when you can confidently do 50% or more of what this chapter promised.
Sign in to record how you're doing.