Architecture  ·  Level 6
Building Construction Technology Principles
Chapter 3: Apply Construction superstructure work principles
📚 5 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • Identify different types of building walls correctly using construction principles.
  • Install building openings accurately to meet work specifications.
  • Carry out building concreting tasks correctly following all work requirements.
  • Install roof construction elements properly to ensure they meet job standards.

These skills are essential for creating strong, safe, and reliable buildings in the construction trade.

Construction superstructure work is a critical phase in architectural projects, involving the erection of the above-ground components that define the building’s shape, function, and durability. In Kenya, architects must carefully select walling systems that respond to local climate, material availability, and structural requirements, ensuring safety and aesthetics. Understanding the types of building walls is essential for designing structures that comply with national building codes and meet client expectations. This chapter explores the various walling types used in Kenya’s architectural practice, focusing on load-bearing walls, non-load-bearing walls, and curtain walls.

3.1 Building Walling Types

3.1.1 Load-Bearing Walls

Load-bearing walls are fundamental elements in many Kenyan buildings, particularly in residential and low-rise commercial structures. These walls carry and transfer structural loads from the roof and upper floors down to the foundation, thus playing a crucial role in the building’s stability.

Structural Role of Load-Bearing Walls

Load-bearing walls support vertical loads such as the weight of floors, roofs, and live loads including occupants and furniture. They must be designed to resist both compressive forces and lateral forces such as wind or seismic activity. In Nairobi’s medium-density housing, for example, load-bearing walls made of reinforced concrete blocks provide the necessary strength while optimizing construction costs.

Materials Used in Load-Bearing Walls

Common materials include concrete blocks, fired clay bricks, and stone masonry. Concrete blocks are favored in Kenya for their uniformity, strength, and ease of installation, allowing faster construction. Stone masonry is often used in rural settings where stone is abundant, offering durability but requiring skilled labor.

Design Considerations and Dimensions

Load-bearing walls require adequate thickness to support imposed loads; typical dimensions range from 150mm to 230mm depending on the height and load. Architects must consider wall length, height, and openings such as doors and windows, ensuring lintels or arches are incorporated to redistribute loads around these voids. In educational institutions like public schools, proper dimensioning prevents structural failures and enhances longevity.

Advantages and Limitations

Load-bearing walls reduce the need for complex frames, lowering overall construction costs. However, they limit architectural flexibility because wall positions dictate room layouts and future modifications can be difficult. This is why high-rise buildings in Nairobi use frame structures instead, reserving load-bearing walls for smaller projects.

3.1.2 Non Load-Bearing Walls

Non load-bearing walls are primarily used to partition internal spaces and do not carry structural loads except their own weight. They allow greater flexibility in interior design, which is particularly valuable in commercial and institutional buildings where space usage changes over time.

Functions of Non Load-Bearing Walls

These walls provide privacy, sound insulation, and fire separation between rooms without supporting floors or roofs. In hospitals, non load-bearing walls often separate wards and offices, enabling easy reconfiguration as patient needs evolve.

Materials Commonly Employed

Lightweight materials such as gypsum boards on metal studs, timber panels, and hollow concrete blocks are typical. Gypsum board walls are common in Nairobi office buildings due to their smooth finish and ease of installation, while timber panels are used in rural clinics for cost-effectiveness.

Installation and Structural Support

Non load-bearing walls require attachment to the main structural frame or load-bearing walls for stability. Proper fixing methods prevent movement and ensure durability. For instance, in a county government office, metal stud walls are anchored to reinforced concrete columns and beams for rigidity.

Benefits and Constraints

The main advantage is adaptability, allowing spaces to be changed without affecting the building’s structural integrity. However, these walls offer limited resistance to impact and require maintenance to prevent damage. Acoustic performance can also be a challenge, necessitating additional insulation in noisy environments like schools.

3.1.3 Curtain Walls

Curtain walls are non-structural external cladding systems that hang from the building frame, providing weather protection and aesthetic appeal. Their use in Kenya’s urban commercial towers and institutional buildings is increasing due to modern architectural trends.

Definition and Purpose of Curtain Walls

Curtain walls do not carry any load from the building other than their own weight and environmental forces such as wind. They form the building envelope, preventing water ingress and allowing natural light, which improves occupant comfort in office blocks and hotels.

