Accountancy  ·  Level 6
Quantitative Techniques
Chapter 6: Analyse project networks
📚 5 Topics
⚑ What you will be able to do

By the end of this chapter, you will be able to:

  • Analyze project networks accurately by applying the correct network rules.
  • Identify and determine network rules correctly according to established guidelines.
  • Construct network analyses accurately while following all necessary network rules.
  • Determine the project’s critical path and overall duration correctly using network rules.

Mastering these skills will help you plan and manage projects efficiently, ensuring successful and timely completion in your future trade work.

Project networks are essential quantitative tools that enable accountancy professionals to plan, schedule, and control projects effectively, especially in environments where multiple interdependent activities must be coordinated. In Kenya, where diverse projects from financial audits to system implementations require precise time and resource management, mastering project network analysis enhances decision-making and optimises project outcomes. This chapter focuses on the fundamental terms used in project networks, laying the groundwork for understanding complex project scheduling and control techniques.

6.1 Meaning of terms

Project networks rely on a set of core terms and concepts that describe the structure, timing, and dependencies of project activities. Understanding these terms is critical for accountants tasked with budgeting, forecasting, and monitoring project progress to ensure timely delivery within cost constraints.

6.1.1 Activity

An activity in project networks represents a distinct task or work element that must be completed as part of the overall project. Activities consume time and resources and are the building blocks of the project schedule.

Definition and Characteristics

  • An activity has a defined start and finish point.
  • It requires resources such as labour, materials, or capital.
  • Activities can be sequential or parallel depending on project requirements.
  • Each activity has a duration, which is the estimated time needed for completion.
  • Activities are linked by dependencies that determine the order of execution.

Worked Examples

Example 1: A bank plans to implement a new accounting software system. One activity is "Data Migration" estimated to take 5 days.

Given: Duration = 5 days

Calculate the time required to complete the activity:

Answer: The activity "Data Migration" requires 5 days.

Example 2: In a retail business expansion, the activity "Inventory Setup" takes 3 days, followed by "Staff Training" which takes 4 days. Both are sequential.

Calculate the total duration for both activities.

Step 1: Add durations: 3 days + 4 days

Step 2: Total duration = 7 days

Answer: Total duration for both activities is 7 days.

Example 3: For a cooperative's financial audit, activities "Document Collection" and "Preliminary Review" are done in parallel, taking 2 and 3 days respectively.

Calculate the project duration for these parallel activities.

Step 1: Identify the longer duration: max(2,3) = 3 days

Answer: The parallel activities take 3 days to complete.

6.1.2 Event (Node)

An event or node in project networks signifies a point in time marking the start or completion of one or more activities. Events themselves consume no time or resources but represent milestones in the project timeline.

Definition and Properties

  • Events represent the start or end of one or more activities.
  • They act as connectors between activities in network diagrams.
  • Events have no duration or resource consumption.
  • They are used to track progress and dependencies.
  • Each event is uniquely identified, often by numbering.

Worked Examples

Example 1: In a SACCO loan processing project, event 1 marks the start of "Application Verification" and event 2 marks its completion.

Given: Activity duration between event 1 and 2 is 4 days.

Calculate the duration between events.

Answer: Duration between event 1 and 2 is 4 days.

Example 2: A county government office project has event 3 as the completion of "Budget Approval" and event 4 as the start of "Procurement".

Given: No activity duration between event 3 and 4 (events occur consecutively).

Calculate activity duration.

Step 1: Duration = 0 (events only mark milestones)

Answer: No duration; events mark transition points.

Example 3: In a hotel renovation, event 5 marks start of "Electrical Works" and event 6 marks start of "Interior Painting". If "Electrical Works" takes 6 days, find the duration between events 5 and 6.

Given: Activity duration = 6 days

Answer: Duration between event 5 and 6 is 6 days.

6.1.3 Critical Path

The critical path is the longest sequence of activities in a project network that determines the shortest possible project duration. Delays on the critical path directly delay the entire project.

Definition and Identification

  • The critical path is the longest-duration path through the network.
  • Activities on this path have zero slack or float.
  • It determines the minimum completion time for the project.
  • Identifying the critical path helps prioritize resource allocation.
  • Any delay on the critical path delays project completion.

Worked Examples

Example 1: A retail store refurbishment has activities with durations: A=4 days, B=3 days, C=5 days. Paths: A-B (7 days), C alone (5 days).

Find the critical path.

Step 1: Calculate path durations: A + B = 4 + 3 = 7 days; C = 5 days

Step 2: Critical path = longest path = 7 days (A-B)

Answer: Critical path is A-B with 7 days duration.

Example 2: In a university audit project, paths are:

  • Path 1: Activities D (3 days), E (4 days), F (2 days) total 9 days

  • Path 2: Activities G (5 days), H (3 days) total 8 days

Determine the critical path.

Step 1: Sum durations:

Path 1 = 3 + 4 + 2 = 9 days

Path 2 = 5 + 3 = 8 days

Step 2: Critical path = Path 1

Answer: Critical path is Path 1 with 9 days.

Example 3: For a bank's system upgrade:

  • Path 1: Activities I (2), J (3), K (6) = 11 days

  • Path 2: Activities L (5), M (7) = 12 days

Find critical path and project duration.

Step 1: Calculate path durations:

Path 1 = 2 + 3 + 6 = 11 days

Path 2 = 5 + 7 = 12 days

Step 2: Critical path = Path 2

Answer: Critical path is Path 2 with 12 days duration.