Types of Curtain Wall Systems

Common types include stick systems, unitized systems, and structural glazing. Stick systems involve assembling mullions and transoms on site, suitable for large projects like Nairobi’s high-rise hotels. Unitized systems are pre-fabricated panels installed quickly, reducing construction time in university buildings. Structural glazing uses glass bonded to frames for sleek façades seen in commercial banks.

Materials and Components

Curtain walls typically combine aluminum frames, glass panels, and sealants. Aluminum’s corrosion resistance suits Kenya’s varying climates, while double-glazed glass improves thermal insulation. Sealants prevent water penetration and accommodate thermal expansion, critical for durability in coastal cities like Mombasa.

Performance and Maintenance

Curtain walls enhance energy efficiency by controlling solar gain and reducing heat loss. Regular maintenance includes cleaning glass surfaces and inspecting seals to prevent leaks. In Nairobi’s commercial buildings, maintenance contracts ensure façade integrity and preserve the building’s visual appeal.

Practice Questions

  1. Explain the structural role of load-bearing walls and discuss the materials commonly used for their construction in Kenya. (10 marks)
  2. Compare and contrast non load-bearing walls and load-bearing walls in terms of function and material use. (10 marks)
  3. Describe the types of curtain wall systems and their suitability for different building projects in Kenya. (10 marks)
  4. Discuss the advantages and limitations of using load-bearing walls in medium-rise buildings. (10 marks)
The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒3.2 Building openings installation

In architectural construction, the installation of building openings such as doors, windows, and arches is critical to the structural integrity, functionality, and aesthetic appeal of a building. In the Kenyan context, where climatic conditions and security co…

🔒3.3 Building Concreting Works

In architectural construction projects across Kenya, concreting forms the backbone of durable and safe superstructures. Proper execution of concreting works ensures structural integrity, longevity, and compliance with design specifications. Whether constructin…

🔒3.4 Concreting areas

In architectural construction, concreting is a fundamental activity that shapes the durability, strength, and usability of a building’s superstructure. In Kenya, the quality of concreting directly affects the longevity of structures, given the local climatic c…

🔒3.5 Roof construction elements

Roof construction is a crucial aspect of architectural design and building construction in Kenya, particularly due to the varied climatic conditions across regions. The roof protects the building from weather elements, supports structural loads, and contribute…

Chapter Summary

This chapter explored the principles of construction superstructure work, beginning with various building walling types including load-bearing walls, non load bearing walls, and curtain walls, each serving distinct structural and aesthetic functions. It then examined the installation of building openings such as doors, windows, and arches, highlighting their importance in access, ventilation, and architectural design. The chapter provided a detailed overview of building concreting works, covering key processes like batching by weight and volume, manual and mechanical mixing, placing, compacting, and curing to ensure durable concrete structures. Different concreting areas were discussed, focusing on foundations, beams, slabs, columns, and retaining walls, each requiring specific concreting techniques. Roof construction elements were also covered extensively, addressing timber and steel sections, roofing coverings and materials, as well as framing methods. Finally, the chapter emphasized the role of insulation, ventilation, and flashing in protecting the roof and enhancing building performance. Together, these topics provide a comprehensive foundation for understanding and applying superstructure construction principles effectively.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

A. Written Assessment

  1. Which of the following wall types primarily supports structural loads in a building?
    a) Non load-bearing walls
    b) Curtain walls
    c) Load-bearing walls
    d) Partition walls
    (2 marks)

  2. Describe two key differences between load-bearing walls and non load-bearing walls in building construction. (4 marks)

🔒20 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Explain the main structural difference between load-bearing walls and non-load bearing walls in building construction. (4 marks)
  2. Describe two advantages of using curtain walls in modern Kenyan commercial buildings. (4 marks)
🔒21 more in this section.

Chapter Practical Activities

Practical 1: Construct a load-bearing wall 4000mm x 300mm x 2400mm high

Architecture · Level 6
Building Construction Technology Principles
PRACTICAL ASSESSMENT
TIME: 5 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Construct a load-bearing wall 4000mm long, 300mm thick, and 2400mm high as per the provided working drawing.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
TrowelCement
Spirit levelSand
Plumb bobAggregate
Tape measureConcrete blocks
Mason's hammerWater
Brick jointerBinding wire
WheelbarrowTimber for supports
Shovel
Bucket
2400mm300mmELEVATION4000mm300mmSECTION A-AConstruct a load-bearing wall…2400 x 300 x 4000 mmNTS
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Cement bags1 bag per 3 Candidates
2Sand (sharp, clean)0.03 m3 per Candidate
3Aggregate (10mm)0.04 m3 per Candidate
4Concrete blocks (440mm x 215mm x 100mm)70 Pcs per Candidate
5Masonry nails30 Pcs per Candidate
6Binding wire10 meters per Candidate
7WaterAdequate quantity per Candidate
8Timber for scaffolding and supports2.5 m x 0.1 m x 0.05 m per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Preparation and Setting Out
Wore correct PPE: overall, safety boots, gloves
(Award 1 mark each or zero x3 = 3 Marks)
3
Measured and marked wall length of 4000mm on foundation
(Award 2 marks or zero)
2
Measured and marked wall thickness of 300mm accurately
(Award 2 marks or zero)
2
Set out plumb lines and levels using plumb bob and spirit level
(Award 3 marks or zero)
3
Sub-Total10
TASK 2: Wall Construction
Prepared mortar mix (cement:sand ratio 1:6) correctly
(Award 3 marks or zero)
3
Laid concrete blocks in stretcher bond with uniform 10mm joints
(Award 4 marks or zero)
4
Ensured wall thickness maintained at 300mm throughout
(Award 3 marks or zero)
3
Used binding wire to tie blocks as per specification
(Award 2 marks or zero)
2
Maintained wall height of 2400mm as per drawing
(Award 3 marks or zero)
3
Cleaned excess mortar from joints and surface
(Award 2 marks or zero)
2
Sub-Total17
TASK 3: Finishing and Quality Checks
Checked verticality with plumb bob and corrected deviations
(Award 3 marks or zero)
3
Checked horizontal level of wall courses with spirit level
(Award 3 marks or zero)
3
Ensured uniform joint thickness and neat finishing
(Award 3 marks or zero)
3
Removed all debris and cleaned work area
(Award 2 marks or zero)
2
Sub-Total11
PRODUCT CHECKLIST
Wall length is 4000mm ±10mm
(Award 3 marks or zero)
3
Wall thickness is uniform at 300mm ±5mm
(Award 3 marks or zero)
3
Wall height is 2400mm ±10mm
(Award 3 marks or zero)
3
Wall is plumb within 5mm deviation
(Award 3 marks or zero)
3
Wall courses are level and joints are uniform at 10mm ±2mm
(Award 3 marks or zero)
3
Wall surface is clean with no mortar droppings
(Award 2 marks or zero)
2
Sub-Total17
GRAND TOTAL55
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)

Practical 2: Construct a non load-bearing wall 4000mm x 300mm x 2400mm high

Architecture · Level 6
Building Construction Technology Principles
PRACTICAL ASSESSMENT
TIME: 5 HOURS
⬇ PDFCandidate Instructions (Candidate Tool)