6.1.4 Float (Slack)

Float or slack is the amount of time an activity can be delayed without affecting the overall project completion time. It provides flexibility in scheduling non-critical activities.

Definition and Types

  • Total Float: Maximum delay possible without delaying project finish.
  • Free Float: Delay allowed without delaying successor activities.
  • Float helps identify critical and non-critical activities.
  • Activities on the critical path have zero float.
  • Managing float optimises resource allocation and risk.

Worked Examples

Example 1: A farm project has activity N with duration 4 days, earliest start day 3, latest start day 7.

Calculate total float.

Step 1: Total float = Latest start - Earliest start = 7 - 3 = 4 days

Answer: Total float for activity N is 4 days.

Example 2: In a retail expansion, activity O has earliest finish at day 10 and latest finish at day 12.

Calculate total float.

Step 1: Total float = Latest finish - Earliest finish = 12 - 10 = 2 days

Answer: Total float for activity O is 2 days.

Example 3: A county office project activity P has earliest start 5, earliest finish 9, latest start 5, latest finish 9.

Calculate float.

Step 1: Total float = Latest start - Earliest start = 5 - 5 = 0 days

Answer: Activity P has zero float and is critical.

Practice Questions

  1. A cooperative project has activities with durations: A=3 days, B=5 days, C=4 days. The paths are A-B and C alone. Determine the critical path and project duration. (5 marks)

  2. In a SACCO loan processing, activity "Verification" has earliest start day 2 and latest start day 6. Calculate the total float for the activity. (4 marks)

  3. For an audit project, event 1 marks the start of "Data Collection" and event 2 marks its completion after 7 days. Event 2 leads immediately to "Data Analysis". What is the duration between event 1 and event 2? (3 marks)

  4. A bank's system upgrade project has two paths: Path 1 with activities of 4, 5, and 3 days; Path 2 with activities of 6 and 7 days. Identify the critical path and total project duration. (5 marks)

  5. An activity in a hotel refurbishment project has an earliest finish time of day 12 and a latest finish time of day 15. Calculate its total float. (3 marks)

The rest of this chapter
🔒

Create a free account to open more of this chapter.

Free: practical guides, quick cards, workplace scenarios and more.

Create a free account
🔒6.2 Rules applicable when drawing networks

In project management for accountancy professionals, especially in Kenya, drawing accurate project networks is essential for planning, scheduling, and controlling financial and operational tasks. Project networks visually represent activities and their depende…

🔒6.3 Construction of project network

Construction of a project network is a critical quantitative technique for accountancy professionals managing complex projects in Kenya. It involves organizing activities, their dependencies, and durations into a structured diagram that facilitates scheduling,…

🔒6.4 Critical path and project duration

In accounting-related projects, such as budgeting for an audit engagement or financial system implementation, understanding the critical path and project duration is essential for effective time and resource management. The critical path determines the longest…

🔒6.5 Application of network analysis

Network analysis is a critical quantitative technique used in project management to plan, schedule, and control projects effectively. In the Kenyan accountancy profession, network analysis assists project accountants and financial analysts to determine the opt…

🔒7 Apply calculus

Calculus is a powerful quantitative tool for accountancy professionals in Kenya to analyze changes in financial variables, optimize costs, revenues, and profits, and model continuous growth or decay processes. Calculus techniques such as differentiation and in…

Chapter Summary

This chapter began by defining essential terms used in project network analysis, establishing a clear foundation for understanding the concepts involved. It then outlined the fundamental rules that must be followed when drawing project networks to ensure accuracy and logical sequencing of activities. The construction of project networks was explored in detail, demonstrating how to represent project activities and their dependencies graphically. The chapter explained how to identify the critical path, which determines the minimum project duration and highlights activities that directly affect the completion time. Techniques for calculating project duration were presented, emphasizing the importance of timely project completion. Finally, the chapter discussed practical applications of network analysis in project management and introduced the use of calculus to optimize project scheduling and resource allocation. Together, these topics provide a comprehensive overview of analyzing project networks for effective project control.

Self-Assessment

🔒 PDFDownload this self-assessment, with answers

Written Assessment

  1. A project consists of three activities A, B, and C. Activity A takes 5 days, B takes 8 days, and C takes 6 days. Activity B and C cannot start until A is complete. Calculate the total project duration. (2 marks)

  2. Activity D takes 7 days and must be completed before activities E and F can start. Activity E takes 4 days and activity F takes 5 days. Calculate the critical path and the project duration. (3 marks)

🔒18 more in this section.

Chapter Examination Questions

🔒 PDFDownload these examination questions, with worked answers

SECTION A (40 Marks) - Answer ALL Questions

  1. Explain the term critical path in a project network and why it is important for an accountant managing project budgets. (4 marks)
  2. List four key rules to follow when drawing a project network for a construction project in Nairobi County. (4 marks)
🔒18 more in this section.
Flashcards 20 cards Study deck ▾
Question
1

↻ Tap card to reveal answer
🔒

18 more in this section.

Create a free account
Test Yourself 17 questions Start quiz ▾
0%
0 / 2
🔒

15 more in this section.

Create a free account
Am I competent?

At the start of this chapter we promised you would be able to:

  • Analyze project networks accurately by applying the correct network rules.
  • Identify and determine network rules correctly according to established guidelines.
  • Construct network analyses accurately while following all necessary network rules.
  • Determine the project’s critical path and overall duration correctly using network rules.

Tick each one you can genuinely do.

So, are you there yet?

You're competent when you can confidently do 50% or more of what this chapter promised.

Sign in to record how you're doing.