Type: Individual

INSTRUCTIONS TO CANDIDATE:
1.  You are required to perform the following task:
i.  Construct a non load-bearing internal wall 4000mm long, 300mm thick, and 2400mm high as per the provided working drawing.
2.  You have been provided with the following resources for the practical task:
Tools & EquipmentMaterials
TrowelCement
Spirit levelSand
HammerConcrete blocks
Tape measureWater
Mason's lineWall ties
Plumb bobBinding wire
BucketTimber for support
HoePlastic sheeting
2400mm300mmELEVATION4000mm300mmSECTION A-AConstruct a non load-bearing w…2400 x 300 x 4000 mmNTS
⬇ PDFResources Required (Cutting List)
S/NItemQuantity
1Cement bags1 bag per 3 Candidates
2Sand (fine)0.1 m3 per Candidate
3Concrete blocks 440mm x 215mm x 100mm40 Pcs per Candidate
4Water5 litres per Candidate
5Wall ties20 Pcs per Candidate
6Masonry nails10 Pcs per Candidate
7Binding wire1 roll per 5 Candidates
8Timber for temporary support2 lengths of 2.5m per Candidate
9Plastic sheeting (for curing)1 sheet 3m x 2m per Candidate
⬇ PDFAssessor Guide
Items to be EvaluatedMarks AvailableMarks ObtainedComments
TASK 1: Preparation and Safety
Wore correct PPE: overall, safety boots, gloves
(Award 1 mark each or zero x 3 = 3 Marks)
3
Checked and prepared mortar mix according to standard ratio
(Award 4 marks for correct mix or zero)
4
Set out wall dimensions on foundation using tape measure and mason’s line
(Award 5 marks for accuracy or zero)
5
Sub-Total12
TASK 2: Wall Construction
Laid first course of blocks with mortar, ensuring level and alignment
(Award 5 marks for accuracy or zero)
5
Maintained proper mortar joint thickness of 10mm throughout
(Award 4 marks for consistency or zero)
4
Used wall ties and binding wire correctly at 900mm vertical spacing
(Award 3 marks or zero)
3
Ensured verticality using plumb bob and spirit level after every 3 courses
(Award 4 marks or zero)
4
Completed wall to specified height of 2400mm
(Award 2 marks or zero)
2
Sub-Total18
TASK 3: Finishing and Curing
Removed excess mortar and ensured neat joints
(Award 3 marks or zero)
3
Applied curing by covering wall with plastic sheeting for 7 days
(Award 4 marks or zero)
4
Cleaned work area and disposed of waste properly
(Award 3 marks or zero)
3
Sub-Total10
PRODUCT CHECKLIST
Wall length is 4000mm ±10mm
(Award 3 marks for correct dimension or zero)
3
Wall thickness is 300mm ±5mm
(Award 3 marks for correct dimension or zero)
3
Wall height is 2400mm ±10mm
(Award 3 marks for correct dimension or zero)
3
Wall is plumb and level throughout
(Award 4 marks for plumb and level or zero)
4
Mortar joints are uniform and neat
(Award 3 marks for neat joints or zero)
3
Wall is stable with proper bonding and wall ties
(Award 4 marks for stability and bonding or zero)
4
Wall shows evidence of proper curing
(Award 3 marks for curing or zero)
3
Sub-Total23
GRAND TOTAL63
ASSESSMENT OUTCOME:   ☐ Competent    ☐ Not Yet Competent (competent if at least 50%)
🔒

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒Installation of Curtain Wall Panel System 3000mm x 2400mmPractical 3
🔒Install timber door and window frames into brick wall openingsPractical 4
🔒Construct a semicircular masonry arch 1200mm span and 300mm risePractical 5
🔒Batch and weigh concrete materials for a 1m³ mixPractical 6
🔒Manual and Mechanical Concrete Mixing for a 1m³ MixPractical 7
🔒Place and compact concrete for a reinforced concrete slab 4000mm x 3000mm x 150mmPractical 8
🔒Cure a concrete slab 3500mm x 2500mm x 150mm correctlyPractical 9
🔒Construct a reinforced concrete foundation strip 5000mm x 300mm x 450mmPractical 10
🔒Construct a reinforced concrete beam 4000mm x 300mm x 500mmPractical 11
🔒Construct a reinforced concrete slab 4000mm x 3000mm x 150mm thickPractical 12
🔒Construct reinforced concrete column 300mm x 300mm x 1800mm highPractical 13
🔒Construct a reinforced concrete retaining wall 4000mm long x 1000mm high x 300mm thickPractical 14
🔒Erect timber and steel roof framing and install corrugated iron sheet roofing coveringPractical 15
🔒Install roof insulation, ventilation and flashing for a residential building roofPractical 16
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 16 questions Start quiz ▾
0%
0 / 2
🔒

14 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Identify different types of building walls correctly using construction principles.
  • Install building openings accurately to meet work specifications.
  • Carry out building concreting tasks correctly following all work requirements.
  • Install roof construction elements properly to ensure they meet job standards.

Tick each one you can genuinely do.

So, are you there yet?

You're competent when you can confidently do 50% or more of what this chapter promised.

Sign in to record how you're doing.